Print Statement | | | 8/12/2019 | | DONE |
|
|
|
|
First Notice | | 7/29/2019 | 8/2/2019 | | DONE |
|
|
|
mailed 8/5/19
|
BLD-Final | 7/18/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Mike Jordan
|
|
|
Chad Phone #: ###-####
|
Permanent Occupancy | | | 7/19/2019 | | DONE |
|
|
|
|
BLD-Final | 7/2/2019 | 7/8/2019 | 7/8/2019 | P | CANC |
Mike Jordan
|
|
|
Frankie-elevator only Phone #: ###-####
|
FIRE-Final Inspection | 7/2/2019 | 7/5/2019 | 7/5/2019 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
Frankie-elevator only Phone #: ###-####
|
FIRE-Final Inspection | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Franky Phone #: ###-####
|
Temporary Occupancy | 6/21/2019 | 9/19/2019 | 6/21/2019 | | DONE |
Judith Amador
|
|
|
|
BLD-Final | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PASS |
Mike Jordan
|
|
|
Franky- Phone #: ###-####. OK for temp occ. Will be ok or perm occ. once trades sign perm.
|
FIRE-Final Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is ok with Chief Ron's permission until the elevator has been installed and tested. Chad Phone #: ###-####
|
Plan assigned to (JG) | 6/11/2019 | 6/11/2019 | 6/18/2019 | | PASS |
Javier Guzman
|
|
|
Plan Mod Floor Trader Outlet ePlan
|
Permit Ready to Issue | | | 6/18/2019 | | DONE |
|
|
|
DO NOT ISSUE- plan mod
|
CHANGE STATUS TO (ISS) | | | 6/18/2019 | | DONE |
|
|
|
plan mod
|
Routing - FIRE | 6/17/2019 | 6/17/2019 | 6/17/2019 | | PASS |
Erika Akin
|
|
|
Change in FD access approved via email 5-3 from Ron Johnson. Two paved access points must be maintained as shown.
|
Routing PW Drainage | 6/17/2019 | | 6/17/2019 | | PASS |
Brian Murphy
|
|
|
APPROVED UNDER GRADING PERMIT
|
Routing PW Street Lights | 6/17/2019 | | 6/17/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 6/17/2019 | | 6/17/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 6/17/2019 | | 6/17/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 6/17/2019 | | 6/17/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 6/12/2019 | | DONE |
Javier Guzman
|
|
|
plan mod prescreen failed for the following
Provide and upload the following:
1. A completed plan modification application required (app found at https://www.cityofboise.org/media/5655/522_planmod.pdf)
2. The uploaded revised sheet A101 is not acceptable as this plan sheet has the city approved stamp on the bottom right corner, this revised sheet A101 will need to be a new sheet that does not show the previous approved city stamp
|
Plan Reviewer's activity | | | 6/12/2019 | | |
|
|
|
Plan Mod prescreen failed
Provide and upload the following:
1. Request for Plan modification application not addressed 6/12/2019
Provide and upload a completed plan modification application required (application found at https://www.cityofboise.org/media/5655/522_planmod.pdf)
|
BLD-Final | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | DONE |
Mike Jordan
|
|
|
Walk through. Needs to complete fire caulking and lower breakroom counter. for ADA.
|
BLD-Final | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | CANC |
Mike Jordan
|
|
|
Chad Phone #: ###-####
|
PubWorks Occupancy Approval | 6/11/2019 | 6/11/2019 | 6/11/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Plan Modification Accepted | | | 6/11/2019 | | DONE |
|
|
|
plan mod per Wesley Steel. Delete pavement on west and south sides of Lot 2 access until such time as Lot 2 is developed
|
Zoning Approval | 6/10/2019 | 6/10/2019 | 6/10/2019 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 6/7/2019 | 6/7/2019 | 6/7/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide sign offs for the project related fire sprinkler and fire alarm permits, Provide emergency light for the Fire Pump Room, Provide testing/inspection for the elevator, Provide singage for the Fire Pump/Riser Room.
Chad- Phone #: ###-####
|
FIRE-Conference | 5/24/2019 | 5/24/2019 | 5/24/2019 | P | DONE |
Troy Cobbley
|
|
|
Chad and I spoke about fire dept signage, addressing and inspection scheduling for fire pump certification.
|
BLD-Ceiling Grid Inspection | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Mike Jordan
|
|
|
Chad Phone #: ###-####. 1st. floor ceiling grid ok.
|
BLD-Framing/Rough-in | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PASS |
Mike Jordan
|
|
|
Chad Phone #: ###-####. fireblocking around duck work at 2nd. floor penetrations.
|
BLD-Framing/Rough-in | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PART |
Jim Sly
|
|
|
chad Phone #: ###-#### Roof screenwall framing.....OK.
|
BLD-Wall Bracing | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | FAIL |
Mike Jordan
|
|
|
chad Phone #: ###-####Steel stud framing for screen walls on roof. Needs to provide more screws as per the approved plans.
|
BLD-Wall cover | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PART |
Dave Hannah
|
|
|
Chad Phone #: ###-#### inter layer of sheet rock at stairs ok
|
BLD-Framing/Rough-in | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Mike Jordan
|
|
|
chad Phone #: ###-####. Interior steel stud framed walls 1st. floor ok.
|
BLD-Foundation | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Mike Jordan
|
|
|
rebar Phone #: ###-####. Reinforcement for interior slab on grade at 2nd floor.
|
FIRE-Conference | 4/5/2019 | 4/9/2019 | 4/9/2019 | A | DONE |
Troy Cobbley
|
|
|
Chad and I went over fire extinguisher placement, knox box location (deferred to Fire Dept), fire pump room requirements and sprinkler obstructions and small safety factor for the overhead system.
