Permit Information
Permit NumberESC19-00304
StatusIssued
Name TIM MOKWA
Site Address 7791 W LAKE HAZEL RD
Project NameBASSERI SUB NO 2
Customer Number 
ePlanReviewNo
Description
Residential Subdivision Construction. See CGP #IDR1001C9 and ESC19-00303. 27 acre subdivision on two seperate parcels north and south of Lake Hazel, west of Cole Road.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/16/20207/16/20207/16/2020 PASS
DetailsMichael Zawacki
North side of lake hazel has no activity, weed growth all lots stabalized.
South Side:
No trackout onto silver spur from future phase to south. Multiple SFH are completed on street.
All current lots that have activity are clean.
Neska has future phase to south, no activity but is possible for people to drive into dirt without entrance.
All empty lots along corona are vegetated with weeds.
No construction activity on maverick, all lots are stable with weeds. Washout is lined and located on maverick.
ite prep activity on southern section of site. Rock pad entrance on Merdona Wood. Currently some joint trench open on site, no heavy equipment or activity. Lots of stockpiles on site. While on site a truck hauled in more fill.
No tracking or blowing dust.
General Inspection6/15/20206/15/20206/15/2020 CANC
DetailsMichael Zawacki
Conference5/12/20205/13/20205/13/2020PPASS
DetailsAndy J. Long
3 PM

Onsite meeting to discuss SWPPP/ESC responsibilities for Basserri Subdivision phases 1-4. Organized by ESC Responsible Person Tim with Hayden Homes land development:

Knife River and Syman doing ESC related activities for land developemnt. Homes in phase 2 permitted seperately with HH RP Alan and Tek Solutions doiong SWPPP inspections:

Knife River duties:
- maintain construction entrance to prevent trackout from work and hauling area. Phase 3 & 4 rock construction entrance is at SE corner off Cole.
- use own leakproof concrete washout facility for any subdivsion concrete worki nstead of Hayden Homes home building washout pan
- have water truck on duty for fugitive dust control. May need to end of day crusting of work areas and stockpiles

Syman Company:
- will sweep subdivsion and access point on Cole once a week on Fridays. Excessive trackout or mud clods on Cole should be cleaned up within 24 hours
- will conduct SWPPP inspections on 2 week frequency and after 0.25" rain events
- during inspections will inspect storm dran sediment bags and do maintenance as needed

Hayden Homes RP Tim shall be notified by Boise ESC Inspectors for all correction requests and will delegate tasks as needed.

Discussed that any bare lots not build upon and causing dust issues will need temporary stabilization/seeding until construciton. Plan is to build out phase 2 this year. No wind blown dust issues observed at time of inspection.

Inspection observation:

Sediment control BMPs installed in subdivision, no violations observed. Minor trackout from construction entrance due to rain earlier in day, Request to scrape/maintain construction entrance rock or widen so all vehicles have to pass over track pad
General Inspection4/23/20204/23/20204/23/2020PPASS
DetailsAndy J. Long
WIP on homes on Silver Spur and Corona. Washout pan onsite next to job trailer. Storm drains have sediment bags installed.

Notified RP Allen from Hayden to have washout pan service requested for tomorrow.
General Inspection4/7/20204/7/20204/7/2020PPASS
DetailsMichael Zawacki
Paving and sidewalks done throughout site. Knife river has sweeper and rock entrance in to south area. Washout cleaned up.
No issues at site.
General Inspection3/24/20203/24/20203/24/2020PFAIL
DetailsMichael Zawacki
Lots of dirt from backfill on sidewalks.
Knife river doing site prep on far south of site. Road is not paved to south cole. Heavy equipment is running throughout site.
Multiple homes under construction on western perimeter.
No homes have begun on north side. Culdesac curbing completed, not paved.
Multiple phases of construction under multiple permits. Lots of overlap, site getting same inspection report for all permits.
General Inspection2/24/20202/24/20202/24/2020PPASS
DetailsMichael Zawacki
No site development work. SOme large stockpiles on noth of Lake hazel. Phase 1 construction has begun on south side.
Tracking Control1/23/20201/28/20201/28/2020APASS
DetailsMichael Zawacki
Trackout cleaned and entrance improved.
General Inspection1/22/20201/22/20201/23/2020 FAIL
DetailsMichael Zawacki
South side idle.
One crew on north side, Alloway Electric on site, lots of trackout, thier truck and tailer ar muddy.
Sent messdage to RP to clean street in neighborhood on nort, follow up scheduled.
Tracking Control12/17/201912/17/201912/17/2019PFAIL
DetailsAndy J. Long
Need to provide stabilized entrance and or employee parking area. Lots of mud and loose dirt on Cole south of Lake Hazel.

Correction request to provide entrance, post ESC perrmit signs, and sweep Cole Road
General Inspection11/20/201911/20/201911/20/2019PPASS
DetailsMichael Zawacki
South Side.
Only activity is Knife River maintenance truck on site.
General Inspection11/6/201911/6/201911/6/2019PPASS
DetailsMichael Zawacki
WIP on both sides of Lake Hazel. Lots of stockpiles. No tracking from either side. Blowing dust coming from behind trucks and equipment.
Looks like utility work.
General Inspection10/14/201910/14/201910/16/2019PPASS
DetailsMichael Zawacki
No activity on site. Windy, no blowing dust. Curbing along Lake Hazel completed.
General Inspection9/24/20199/24/20199/24/2019PPASS
DetailsMichael Zawacki
WIP on water lines. Water truck on site. Some dust behind excavators. No major issues.
Tracking Control8/19/20198/21/20198/23/2019PPART
DetailsAndy J. Long
Dust control seems to have improved, with more circulation on the haul routes. Construction entrance was extended and roughened.

Shoulder along Lake Hazel needs sweeping. Request for Knife River to get sweeeper since much of the track out is from water truck moving between Baserri sub and Barnwood.
Complaint Inspection8/19/20198/19/20198/19/2019PFAIL
DetailsAndy J. Long
Dust complaint:

- rock drill and vehicle movement through site is causing fugitive dust.


Corrections needed:
- improve and lengthen construction entrance.
- sweep apron and Lake Hazel between site and Cole Road.
- water truck should be circulating on haul roads when not being used for backfill compaction.
General Inspection8/7/20198/7/20198/7/2019PPASS
DetailsMichael Zawacki
WIP on utilities. Excavators and loaders on site, material is being hauled off. Water truck on site spraying. Some tracking onto lake hazel, road is closed. Water truck is spraying stockpiles.
General Inspection7/24/20197/24/20197/24/2019PPASS
DetailsMichael Zawacki
Permits for both sides of road displayed at entrance, stabalized entrance installed.
All work is currently on west side of site. Drilling rig on site not currently being used. One front end loader running on site and an excavator doing pipe work. Site has been watered and is dust free.
General Inspection7/11/20197/11/20197/11/2019PPASS
DetailsMichael Zawacki
Few drill rigs working on site. Area mostly being used for parking for workers. Water has been used to keep dust down, no trackout.
Site Preparation6/14/20196/14/20196/17/2019PPASS
DetailsAndy J. Long
Construciton entrance installed, permit signs and SWPPP information posted on south phase. No dust plumes leaving site currently, but will need to get water truck(s) on site.

Jess Rosen from Knife River called regarding blasting permits, I referred him to the Fire Dept.