Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberESC19-00994
StatusIssued
Name RHETT COLLINS
Site Address 5176 N BOGUS BASIN RD
Project NameHackberry Ridge.
Customer Number 
ePlanReviewNo
Description
see also GRD19-00044/ESC19-00702. This for the parcel on the east side of Bogus Basin. Site preparation inspection is REQUIRED.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/10/20208/10/20208/10/2020 PASS
DetailsMichael Zawacki
No new activity. East is stable. No homes or construction activitys have begun on west.
General Inspection7/24/20207/24/20207/28/2020 PASS
DetailsMichael Zawacki
East is stable.
West side road has been seal coated and is blocked. Does not look like there has been any activity.
General Inspection7/9/20207/9/20207/9/2020 PASS
DetailsMichael Zawacki
No issues at site. Repairs have been made. Site should get reapplication of seed before winter.
General Inspection6/24/20206/24/20206/24/2020 PASS
DetailsMichael Zawacki
East side of road is stable.
West side has had lots and berms cleaned up. Some prep work for repair of sidewalk.
General Inspection6/8/20206/8/20206/8/2020PPART
DetailsMichael Zawacki
Issues where water has come of Bogus Basin rd. Rills down embankment, sediment and water going through culvert and causing issues.
Lot is good and stable.
General Inspection6/2/20206/2/20206/3/2020 PASS
DetailsMichael Zawacki
Gate into upper section closed.
Hillside has good growth. Wattle has been installed on BB road where water was causing rills. Upper berm repaired to direct water back onto road.
Heavy equipment operating on west side of road.
General Inspection5/15/20205/15/20205/19/2020 PEND
DetailsAndy J. Long
Runoff from Bogus Basin Road causing erosion on road shoulder. ACHD installed the existing rip rap, not the construction site.

GC/RP Scott said that tomorrow outfall on the culvert on west side of road near trail will get repaired.

Going to notify ACHD of the roadway runoff issue
General Inspection4/30/20204/30/20204/30/2020PPASS
DetailsMichael Zawacki
Gate to upper section is closed.
Slopes have good grass growth, wattles still on slopes.
Large rill forming inside curve on Bogus Basin rd. All dirt is staying on site.
General Inspection1/27/20201/27/20201/27/2020PFAIL
DetailsMichael Zawacki
Rill forming under berm along Bogus Basin road. Looks like concentrated flow coming from road. Sent pictures to Scott, will need to look at way to resolve issue.
Rest of site has held up very well.
General Inspection1/24/20201/24/20201/24/2020PPASS
DetailsMichael Zawacki
Disturbed area has been hydroseeded and wattle space on hillside. Berm along Bogus Basin road has been installed. Do not see any rills or other issues.
General Inspection12/23/201912/23/201912/23/2019PPASS
DetailsMichael Zawacki
All hillsides and lots on both sides of road in good shape. No erosion issues. Some game trails across tackified hillsides.
General Inspection12/9/201912/9/201912/9/2019PPASS
DetailsMichael Zawacki
All lots held their water during weekend rain event. No rilling on hillsides or signs of issues in gulleys. Hydroseed and wattle in good condition. No issues from water flowing off Bogus Basin Road. No issues from outflow pipe that comes under road.
General Inspection11/19/201911/19/201911/20/2019PPASS
DetailsAndy J. Long
Slopes have been tracked, installed with wattle, and a double application of hydroseed with tacifying mulch. Road mix/gravel walking path has been installed between Hackberry Ranch and Hackberry Ridge. Grading and lot prep is complete, some minor concrete work for shoulder work is occuring.
General Inspection11/8/201911/8/201911/8/2019PPASS
DetailsMichael Zawacki
Lower section along BB road has been hydroseeded. Wattle wasn't repaired, looks like some more large rocks have been added below outlet.
Syman is starting to hydroseed the upper west side. Wattles on hillside installed properly, 3 rows on steeper areas, long drainage will get more. Lots are bermed to contain water.
East side will begin when west done, will add wattles to long mild slope to prevent water velocity from becomming damaging. Crushed rock to be added where road was being crossed. Gravel path also being constructed connecting phases for walking or biking.
Will also stabilize and landscape ACHD property above road.
General Inspection11/5/201911/5/201911/5/2019PFAIL
DetailsAndy J. Long
Corrections needed:

- install additional riprap for the piped outlet west of Bogus Basin Road

- check for correct wattle installation

General Inspection11/1/201911/1/201911/1/2019PPASS
DetailsMichael Zawacki
Met with Scott on site. Is having the hillsides watered and retracked with a bigger machine, smaller machine was having issues getting up hills.
Syman should start hydroseeding next week. Let him know to have wattle ends overlap and have stakes at 5' intervals.
General Inspection10/17/201910/17/201910/22/2019PPASS
DetailsMichael Zawacki
Crew starting to install wattle on lower area west of Bogus Basin Rd where grading completed.
No construction activity today.
No blowouts or failures from rain events.
General Inspection10/17/201910/17/201910/17/2019PPASS
DetailsMichael Zawacki
Major earthwork expected to be done in two weeks. Syman has took samples to determine fertilizer mix to use in hydroseeder. Topsoil is being stockpiled. No issues at time of inspection.
General Inspection10/2/201910/2/201910/2/2019PPASS
DetailsMichael Zawacki
Met with site owner on site. Has syman scheduled to do hydroseeding as soon as grading is completed, will see about staging and starting work in areas where it is ready instaed of waiting for all grading to be completed. Is going to double check riprap at outlet.
Granite is now hauling material from east to west side of bogus. Some dirt trails across road, get swept as day goes on.
General Inspection9/17/20199/17/20199/17/2019PPASS
DetailsMichael Zawacki
No rilling or blowouts from rain event. No hillside protection, grading still in progress. Mud on road from where trucks and equipment are crossing.
General Inspection9/6/20199/6/20199/6/2019PPASS
DetailsMichael Zawacki
Post rainfall inspection.
No blow outs onto Bogus Basin Rd, no issues.
General Inspection8/29/20198/29/20198/30/2019PPART
DetailsMichael Zawacki
Haul trucks taking material from upper to lower sections. Lots of dust on haul road, has been watered. Sweeper and broom crew working site at time of inspection.
Site will need to be watered, trucks slow down, or some kind of soil binder on haul road.
General Inspection8/21/20198/21/20198/21/2019PPASS
DetailsMichael Zawacki
Majority of work is on east side of Bogus Basin Rd. Water trucks running, crew running compactor along side of road. Hillside grubbing has begun. No tracking or wattles installed on steep slopes.
Lots of cutting on sout west of project also. No dusst, watter trucks getting water at hydrant in church parking lot at Cartwright.
General Inspection8/21/20198/21/20198/21/2019PPASS
DetailsMichael Zawacki
entry error
Site Preparation8/13/20198/13/20198/15/2019PPASS
DetailsAndy J. Long
Boise ESC permit issued and posted at site. No grubbing and grading has occured.

Approved to start construction. First BMP will be fugitive dust control and sweeping up Bogus Basin Road at end of hauling operations from the east side of site to west side.