Permit Information
Permit NumberBLD16-02899
StatusFinaled
Name K2 CONSTRUCTION
Site Address 350 S ALLUMBAUGH WAY
Project NameGrace Memory Care
Customer NumberCUP07-00126
ePlanReviewNo
Description
(MORNINGSTAR MEMORY CARE AT ENGLEFIELD) MODIFICATION TO ADD HVAC SCREENING"" ""MODIFICATION TO INCLUDE CHANGING THE STUCCO SOFFITS TO ALUMINUM WITH TWO LAYERS OF 5/8 TYPE GYPSUM FOR THE ONE HOUR SOFFIT.""Permit for the construction of a new 43,986 sq. ft. memory care building with 50 dwelling/sleeping units, a commercial kitchen, associated dining areas, a theater room, coffee bar and an activity room and two outdoor courtyards per the approved plans and the attached engineering. This building is to be fire sprinklered with a NFPA 13 system with an alarm and shall comply with NFPA 13 and 72 as required by the Boise City Building department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/29/20179/29/20179/29/2017PPASS
DetailsMike Jordan
Ok for perm occ.
DOC - Permit Finaled9/29/20179/29/20179/29/2017PPASS
DetailsMike Jordan
(This activity was added in error so we have changed the case status back to Issued.)
BLD-Final9/28/20179/29/20179/29/2017APASS
DetailsMike Jordan
Late morning - Doug Phone #: ###-####
BLD-Final9/12/20179/13/20179/13/2017APASS
DetailsMike Jordan
Temp Occupancy-Herb Phone #: ###-####. Temp occ granted at this time. Will be ok for perm occ. once zoning and public works has signed perm.occ.
BLD-Final9/13/20179/13/20179/13/2017PCANC
DetailsMike Jordan
FIRE-Final Inspection9/8/20179/11/20179/11/2017APASS
DetailsTroy Cobbley
Life safety passed
BLD-Conference9/7/20179/7/20179/7/2017PPEND
DetailsMike Jordan
Herb Phone #: ###-####. Needs zoning and public works.
FIRE-Final Inspection9/7/20179/7/20179/7/2017PPART
DetailsTroy Cobbley
A temporary for life safety is being given until the project related fire alrm permit has been finaled and the fire dept access signage is provided and NFPA signage at the Oxygen Room door. Herb provided what appears to be compliant hardware for the Kitchen door.

Herb Phone #: ###-####
FIRE-Conference9/6/20179/6/20179/6/2017PDONE
DetailsTroy Cobbley
Performed the rest of the life safety today. I need the project related fire alarm pemit finaled, NFPA signs for the oxygen room, provide fire dept access signage at the south entrance.
FIRE-Conference9/5/20179/5/20179/5/2017PDONE
DetailsTroy Cobbley
Started on life safety this morning. We tested exit signs and emergency lighting. I noted the two Garden area devices did not function. On a afternoon return trip the electrician had repaired the devices. No other items have been inspected yet since the bulk of time has been spent on the project related fire alarm permit.
FIRE-Final Inspection8/31/20179/1/20179/1/2017ACANC
DetailsTroy Cobbley
Herb Phone #: ###-####
BLD-Conference9/1/20179/1/20179/1/2017PNR
DetailsJim Sly
Herb Phone #: ###-####
BLD-Final8/31/20179/1/20179/1/2017PCANC
DetailsBrandon Shaw
Herb Phone #: ###-####
FIRE-Final Inspection8/29/20178/30/20178/30/2017AFAIL
DetailsTroy Cobbley
Todays inspection was just for a conference for the center portion of the building. I noted acouple of smoke detectors with issues.

Herb Phone #: ###-####
FIRE-Conference8/15/20178/16/20178/16/2017ADONE
DetailsTroy Cobbley
Herb, myself and Mike Jordan did a courtesy walk through one the north and south thirds of the building. I noted missing notificaton devices and two strobes overspaced.

