INSP-Final Inspection | 3/12/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Final Inspection | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | CANC |
Troy Cobbley
|
|
|
Not ready for final until the interconnection with the fire alarm has been tested. Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Troy Cobbley
|
|
|
The remaining sprinkler piping on the first floor is ok for cover. Forward flush test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro's passed. Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | CANC |
Troy Cobbley
|
|
|
Please give me a call it will be for standpipe 2nd through 4th. as late in day as possible Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 2/20/2020 | 2/21/2020 | 2/21/2020 | A | PASS |
Troy Cobbley
|
|
|
The revised location for the earth quake bracing at the Risers is ok. Piping above the hardlids in the 1st floor entry lobby is ok for cover.
Thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | PASS |
Troy Cobbley
|
|
|
Piping to the 2nd and 4th floor linen shoot heads is ok for cover.
Contact: Jeremiah Robison rough to cover of laundry chute Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
INSP-Sprinkler Rough-in | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | PART |
Troy Cobbley
|
|
|
EQ bracing on 1st floor corridor pass. Piping on 1st floor corridir pass. Fire penetration need to be finished, also patching of sheetrock around EQ bracing needs to be completed and inspected before ok to cover.**MAS**
as late as possible Phone #: ###-#### >> Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 1/6/2020 | 1/6/2020 | 1/6/2020 | P | PASS |
Troy Cobbley
|
|
|
Previous noted corrections for the 1st floor ADA room has been addressed. Piping can be covered. 1st floor Nick will be the contact and on site today. Thank you have a great day Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | FAIL |
Jim Page
|
|
|
ADA room level 1 has open outlet above hard-lid, outlet is for sprinkler head in combustible concealed space behind bathtub, piping/head is not installed at time of inspection. Restraint clip for pendant fire sprinkler head in same ADA bathroom is not installed. Pipe size for electrical room (piping from double queen ext room, west of ADA room supplies electrical room) behind storage room shows 1 inch on city approved drawings, 1 1/2 pipe appears to be whats installed, not 1 inch as shown on drawings.
1st floor rooms drop ceilings. Thank you. Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 12/26/2019 | 12/27/2019 | 12/27/2019 | A | FAIL |
Jim Page
|
|
|
Add thrust clips on hangers next to sprinkler heads or make all thread rod long enough to keep the sprinkler head from thrusting up during head activation as required for CPVC, inspection was stopped after multiple heads found without sprinkler head vertical restraint.
rough on 1st floor guest rooms. Thank you Sir have a great day Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PASS |
Troy Cobbley
|
|
|
The underground supply line hydro was witnessed with no pressure loss on the second try.
Nick is the contact thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Supply line flush | 12/4/2019 | 12/4/2019 | 12/4/2019 | P | PASS |
Troy Cobbley
|
|
|
The underground flush was witnessed.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Troy Cobbley
|
|
|
2nd floor hard lids are ok for cover. thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the sofits in the 3rd floor corridor are ok for cover.
looking to cover a few lids in the hall. Thank you have a good day Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 11/15/2019 | 11/15/2019 | 11/15/2019 | P | PASS |
Troy Cobbley
|
|
|
The 2" corridor piping on the third and fourth floors has had the earth quake bracing installed. The sprinkler piping in the fourth floor corridor soffits can be covered. Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 11/5/2019 | 11/5/2019 | 11/5/2019 | P | PASS |
Troy Cobbley
|
|
|
The tenting in room 406 has been corrected. Piping can be covered. Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | PART |
Troy Cobbley
|
|
|
The remainging tenting is passed on the 4th floor except for room 406 which needs the insulation modified. So all room piping can be covered except room 406.
Eric is the contact. it is to look at the west side 3rd and 4th thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | PASS |
Troy Cobbley
|
|
|
Tenting on 4th floor, all rooms east of the elevator, are ok for cover. Contractor stated that a foil barrier will be installed at the bottom of the trusses. I let him know that if it blocked the transfer of heat that it could not be approved. Per him the architect has approved it. Sprinkler piping for the fourth floor east of the elevator is ok for cover.
Contact: Eric Robinson Phone #: ###-#### Inspection requested via web by Hunter Fillmore
|
INSP-Sprinkler Rough-in | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | PART |
Troy Cobbley
|
|
|
Todays inspection was a rough-in for the fourth floor. Rough-in passed for the rooms but piping can not be covered until a tenting inspection has passed. The corridor piping still needs bracing installed. Heads at elevator and shaft need installed.
Please give 30min heads up. Contact Eric Robinson Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 10/14/2019 | 10/15/2019 | 10/15/2019 | P | PART |
Troy Cobbley
|
|
|
**2nd, 3rd floors, and stairwells OK to cover. Sidewalls changed to Viking EC's in guest rooms over 18'-0"*MAS***
Nick is the contact thank you Phone #: ###-#### >> Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 10/7/2019 | 10/7/2019 | 10/7/2019 | P | PART |
Troy Cobbley
|
|
|
The inspection for the second and third floors failed due to the sidewall heads being overspaced. Perm plan review their max spacing is 18'out and 16' to the side. They have been installed 18'-6" from the far wall. What is approved are the hangers for the stand pipe supplies in the east and west stair wells and the short run of 4" to the FDC. Plan modifications will be required for sprinkler modifications to provide the correct coverage. Nick is the contact. Thank you Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | PASS |
Troy Cobbley
|
|
|
Hanger inspection for pre-rock on 1st, 2nd and third floors passed. Also hangers are ok for cover in the riser room and mechanical room.
Nick Curtis is the contact. Phone #: ###-#### Inspection requested via web by jeremiah robison
|