INSP-Final Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete.
Mark Jensen is the contact. This inspection has already been done, they just wanted a paper trail. Call the contact with further questions. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 4/16/2019 | 4/18/2019 | 4/18/2019 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for TCO Phase 2 complete.
Mark Jensen is the contact. This final is only for the east end. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PART |
Jim Page
|
|
|
Fire sprinkler inspection for TCO phase 1 complete.
Contact is Mark Jensen. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 1/28/2019 | 1/30/2019 | 1/28/2019 | A | CANC |
Jim Page
|
|
|
The contact is Todd Ketterling. Thank you for your help! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 1/25/2019 | 1/28/2019 | 1/28/2019 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with GC, inspection will be rescheduled for a later date.
Mark Jensen is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 1/15/2019 | 1/16/2019 | 1/16/2019 | A | FAIL |
Jim Page
|
|
|
Radius ceiling tiles hang down 7 inches from the ceiling, tile locations to sprinkler heads are not code compliant based on tables 8.6.5.1.2 for standard spray sprinklers and table 8.8.5.1.2 for the extended coverage heads per NFPA13. No other items were inspected.
Mark Jensen is the contact. Thank you! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2019 | 1/14/2019 | 1/14/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overehad fire sprinkler piping witnessed, no pressure loss observed.
Hydrostatic test. Jeff Chaney is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Jeff Chaney. Please call 30 minutes before inspection. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete.
Jeff Chaney is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 1/4/2019 | 1/7/2019 | 1/7/2019 | A | DONE |
Jim Page
|
|
|
Undergorund supply hydrostatic test witnessed, no pressure loss observed.
Jeff Chaney is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 1/4/2019 | 1/7/2019 | 1/7/2019 | P | CANC |
Jim Page
|
|
|
Inspection rescheduled per conversation with point of contact, this request is cancelled.
Jeff Chaney is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 2 of addition complete, level 2 of addition approved for cover.
Mark Jensen is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | CANC |
Jim Page
|
|
|
Rescheduled per conversation with POC, inspection scheduled for 13DEC2018.
Mark Jensen is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/20/2018 | 11/20/2018 | 11/20/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with red ink/pink highlighter areas approved for cover.
Contact is Mark Jensen Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/15/2018 | 10/16/2018 | 10/16/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping installed under the raised floor in room 720 complete, approved for cover. Addition of fire sprinkler piping under raised floor will be notated on the as-builts.
rough to cover Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with green highlighter/red ink area approved for cover including date inspection was completed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/30/2018 | 7/30/2018 | 7/30/2018 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
Underground RTC Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping, notated city approved drawings with pink highlighter areas approved for cover. Drop downs and arm overs to be inspected at a later date.
Mark Jensen is the contact for this rough to cover inspection. He is hoping for an appointment in the AM. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/25/2018 | 6/26/2018 | 6/26/2018 | A | PART |
Jim Page
|
|
|
Partial rough to cover nispection complete for overhead fire sprinkler piping, notated city approved drawings with green highlighter areas approved for cover.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping and FDC piping in combustible concealed space (crawl space) on the north and south side of gym area complete, approved for cover.
|
INSP-Sprinkler Rough-in | 3/20/2018 | 3/20/2018 | 3/20/2018 | P | PART |
Troy Cobbley
|
|
|
Todays inspection was just for the supply piping to the FDC that runs under the floor. The piping in itself is ok but the combustible concealed spaces on both side of the gym need to be addressed. I spoke to Tim Frost in plan review and he was going to follow up with the contractor. Piping can not be covered until this is resolved due to needing access to install additional piping , if required.
Mark Jensen is the contact for this rough-in for the FDC. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Conference | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | DONE |
Jim Page
|
|
|
Discussed location for FDC, FDC will be installed on the eastern side of the north wall next to emergrncy exit door instead of the east wall.
|
INSP-Sprinkler Rough-in | 3/15/2018 | 3/15/2018 | 3/15/2018 | P | CANC |
Jim Page
|
|
|
Request is for a conference, this request is cancelled.
|