General Inspection | 2/7/2020 | 2/7/2020 | 2/7/2020 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Michael Zawacki
|
|
|
|
Site Final | 12/16/2019 | 12/23/2019 | 12/23/2019 | A | NR |
Michael Zawacki
|
|
|
DI bags still on 29th across from school.
|
General Inspection | 12/16/2019 | 12/16/2019 | 12/16/2019 | | PASS |
Michael Zawacki
|
|
|
All work looks completed. Scheduled final inspection for 12/23, xmas break.
|
General Inspection | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | | PASS |
Michael Zawacki
|
|
|
Site is stabalized, all exterior completed. OK to final permit when BLD closed.
|
General Inspection | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Michael Zawacki
|
|
|
All disturbance is around 29th and Idaho area. Jeffereson side is completed and stabalized. Disturbed areas have topsoil but not yet landscaped.
|
General Inspection | 7/9/2019 | 7/9/2019 | 7/9/2019 | | PASS |
Andy J. Long
|
|
|
WIP on site improvements. 29th street is closed and gutter, sidewalk, and storm drains have been removed and will replaced. Existing drain at Idaho and Whitewater has protection.
No trackout, discharges, dust or other issues observed on site. Approved.
|
General Inspection | 5/24/2019 | 5/24/2019 | 5/24/2019 | | PASS |
Michael Zawacki
|
|
|
Old school in process of being demoed/repurposed. Perimeter BMPs installed, controlled construction entrances in place. No ESC issues.
|
General Inspection | 4/8/2019 | 4/8/2019 | 4/8/2019 | | PART |
Andy J. Long
|
|
|
New building complete. Crew onsite contracted with BSD to remove portables. RP stated they are causing trachout but will clean it up at end of day.
No sediment runoff around perimter. Gutter on 29th needs sweeping. Maintain all DI bags installed. Need to install DI bag Idaho and Whitewater on SW corner of school site.
|
General Inspection | 2/19/2019 | 2/19/2019 | 2/19/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/4/2019 | 1/4/2019 | 1/7/2019 | | PASS |
Michael Zawacki
|
|
|
Sidewalk has been completed down to WWP Blvd. Site perimeter still needs landscaping. Most paving and concrete work completed, site is contained. No dirt leaving site.
|
General Inspection | 11/19/2018 | 11/19/2018 | 11/20/2018 | | FAIL |
Michael Zawacki
|
|
|
One of the concrete trucks didn't use washout and dumped onto ground, still wet at time of inspection. Foreman is going to have excavator scrape and clean area. Curbing still needed on right of way at Jefferson, they are waiting for ACHD approval. Most of disturbed area is below grade, wattles installed where it is even with road.
|
General Inspection | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Michael Zawacki
|
|
|
Parking lot paved, all workers parking in lot or on street. Landscaping in progress, torn up for sprinkler lines. Sidewalk still hasn't been installed all the way to WWP Blvd. Site is clean and all trash thrown in dumpster. Majority of school work is now interior, building shell nearly complete.
|
General Inspection | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Michael Zawacki
|
|
|
Site clean. Work on extending sidewalk down Jefferson to WWP Blvd, will remove wattle from that area when complete. Area along WWP Blvd has a small buffer and wattles. Staging is on east side of project. No dust or trackout issues.
|
Random Inspection | 8/3/2018 | 8/3/2018 | 8/3/2018 | A | PART |
Andy J. Long
|
|
|
Correction requested:
- clean up concrete slurry from cutting entrance on Whitewater.
Verbal correction to RP Chase.
|
General Inspection | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | PASS |
Michael Zawacki
|
|
|
Water truck on site, area is dust free. Concrete washout and dumpster on site. New entrance will be in place soon, will continue to use existing stabalized entrance as long as possible. All material storage contained on site, diesel has secondary containment. No ESC issues.
|
General Inspection | 5/3/2018 | 5/3/2018 | 5/3/2018 | P | PASS |
Andy J. Long
|
|
|
Construction entrance installed. Concrete and masonry lined washout pit located next to job trailer. Covered storage for materials provided, fuel tank has secondary containment. Water truck is spraying down access around the building 2x daily to keep down dust. No dust issues observed at time of inspection.
Correction to work on for next inspection: - post CGP 2017 required SWPPP notifiication and new green COB ESC sign at entrance or on job sign.
|
General Inspection | 3/2/2018 | 3/2/2018 | 3/2/2018 | P | FAIL |
Andy J. Long
|
|
|
Correction request to install correct type of rock in construction entrance. Crushed or angular 1.5"-3" , no round river rock
|
General Inspection | 2/7/2018 | 2/7/2018 | 2/7/2018 | P | PASS |
Michael Zawacki
|
|
|
Perimeter controls intact and working, DIs are protected and clean. Washout on site that cement trucks are using. No dust or trackout issues.
|
Complaint Inspection | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | PASS |
Andy J. Long
|
|
|
trackout complaint referred from EPA (received by them 1/24)
NO significant trackout. Some minor tracking that can be addressed at end of day. May indicate trackout observed was cleaned up.
Construction entrance installed, receiving storm drain has inlet protection.
|
General Inspection | 1/23/2018 | 1/23/2018 | 1/23/2018 | P | PASS |
Michael Zawacki
|
|
|
Perimeter controls intact, no runoff nto WWP Blvd or Jefferson. Workers are not parking on site. Construction entrance built and maintained, very minimal trackout, just a dust layer. Stockpile is well within limits of BMPs. No dust blowing. Concrete washout on site. Site is in good condition.
|
General Inspection | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | PASS |
Andy J. Long
|
|
|
Working on foundation footprint and site work. Site has perimeter sediment control wattle installed and receiving MS4 DIs have witches hat filters installed. No trackout to Jefferson. Approved.
|
Random Inspection | 12/18/2017 | 12/18/2017 | 12/18/2017 | A | PASS |
Andy J. Long
|
|
|
WIP on site work. Construction entrance installed and in good condition, no trackout. Perimter BMPs installed, no issues observed, no corrections requested.
|
Complaint Inspection | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | CANC |
Michael Zawacki
|
|
|
|
Complaint Inspection | 12/6/2017 | 12/6/2017 | 12/6/2017 | P | PASS |
Michael Zawacki
|
|
|
Report of dewatering. No notice or dewatering plan submitted.
Check to see if dewatering occured and if any clean up is required. Were using water truck to wash pavement & then drained to prevent freezing. No dewatering on site. Conttractor said they will schedule sweepers and no longer use wash waters.
|
General Inspection | 11/16/2017 | 11/22/2017 | 11/24/2017 | A | PASS |
Michael Zawacki
|
|
|
Gate was locked, only able to do perimeter check. Everything staying onsite.
|
Tracking Control | 11/21/2017 | 11/21/2017 | 11/21/2017 | A | PART |
Andy J. Long
|
|
|
Trackout onto Jefferson. Round river rock access is plenty long and deep but is not scraping the tires adequately. Sweeeper has visited site this morning. Material is wet sand material and is sticking to tires. RP Chase on site.
Request for frequent sweeping until rock can be replaced or the new entrance installed. DI bag installed at Whitewater & Jefferson, receives runoff from dirty part of street.
Will check back tomorrow - minimize and clean up trackout - post green Boise ESC permit sign - post proper CGP- SWPPP info.
|
Random Inspection | 11/16/2017 | 11/16/2017 | 11/16/2017 | P | PASS |
Andy J. Long
|
|
|
First phase permit ESC17-00992 has been finaled. All remaining covered under this permit.
Perimeter controls, inlet protection and construction entrance is installed.
Beniton RP Chase Coooper ###-####
|