Phone #: ###-####
BLD-Conference8/16/20178/16/20178/16/2017PCANC
DetailsMike Jordan
BLD-Conference8/16/20178/16/20178/16/2017APART
DetailsMike Jordan
walk through for final on north and south wings rooms only.
BLD-Energy code compliance7/17/20177/18/20177/18/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Remainder of canlight protection and exterior walls in central great room ok.
FIRE-Conference7/12/20177/12/20177/12/2017ADONE
DetailsKatie Marron
Phone Call with K2 Construction on occupant load signs and how only one per assembly room/space is required.
BLD-Other7/11/20177/11/20177/11/2017PPART
DetailsMike Jordan
Work in progress on providing 2 layers of 5/8 type x rock on can lights in horizontal roof/ceiling assembly.
BLD-Other7/10/20177/11/20177/11/2017ANR
DetailsMike Jordan
fire damping- round 12pm- Herb Phone #: ###-####.
BLD-Framing/Rough-in6/28/20176/28/20176/28/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in6/28/20176/28/20176/28/2017APASS
DetailsMike Jordan
5/8 type x sheet rock wraps for 1hr. protection on columns and beams in central great room.
BLD-Framing/Rough-in6/20/20176/21/20176/21/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in6/20/20176/21/20176/21/2017ACANC
DetailsMike Jordan
BLD-Other6/9/20176/9/20176/9/2017PPART
DetailsBrandon Shaw
Fire proofing // Herb Phone #: ###-####
Can lights in gathering rooms 3&4- two layer
Ceiling @ shower furr outs Rm- 131, 132, 135, 136, 130, & 127- two layers.
BLD-Framing/Rough-in6/7/20176/7/20176/7/2017PCANC
DetailsMike Jordan
BLD-Energy code compliance6/1/20176/1/20176/1/2017PPART
DetailsMike Jordan
Herb Phone #: ###-####
BLD-Framing/Rough-in5/31/20175/31/20175/31/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in5/31/20175/31/20175/31/2017APASS
DetailsMike Jordan
Can lights at south half of building know has 2layers of 5/8type x rock for roof/ceiling assembly, ok. north soffits double layer of 5/8 type x ok.
BLD-Framing/Rough-in5/23/20175/24/20175/24/2017PPART
DetailsMike Jordan
2hr. fire barrier wall at east wing at parpet has been repaired ok. Smoke barrier wall above ceiling ok. Noted the can lights only have 1 layer of 5/8 type x rock around them in roof/ceiling assembly. Two layers are required or an UL listed and approved cover.
BLD-Conference5/23/20175/24/20175/24/2017ACANC
DetailsMike Jordan
BLD-Energy code compliance5/23/20175/24/20175/24/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Rooms 103 to 111 and rooms120 to 123.
BLD-Framing/Rough-in5/24/20175/24/20175/24/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Rooms 103 to 111 and rooms 120 to to123.
BLD-Framing/Rough-in5/10/20175/17/20175/17/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in5/10/20175/17/20175/17/2017APART
DetailsMike Jordan
!hr soffit at east side of building complete and ok. 2hr . fire wall above ceiling east and west wings needs to have penetrations removed at roof deck within the 4ft. Smoke barrier west wing above ceiling needs to firestop sprinkler pipe.
BLD-Framing/Rough-in5/3/20175/10/20175/10/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in5/3/20175/10/20175/10/2017ACANC
DetailsMike Jordan
BLD-Framing/Rough-in5/1/20175/3/20175/3/2017APASS
DetailsMike Jordan
Rated exterior soffits at south and south-east areas of building ok.
BLD-Framing/Rough-in5/2/20175/2/20175/2/2017PPASS
DetailsMike Jordan
Exterior shear walls ok.
BLD-Wall Bracing5/2/20175/2/20175/2/2017PPASS
DetailsMike Jordan
exterior wall bracing ok.
BLD-Framing/Rough-in5/1/20175/2/20175/2/2017ANR
DetailsMike Jordan
BLD-Energy code compliance4/28/20175/1/20175/1/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Rooms 113 to 119 ok.
BLD-Framing/Rough-in4/28/20175/1/20175/1/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Rooms 113 to 119 ok.
