Information based on query as of Monday, May 6, 2024.
Permit Information
Permit NumberFIR18-00892
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 2638 W BEDFORD LN
Project NameBedford 5-plex
Customer Number 
ePlanReviewYes
Description
[Bedford 5-Plex]
The fire sprinkler scope of work consists of two level five plex. New 2 ½”x80’± CPVC underground piping will supply a 2” backflow preventer, 2” header with floor control valves.
Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
[BLD18-na]
There does not seem to be an associated building permit at this time.

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/19/20203/23/20203/23/2020PPASS
DetailsTroy Cobbley
Permit finaled. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Final Inspection3/17/20203/18/20203/18/2020AFAIL
DetailsTroy Cobbley
No access due to sign on the door. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Final Inspection2/13/20202/18/20202/18/2020AFAIL
DetailsTroy Cobbley
There is still exposed cpvc piping.

Phone #: ###-#### Inspection requested via web by Jim Danes
INSP-Final Inspection1/17/20201/22/20201/22/2020PFAIL
DetailsTroy Cobbley
To final permit all of the CPVC piping needs to be covered/protected per the UL listing as discussed. The interconnection with the fire alarm panel has been tested. The riser room needs to be one hour and verified by the building inspector.

Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in/Hydro1/7/20201/8/20201/8/2020ADONE
DetailsJim Page
Hydrostatic test witnessed for overhead fire sprinkler piping, no pressure loss observed.

overhead hydro 1st and 2nd floor Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in/Hydro12/6/201912/9/201912/9/2019PCANC
DetailsTroy Cobbley
Needed flush not rough-in.

Barry is ready for you. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Supply line flush12/9/201912/9/201912/9/2019PPASS
DetailsTroy Cobbley
Underground flush witnessed.

Barry is ready for you. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in11/26/201911/27/201911/27/2019APASS
DetailsTroy Cobbley
The underground supply piping is ok for cover. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in11/14/201911/14/201911/14/2019PPASS
DetailsTroy Cobbley
The tenting is approved on the second floor only as per the email/letter from American Fire taking responcibility for the the tenting installation. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in10/17/201910/21/201910/21/2019AFAIL
DetailsTroy Cobbley
Not enough access provided to verify tenting. Provide additional access and a letter as discussed for owner to take responcibility for work performed on the tenting as discussed. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in10/17/201910/18/201910/17/2019ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Connie Danes Inspection cancelled from web by: Connie Danes
INSP-Sprinkler Rough-in10/10/201910/11/201910/11/2019PFAIL
DetailsTroy Cobbley
No access to the single level and tenting is not correct for the two level area. Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in9/26/20199/27/20199/27/2019PPART
DetailsTroy Cobbley
Tenting failed for all areas. No piping to be covered. Rough-in passed for the single level area of work but again no piping can be covered. Also prior to a final inspection R38 insulation value will need to be provided.

Phone #: ###-#### Inspection requested via web by Connie Danes
INSP-Sprinkler Rough-in/Hydro5/21/20195/22/20195/22/2019PPART
DetailsTroy Cobbley
Rough-in passed for the two story section of the project, this includes first and second floor. The opening made to install the piping can be repaired. Another rough-in inspection will be requried to verify that the existing blow-in insulation has been removed from below the new piping and adequate tenting has been provided over the new piping. This inspection needs to happen before the new blow-in insulation is installed. A partial hydro test was witnessed for this two story area and no loss on the second floor but a visible loss for the first floor. The single level area of the project is not ready for inspection yet.

Phone #: ###-#### Inspection requested via web by Connie Danes