Permit Information
Permit NumberESC19-00241
StatusIssued
Name JOSHUA SCHWANDT
Site Address 3434 N BOGUS BASIN RD
Project NameHighlands Elementary School
Customer Number 
ePlanReviewNo
Description
Demolition of existing school and construction of new single story, 42,755 s.f. structure consisting of (16) classroom, (4) resource rooms, administration suite, media center, music room, cafeteria, kitchen, multi-purpose gymnasium and restrooms
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/3/20208/3/20208/3/2020 PASS
DetailsMichael Zawacki
Landscaping is completed. Site will need final cleanup.
General Inspection7/17/20207/17/20207/17/2020 PASS
DetailsMichael Zawacki
Only disturbed areas in rear of school. Landscapers on site. No issues with site.
General Inspection7/2/20207/2/20207/2/2020 PASS
DetailsAndy J. Long
General Inspection6/17/20206/17/20206/17/2020 CANC
DetailsAndy J. Long
General Inspection6/2/20206/2/20206/3/2020 PASS
DetailsMichael Zawacki
Parking lot and ring around school paved, behind school still bare. Outside work is masonary. Some small debris around site, some bare spots, nothing leaving site. Wattle perimeter still installed. Workers all parked on paved lot.
General Inspection5/18/20205/18/20205/19/2020 PASS
DetailsAndy J. Long
WIP. Parking lot and access is now paved. No ESC requests at this time
General Inspection5/1/20205/1/20205/1/2020 PASS
DetailsMichael Zawacki
Most curbing completed. Road bed prepped for paving. No tracking, site is clean and contained.
General Inspection4/16/20204/16/20204/16/2020 PASS
DetailsMichael Zawacki
Brick facade is only work on outside of school. Concrete crew working on section of sidewalk, no iilicit washout. Lots of curbing and sidewalk already completed. Crew is getting bed prepped for paving. Site is clean, no issues.
General Inspection4/1/20204/1/20204/1/2020 PASS
DetailsMichael Zawacki
Site is all contained, no ESC issues.
General Inspection3/17/20203/17/20203/18/2020 PASS
DetailsMichael Zawacki
Site is contained. Most of area has been pit runned, lots of standing water, very few muddy spots. No trackout, most of work is now inside.
General Inspection2/28/20202/28/20203/4/2020 PASS
DetailsAndy J. Long
BMPs installed include perimeter sediment controls, concrete washout pits, controlled access.

WIP prepping front parking lot off curling.

Minor trackout. occuring. Agreed to allow frequent sidewalk and street sweeping in lieu of construction entrance. Site has pit run and drainage established with minimal muddy spots

Trash contained, spill kit onsite. RP on full time duty at site.

Approved.
General Inspection2/12/20202/12/20202/12/2020 PART
DetailsMichael Zawacki
Hauling in backfill and grading. Some trackout, taled to foreman. Will broom the next few days and have a sweeper end of week.
General Inspection1/24/20201/24/20201/24/2020 PASS
DetailsMichael Zawacki
Site is contained, work is inside building. No trackout.
General Inspection1/8/20201/8/20201/8/2020 PASS
DetailsMichael Zawacki
Will turn over entrance next week when excavator back on site. Lots of debris on curling, leaves etc, they will clean. DIs are plugged up road, notified ACHD.
General Inspection12/23/201912/23/201912/23/2019PPASS
DetailsMichael Zawacki
Site is clean and contained. Workers have pit run parking above low spot. No trackout, entrance will soon need to be turned.
General Inspection12/11/201912/11/201912/11/2019 PASS
DetailsMichael Zawacki
Site is clean and contained. Almost all current work is inside building. Only outside activity is roofers. Will need to watch for tras from shrink wrapping on roof materials. One entrance, street is clean. Entire site is pitrun.
General Inspection11/1/201911/1/201911/1/2019PPASS
DetailsMichael Zawacki
WIP on framing.
All concrete work done until spring. Plan is to have framing done and work on interior all winter.
Seepage beds completed, 10" pit run all across site to have it free drain during winter. Two exits, sweeping up weekly.
General Inspection10/2/201910/2/201910/2/2019PPASS
DetailsMichael Zawacki
Met with foreman at site.
Just completed a pour, washouts were used. Masons have secondary containment for mortar mixers and a washout. No loose trash at site.
Pit run will be brought in to make ring road around site. Entrances will be elongated and entrance will get rock to also serve as exit.
General Inspection9/17/20199/17/20199/17/2019PPASS
DetailsMichael Zawacki
Site is low spot and all contained. No trackout at time of inspection. Inside site is muddy.
General Inspection8/20/20198/20/20198/20/2019PPASS
DetailsMichael Zawacki
WIP on stem walls, concrete washouts at site. Some light tracking out of site, warner doung dirtwork, will look into adding rumble bars to stabalized exit. Will sweep end of work day, 40+ trucks a day hauling material.
Stockpile starting to be used, will water if it starts blowing, if going idle they will flatten top. Sprinkler line leaked in rear, wattle kept sediment on site, will cap it when backfill moved from on top of it.
wattle on perimeters that aren't going uphill.
Water truck on site, area is moist and dust free, not muddy.
General Inspection8/2/20198/13/20198/15/2019PPASS
DetailsAndy J. Long
No trackout from site. No fugitive dust observed. Permits posted. No corrections requested at this time.
General Inspection8/2/20198/5/20198/6/2019ACANC
DetailsAndy J. Long
General Inspection8/2/20198/2/20198/2/2019PPASS
DetailsAndy J. Long
Construction entrance installed. No trackout. NO fugitive dust. No corrections requested.
General Inspection7/17/20197/18/20197/19/2019APASS
DetailsMichael Zawacki
School has been demoed and is being halled off. Some of area has been stripped, large buffer still on site. No dust or trackout. No new construction has begun, all related to demo.
Site Preparation7/1/20197/9/20197/9/2019APASS
DetailsAndy J. Long
9 josh with CM

Site walk through with RP Josh and project manager Isaac with CM Company. SWPPP sign and placement for Boise ESC permit is being made. Will need to check for it next inspection. SWPPP binder and ESC plan in job trailer, NOI is active. Site will do 14 day inspections and after 0.25" 24-hr rain events.

For demolition phase, controls will include dust control with water and using existing asphalt for haul off.

After demolition a new 2" fractured rock and fabric construction entrance will be installed at the NE corner of site from Curling. This will be the exit, there will be a one way loop road where entrance is closer to Bogus Basin Road. Staging area will be within the fence on south side of school. The lined concrete washout pit will be in this location. It is not yet installed. Warner Construction will do the earthwork.

Requested that instead of drop inlet sediment protection on the high volume storm drains at Curling discharging to Crane Creek, utilize daily trackout sweeping/monitoring and gutter sediment check bags. Drop inlet filter could causing overflow and road flooding due to high volume.

Perimeter sediment control wattle is properly installed, grass will be preserved on inside of wattle as well as outside. There is more than 50' buffer to Crane Creek.


Approved for construction.
Conference7/1/20197/1/20197/1/2019APASS
DetailsAndy J. Long
site walk-through and BMP inspection scheduled for next Tuesday AM.

Permit sign posted on site. Crews will begin to remove trees and playground asphalt this week. Perimter vegetation will remain preserved. RP on duty.

Building demolition to begin next week.