BLD-Other4/27/20174/27/20174/27/2017PPASS
DetailsMike Jordan
smoke wall insp// Herb Phone #: ###-####. Smoke barrier, east wing abve ceiling grid ok.
BLD-Framing/Rough-in4/25/20174/26/20174/26/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in4/25/20174/26/20174/26/2017ACANC
DetailsMike Jordan
BLD-Energy code compliance4/24/20174/25/20174/25/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Rooms 127 to 133 ok.
BLD-Framing/Rough-in4/25/20174/25/20174/25/2017APASS
DetailsMike Jordan
Herb Phone #: ###-####. Rooms 127 to 13 ok.
BLD-Framing/Rough-in4/19/20174/20/20174/20/2017PCANC
DetailsMike Jordan
BLD-Framing/Rough-in4/19/20174/20/20174/20/2017ACANC
DetailsMike Jordan
BLD-Framing/Rough-in4/18/20174/19/20174/19/2017PCANC
DetailsMike Jordan
BLD-Energy code compliance4/19/20174/19/20174/19/2017PPASS
DetailsMike Jordan
Exterior walls at south wing and east wing south half.
BLD-Conference4/18/20174/19/20174/19/2017ACANC
DetailsMike Jordan
BLD-Framing/Rough-in4/4/20174/5/20174/5/2017PPART
DetailsMike Jordan
Framing inspection on south wing rooms and east wing rooms,South half. Needs to complete all lateral bracing, nail off all simpson hangars, provide additional studs and squash blocking under 2ply girder bearing. Complete the idividual encasement for 1 hr. protection on columns and complete all fire caulking. Work is still in progress in these areas. All rough ins except for electrical have been completed. Aslo Needs to provide the sheetrock at ceiling in concealed areas for 1hr. roof/ceiling assembly.
BLD-Framing/Rough-in4/5/20174/5/20174/5/2017PPASS
DetailsMike Jordan
Remaining roof nailing completed and ok to cover.
BLD-Framing/Rough-in4/4/20174/5/20174/5/2017ACANC
DetailsMike Jordan
BLD-Framing/Rough-in4/4/20174/4/20174/4/2017PPASS
DetailsMike Jordan
Roof nailing around courtyard #1 ok.
BLD-Wall Bracing4/3/20174/4/20174/4/2017ANR
DetailsMike Jordan
Herb Phone #: ###-####. roof nailing, moved to pm. inspection.
BLD-Other3/8/20173/9/20173/9/2017APASS
DetailsMike Jordan
Roof nailing - Herb Phone #: ###-####. North wing, south side ok to cover.
BLD-Framing/Rough-in3/3/20173/6/20173/6/2017PPASS
DetailsMike Jordan
Herb//this is for shear nailing roof Phone #: ###-####. Roof nailing north wing and north west wing. Nailing edge nailing and nailing on drag trusses ok.
BLD-Footing2/16/20172/17/20172/17/2017APART
DetailsJim Sly
Herb Phone #: ###-####
Thickened footings at slab. OK pending Geotech special inspections, tests and approvals.
BLD-Final2/2/20172/3/20172/3/2017ACANC
DetailsMike Jordan
Herb Phone #: ###-#### **not sure this should be a final. herb said roof, but didn't sound too sure**
BLD-Framing/Rough-in2/3/20172/3/20172/3/2017APASS
DetailsMike Jordan
Herb Phone #: ###-#### **not sure this should be a final. herb said roof, but didn't sound too sure**. Roof nailing ok.
BLD-Framing/Rough-in1/17/20171/17/20171/17/2017PPART
DetailsMike Jordan
Work in progress on roof sheeting.
BLD-Ceiling Grid Inspection1/13/20171/17/20171/17/2017ACANC
DetailsMike Jordan
Herb Phone #: ###-####. Moved to pm.
BLD-Other1/11/20171/12/20171/12/2017PPASS
DetailsMike Jordan
Herb-roof nailing scheduling Phone #: ###-####. South east portion ok.