Aging Inspection | 7/6/2020 | 7/6/2020 | 7/7/2020 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 7/7/2020 | 7/7/2020 | 7/7/2020 | P | PASS |
Michael Zawacki
|
|
|
|
Aging Inspection | 5/4/2020 | 5/4/2020 | 5/5/2020 | | PASS |
Michael Zawacki
|
|
|
3 homes left in subdivision. 2 lots still need to be landscaped. All concrete work completed. Site is clean.
|
Tracking Control | 3/4/2020 | 3/6/2020 | 3/6/2020 | A | PART |
Michael Zawacki
|
|
|
Street looks like it was swept. Workers parked in area, looks like some new tracking coming from site. Should be cleaned when everyone off site.
|
Tracking Control | 3/2/2020 | 3/5/2020 | 3/4/2020 | A | PART |
Michael Zawacki
|
|
|
Backfill has been removed and street scraped. Still needs to be swept, follow up scheduled. Talked to RP at original inspection, follow up was ahead of schedule since I was in area.
|
General Inspection | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | FAIL |
Michael Zawacki
|
|
|
Lots of dirt on road back on Landmark. Sent message to Herbert, follow up scheduled.
|
Aging Inspection | 1/14/2020 | 1/14/2020 | 1/14/2020 | | PASS |
Michael Zawacki
|
|
|
WIP on multiple homes. Snow covered site.
|
BMP Violation | 11/14/2019 | 11/19/2019 | 11/18/2019 | A | DONE |
Michael Zawacki
|
|
|
Talked with RP. Has washout on site, will clean old dumped when excavator at site to do next foundations this week. Will do a trash walk also.
|
General Inspection | 11/14/2019 | 11/14/2019 | 11/14/2019 | P | FAIL |
Michael Zawacki
|
|
|
Merssage sent to RP William. Old washout dump has been exposed now that vegetation has died, also lots of wind blown trash. Follow up scheduled.
|
General Inspection | 10/7/2019 | 10/7/2019 | 10/7/2019 | | PASS |
Michael Zawacki
|
|
|
2 homes under construction on Woodcreek. One is currently being framed the other has foundation poured with no more work done. Streets and sidewalks are being swept, trash boxes in use. South end of site is vegetated and stable.
|
General Inspection | 8/5/2019 | 8/5/2019 | 8/5/2019 | | PART |
Andy J. Long
|
|
|
Subdivsion is clean, Red Oak home still onsite.
Correction request to Willie to change out the storm drain sediment bag on Woodcreek
|
General Inspection | 6/3/2019 | 6/3/2019 | 6/3/2019 | P | PASS |
Michael Zawacki
|
|
|
No new foundations, washout has been broken and needs repair before next pour. 3 of 4 homes exterior work completed. One roofer on site. No ESC issues.
|
General Inspection | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with RP on site. Some trash from last home, box was built this morning and will be cleaned. Sidewalks and gutter will be swept when everyone leaves.
|
General Inspection | 3/19/2019 | 3/19/2019 | 3/19/2019 | | PASS |
Michael Zawacki
|
|
|
WIP on two homes. Sidewalks are swept, no dirt leaving lots. Washout on site.
|
General Inspection | 1/14/2019 | 1/14/2019 | 1/14/2019 | P | FAIL |
Michael Zawacki
|
|
|
Trackout onto road and sidewalk. Talked to RP of homes under construction and asked for cleanup.
|
General Inspection | 11/15/2018 | 11/15/2018 | 11/15/2018 | A | PASS |
Andy J. Long
|
|
|
Site work in final stages of completion. Storm drains have been fitted with sediment protection. Landscaping in progress.
First SFH permit issued on Woodcreek, site meeting conducted with Red Oak RP Willie.
Will close this permit next general inspection.
|
General Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Michael Zawacki
|
|
|
No current activity. Road is paved and curbing and sidewalks completed. Lots are all marked with survey stakes and are bare. Fence along south edge by canal, wattles have been removed and area will need to be monitored.
|
Tracking Control | 8/22/2018 | 8/24/2018 | 8/24/2018 | A | PASS |
Andy J. Long
|
|
|
Area of concern at south end of subdivision has been swept as requested. Crew on site installing neighborhood fence.
Will need to install sediment protection on the stormdrain on Woodcreek and on Landmark.
|
Tracking Control | 8/21/2018 | 8/22/2018 | 8/22/2018 | A | FAIL |
Andy J. Long
|
|
|
No crew or activity. Subdivision infrastructure is complete. No SFHs yet.
Dirt and sandy trackout to Landmark has not been swept or was missed or added after sweeping request. Follow up scheduled for 8/23.
If no clean up, re-inspection fees will be charged for repeat Fails.
|
Tracking Control | 8/13/2018 | 8/15/2018 | 8/15/2018 | A | FAIL |
Michael Zawacki
|
|
|
Not swept
|
Tracking Control | 8/13/2018 | 8/13/2018 | 8/13/2018 | P | NR |
Michael Zawacki
|
|
|
check for track out clean up Conger has sweeper and is supposed to be on site today. Follow up 8-15
|
Complaint Inspection | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | FAIL |
Michael Zawacki
|
|
|
Lots of trackou on Landmark leading into existing neighborhood. Left message with David.
|
General Inspection | 5/18/2018 | 6/4/2018 | 6/4/2018 | P | PASS |
Michael Zawacki
|
|
|
Stripping and prep nearly completed. Pipe crew will be coming in soon. Water truck is on site, no dust issues. Canal on southern edge is protected with wattle. No trackout. Topsoil is stockpiled in middle of site.
|
Site Preparation | 5/17/2018 | 5/18/2018 | 5/18/2018 | A | PASS |
Andy J. Long
|
|
|
9 AM pre-construction meeting
Construction entrance and permit sign to be located on Sunflower Street. Initial access to site will be on existing gravel entrance. Wattles installed along south clearing limits. Top soil will be saved for reuse. Irrigation ditch has already been piped and re-routed, old ditch to be filled in. Will need fugitive dust control.
Approved for construction. Construction to begin in approximately 2 weeks. Follow up scheduled
|