General Inspection | 7/27/2020 | 7/27/2020 | 7/27/2020 | | PASS |
Michael Zawacki
|
|
|
Southern half is bare and has stockpiles. Northern half has paved roads, curbing, and sidewalk. ne crew working on nw corner, have water truck, no issues.
|
General Inspection | 6/25/2020 | 6/25/2020 | 7/1/2020 | | PASS |
Andy J. Long
|
|
|
WIP paving roads. NO fugitive dust or trackout observed. No corrections requested at this time.
|
General Inspection | 5/25/2020 | 5/25/2020 | 5/27/2020 | | PASS |
Michael Zawacki
|
|
|
Western phase is all graded, east section starting to get weed coverage. Stockpiles on south of site. Water truck on site. SOme activity, no street or curbing work has begun.
|
General Inspection | 4/24/2020 | 4/24/2020 | 4/24/2020 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/24/2020 | 3/24/2020 | 3/24/2020 | P | PASS |
Michael Zawacki
|
|
|
No new site activity. One worker from track utilities on site.
|
General Inspection | 2/24/2020 | 2/24/2020 | 2/24/2020 | | PASS |
Michael Zawacki
|
|
|
Stripping has begun on south end. Some stockpiles. Road has been cut going far south. No machinery or workers at site.
|
General Inspection | 1/23/2020 | 1/23/2020 | 1/23/2020 | P | PASS |
Michael Zawacki
|
|
|
No activity, surveyor on site. Some tracking onto lake hazel on north side, coming from gates going to ag land and not construction site.
|
General Inspection | 1/13/2020 | 1/13/2020 | 1/14/2020 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 12/13/2019 | 12/13/2019 | 12/17/2019 | P | PASS |
Andy J. Long
|
|
|
No significant trackout. Some minor site work occuring. Will soon be shut down for winter. No corrections at this time.
|
Tracking Control | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | FAIL |
Michael Zawacki
|
|
|
Lots of dirt along curbing and some light trackout. Message sent to John Laude.
|
General Inspection | 11/1/2019 | 11/1/2019 | 11/6/2019 | P | PART |
Michael Zawacki
|
|
|
Trucks running laps hauling fill. Some tracking aT BOTH ENTRANCES.
|
General Inspection | 10/14/2019 | 10/14/2019 | 10/16/2019 | P | PASS |
Michael Zawacki
|
|
|
Work is getting near north east corner, water truck running on site. No dust in work area, truck kicked up cloud going towards exit, water truck sprayed area after dust cloud. Very little trackout.
|
General Inspection | 9/23/2019 | 9/23/2019 | 9/24/2019 | | PART |
Michael Zawacki
|
|
|
Work on water and sewer line install. Water truck on site. People exiting on western side where there is no stabalized entrance. Some dirt on road apron.
|
Tracking Control | 8/21/2019 | 8/21/2019 | 8/23/2019 | P | PART |
Andy J. Long
|
|
|
Construction entrance was maintained, but there is a lot of loose sand, sediment, and gravel in the shoulder along the Lake Hazel frontage of the site.
Request to have shoulder swept next week. Much of it is from Knife River water truck going between Barnwood (trilogy) and Baserri (hayden homes).
|
Complaint Inspection | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | FAIL |
Andy J. Long
|
|
|
Corrections needed:
- sweep Lake Hazel Rd. between site and Cole - improve and lengthen construction entrance - water the site at the end of each day to "crust" down loose dirt on access roads to limit wind blown dust.
|
General Inspection | 8/13/2019 | 8/13/2019 | 8/13/2019 | | PART |
Michael Zawacki
|
|
|
Doing sewer and water lines, water truck on site. Some trackout, road will need to be swept end of day.
|
General Inspection | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Michael Zawacki
|
|
|
Giant trencher on site. Some dust from work on far south of site. SOme dirt on road apron, no trackout onto road.
|
General Inspection | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Andy J. Long
|
|
|
WIP on infrastructure/utlity installed. Construction entrance installed. No fugitive dust plumes observed. Site staying within clearing limits.
|
General Inspection | 6/6/2019 | 6/6/2019 | 6/6/2019 | P | PASS |
Michael Zawacki
|
|
|
Site work in progress. Water truck on site. Only one excavator active.
|
General Inspection | 5/9/2019 | 5/9/2019 | 5/9/2019 | P | PASS |
Michael Zawacki
|
|
|
Blasting completed. Some grading and hauling on site. Lots of dust, area is surrounded by open desert. No trackout. Pipe is staged by east entrance.
|
General Inspection | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | PASS |
Michael Zawacki
|
|
|
Superior blasting currently on site. Pipe staged and will begin after all blasting completed.
|
Site Preparation | 4/22/2019 | 4/22/2019 | 4/22/2019 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Michael Zawacki
|
|
|
Drill rigs on site, no site grading or dirt moving. Syman is doing ESC inspections for site. No issues, no dust.
|
General Inspection | 1/17/2019 | 1/17/2019 | 1/17/2019 | P | PASS |
Michael Zawacki
|
|
|
No workers on site. Area is graded, some stockpiles on site.
|
General Inspection | 1/9/2019 | 1/10/2019 | 1/10/2019 | P | FAIL |
Andy J. Long
|
|
|
Corrections needed:
- clean up paved apron to construction entrance - uncompact the rock in the entrance - add more rock w/ lining to increase the length of the entrance.
Correction request left on RP John's voicemail
- possible work occuring on the parcel across the street.
|
General Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PART |
Andy J. Long
|
|
|
Notified RP of notice from Syman that SWPPP is not complete. He was not aware of the issue,.
Site is currently inactive. Correction request to John to clean up trackout into the road apron on the east entrance.
|
General Inspection | 11/21/2018 | 11/21/2018 | 11/21/2018 | P | PASS |
Michael Zawacki
|
|
|
Site is rough graded. No current activity and most machines are gone. Lots of light soil that looks like ash, may blow if windy. No ESC issues.
|
General Inspection | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Michael Zawacki
|
|
|
No activity at site during inspection, area is rough graded. Syman is doing site inspections.
|
General Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Michael Zawacki
|
|
|
Graders running on site, some dust, water wagon spraying site. East entrance has stabalized rock. Site is in a depression, no run off concern.
|
General Inspection | 9/18/2018 | 9/18/2018 | 9/19/2018 | P | PASS |
Michael Zawacki
|
|
|
Graders and water wagons working on south side of property. No blowing dust. Crushed rock exit installed, no trackout. Very windy at time of inspection.
|
General Inspection | 8/21/2018 | 8/29/2018 | 8/29/2018 | A | PASS |
Michael Zawacki
|
|
|
Work hasn't begun. silt fence along perimeter of lake hazel.
|
Site Preparation | 8/20/2018 | 8/21/2018 | 8/21/2018 | A | PASS |
Andy J. Long
|
|
|
check out site location and potential BMPs. Few physical BMPs on ESC site plan. Project should start late this week or next week.
ESC permit sign and SWPPP are posted. Entrance is just east of the NY Canal at Lake Hazel @ Cole. Initial BMPs installed.
Reviewed fugitive dust control requirements with RP.
Approved for construction.
|