General Inspection | 8/10/2020 | 8/10/2020 | 8/10/2020 | | PASS |
Michael Zawacki
|
|
|
No new activity. East is stable. No homes or construction activitys have begun on west.
|
General Inspection | 7/24/2020 | 7/24/2020 | 7/28/2020 | | PASS |
Michael Zawacki
|
|
|
East is stable. West side road has been seal coated and is blocked. Does not look like there has been any activity.
|
General Inspection | 7/9/2020 | 7/9/2020 | 7/9/2020 | | PASS |
Michael Zawacki
|
|
|
No issues at site. Repairs have been made. Site should get reapplication of seed before winter.
|
General Inspection | 6/24/2020 | 6/24/2020 | 6/24/2020 | | PASS |
Michael Zawacki
|
|
|
East side of road is stable. West side has had lots and berms cleaned up. Some prep work for repair of sidewalk.
|
General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PART |
Michael Zawacki
|
|
|
Issues where water has come of Bogus Basin rd. Rills down embankment, sediment and water going through culvert and causing issues. Lot is good and stable.
|
General Inspection | 6/2/2020 | 6/2/2020 | 6/3/2020 | | PASS |
Michael Zawacki
|
|
|
Gate into upper section closed. Hillside has good growth. Wattle has been installed on BB road where water was causing rills. Upper berm repaired to direct water back onto road. Heavy equipment operating on west side of road.
|
General Inspection | 5/15/2020 | 5/15/2020 | 5/19/2020 | | PEND |
Andy J. Long
|
|
|
Runoff from Bogus Basin Road causing erosion on road shoulder. ACHD installed the existing rip rap, not the construction site.
GC/RP Scott said that tomorrow outfall on the culvert on west side of road near trail will get repaired.
Going to notify ACHD of the roadway runoff issue
|
General Inspection | 4/30/2020 | 4/30/2020 | 4/30/2020 | P | PASS |
Michael Zawacki
|
|
|
Gate to upper section is closed. Slopes have good grass growth, wattles still on slopes. Large rill forming inside curve on Bogus Basin rd. All dirt is staying on site.
|
General Inspection | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | FAIL |
Michael Zawacki
|
|
|
Rill forming under berm along Bogus Basin road. Looks like concentrated flow coming from road. Sent pictures to Scott, will need to look at way to resolve issue. Rest of site has held up very well.
|
General Inspection | 1/24/2020 | 1/24/2020 | 1/24/2020 | P | PASS |
Michael Zawacki
|
|
|
Disturbed area has been hydroseeded and wattle space on hillside. Berm along Bogus Basin road has been installed. Do not see any rills or other issues.
|
General Inspection | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PASS |
Michael Zawacki
|
|
|
All hillsides and lots on both sides of road in good shape. No erosion issues. Some game trails across tackified hillsides.
|
General Inspection | 12/9/2019 | 12/9/2019 | 12/9/2019 | P | PASS |
Michael Zawacki
|
|
|
All lots held their water during weekend rain event. No rilling on hillsides or signs of issues in gulleys. Hydroseed and wattle in good condition. No issues from water flowing off Bogus Basin Road. No issues from outflow pipe that comes under road.
|
General Inspection | 11/19/2019 | 11/19/2019 | 11/20/2019 | P | PASS |
Andy J. Long
|
|
|
Slopes have been tracked, installed with wattle, and a double application of hydroseed with tacifying mulch. Road mix/gravel walking path has been installed between Hackberry Ranch and Hackberry Ridge. Grading and lot prep is complete, some minor concrete work for shoulder work is occuring.
|
General Inspection | 11/8/2019 | 11/8/2019 | 11/8/2019 | P | PASS |
Michael Zawacki
|
|
|
Lower section along BB road has been hydroseeded. Wattle wasn't repaired, looks like some more large rocks have been added below outlet. Syman is starting to hydroseed the upper west side. Wattles on hillside installed properly, 3 rows on steeper areas, long drainage will get more. Lots are bermed to contain water. East side will begin when west done, will add wattles to long mild slope to prevent water velocity from becomming damaging. Crushed rock to be added where road was being crossed. Gravel path also being constructed connecting phases for walking or biking. Will also stabilize and landscape ACHD property above road.
|
General Inspection | 11/5/2019 | 11/5/2019 | 11/5/2019 | P | FAIL |
Andy J. Long
|
|
|
Corrections needed:
- install additional riprap for the piped outlet west of Bogus Basin Road
- check for correct wattle installation
|
General Inspection | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with Scott on site. Is having the hillsides watered and retracked with a bigger machine, smaller machine was having issues getting up hills. Syman should start hydroseeding next week. Let him know to have wattle ends overlap and have stakes at 5' intervals.
|
General Inspection | 10/17/2019 | 10/17/2019 | 10/22/2019 | P | PASS |
Michael Zawacki
|
|
|
Crew starting to install wattle on lower area west of Bogus Basin Rd where grading completed. No construction activity today. No blowouts or failures from rain events.
|
General Inspection | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Michael Zawacki
|
|
|
Major earthwork expected to be done in two weeks. Syman has took samples to determine fertilizer mix to use in hydroseeder. Topsoil is being stockpiled. No issues at time of inspection.
|
General Inspection | 10/2/2019 | 10/2/2019 | 10/2/2019 | P | PASS |
Michael Zawacki
|
|
|
Met with site owner on site. Has syman scheduled to do hydroseeding as soon as grading is completed, will see about staging and starting work in areas where it is ready instaed of waiting for all grading to be completed. Is going to double check riprap at outlet. Granite is now hauling material from east to west side of bogus. Some dirt trails across road, get swept as day goes on.
|
General Inspection | 9/17/2019 | 9/17/2019 | 9/17/2019 | P | PASS |
Michael Zawacki
|
|
|
No rilling or blowouts from rain event. No hillside protection, grading still in progress. Mud on road from where trucks and equipment are crossing.
|
General Inspection | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Michael Zawacki
|
|
|
Post rainfall inspection. No blow outs onto Bogus Basin Rd, no issues.
|
General Inspection | 8/29/2019 | 8/29/2019 | 8/30/2019 | P | PART |
Michael Zawacki
|
|
|
Haul trucks taking material from upper to lower sections. Lots of dust on haul road, has been watered. Sweeper and broom crew working site at time of inspection. Site will need to be watered, trucks slow down, or some kind of soil binder on haul road.
|
General Inspection | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Michael Zawacki
|
|
|
Majority of work is on east side of Bogus Basin Rd. Water trucks running, crew running compactor along side of road. Hillside grubbing has begun. No tracking or wattles installed on steep slopes. Lots of cutting on sout west of project also. No dusst, watter trucks getting water at hydrant in church parking lot at Cartwright.
|
General Inspection | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Michael Zawacki
|
|
|
entry error
|
Site Preparation | 8/13/2019 | 8/13/2019 | 8/15/2019 | P | PASS |
Andy J. Long
|
|
|
Boise ESC permit issued and posted at site. No grubbing and grading has occured.
Approved to start construction. First BMP will be fugitive dust control and sweeping up Bogus Basin Road at end of hauling operations from the east side of site to west side.
|