Chad Phone #: ###-####
|
FIRE-Conference | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | CANC |
Jim Page
|
|
|
Rescheduled conference for 09APR2019 per conversation with point of contact.
Chad Phone #: ###-####
|
BLD-Conference | 4/2/2019 | 4/3/2019 | 4/3/2019 | A | DONE |
Mike Jordan
|
|
|
Chad ###-####
|
BLD-Other | 3/29/2019 | 4/1/2019 | 4/1/2019 | A | PART |
Mike Jordan
|
|
|
welding for mezzanine // Chad Phone #: ###-####. Work in progress on puddle welds on mezz. decking. Ok for concrete pending special inspection.
|
BLD-Foundation | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | CANC |
Mike Jordan
|
|
|
rebar // chad Phone #: ###-####
|
BLD-Concrete | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PART |
Mike Jordan
|
|
|
Chad- Rebar inspction Phone #: ###-####. Cmu wall, FF to 4ft. elevation. Ok pending special inspection.
|
BLD-Foundation | 3/4/2019 | 3/4/2019 | 3/4/2019 | P | DEFR |
Mike Jordan
|
|
|
masonry rebar // Chad Phone #: ###-####
|
BLD-Foundation | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Mike Jordan
|
|
|
Chad Phone #: ###-####. MAsonry elevator shaft, top of stemwall to 4ft. elevation. Will do hight lift, cleanouts ok, engineer of record ok. Ok pending special inspection.
|
BLD-Other | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | DEFR |
Mike Jordan
|
|
|
welding // Chad Phone #: ###-####.
|
BLD-Foundation | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | CANC |
Mike Jordan
|
|
|
rebar - pouring at 2pm // Chad Phone #: ###-####
|
BLD-Foundation | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | PART |
Mike Jordan
|
|
|
Chad Phone #: ###-####. Work in progress on rebar for tilt panels. Engineer of record to provide RFI for panels #27 and #29 noting in place reinforcement is ok. Special inspector on site. ok to place concrete pending special inspection.
|
BLD-Foundation | 1/29/2019 | 1/30/2019 | 1/30/2019 | P | PART |
Mike Jordan
|
|
|
Chad Phone #: ###-####. Panels 22 through 30. panels 27 and 29 rebar is incorrect. Ok to place concregte pending special inspection.
|
BLD-Footing | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PART |
Mike Jordan
|
|
|
Chad-footings & panel Phone #: ###-#### Work in progress. Special inspector on site. Ok to place concrete pending special inspection.
|
BLD-Foundation | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | DEFR |
Mike Jordan
|
|
|
rebar // Chad Phone #: ###-####
|
BLD-Foundation | 12/12/2018 | 12/13/2018 | 12/13/2018 | P | PASS |
Mike Jordan
|
|
|
rebar // chad Phone #: ###-####. Panels 1,2,3,4,5 and 6 ok.
|
BLD-Other | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PART |
Dave Hannah
|
|
|
rebar // Chad Phone #: ###-#### wire mess ok
|
BLD-Foundation | 11/8/2018 | 11/9/2018 | 11/9/2018 | P | PART |
Mike Jordan
|
|
|
Chad=-slab Phone #: ###-####. Work in progress on interior thickend footings and interior slab on grade. Will have special inspection.
|
BLD-Foundation | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | CANC |
Mike Jordan
|
|
|
Chad-slab-would like as late as possible Phone #: ###-####
|
BLD-Foundation | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
Mike Jordan
|
|
|
rebar // Chad Phone #: ###-####. Interior and exterior column pad footings.
|
Issue PAID IN FULL permit | | | 11/1/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/1/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2018 | | DONE |
|
|
|
brian @ bblack@petrainc.net
|
Routing - Design Review | 10/31/2018 | | 10/31/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Design Review | 10/31/2018 | | 10/31/2018 | | PASS |
Andrea Tuning
|
|
|
Changemark removed
|
CHANGE STATUS TO (RDY) | | | 10/31/2018 | | DONE |
|
|
|
not sure how it was changed back into REV status
|
Routing PW Drainage | 10/31/2018 | | 10/31/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 10/16/2018 | 10/16/2018 | 10/30/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Plan assigned to (JG) | 8/16/2018 | 8/16/2018 | 10/30/2018 | | PASS |
Javier Guzman
|
|
|
1st rev comp, 9/20 CJD Investments New ePlan, pend fire and eng
|
Routing Off Site - STRUCTURAL | 10/16/2018 | | 10/30/2018 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by KPFF Jordan Terry
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/16/2018 | | 10/24/2018 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLANNING | 10/16/2018 | | 10/23/2018 | | PASS |
Andrea Tuning
|
|
|
No review required for Current Planning
|
Routing PW Sewer Design | 10/16/2018 | | 10/17/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Drainage | 10/16/2018 | | 10/17/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLUMBING | 10/16/2018 | | 10/16/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 10/16/2018 | | 10/16/2018 | | PASS |
Andrea Tuning
|
|
|
|
Route to Impact Fee Review | 9/27/2018 | 9/30/2018 | 10/4/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/21/2018 | 8/21/2018 | 9/27/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
1st review completed | | | 9/27/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/21/2018 | | 9/21/2018 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 8/21/2018 | | 9/11/2018 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by KPFF Jordan Terry
|
Routing - Design Review | 8/21/2018 | | 9/11/2018 | | FAIL |
Andrea Tuning
|
|
|
Failed in ePlan by DR Andrea Tuning (DRH18-00208)
|
Routing PW Environmental | 8/22/2018 | | 8/29/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 8/22/2018 | | 8/23/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - MECHANICAL | 8/21/2018 | | 8/23/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/21/2018 | | 8/22/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Design | 8/22/2018 | | 8/22/2018 | | FAIL |
DeAnn Brown
|
|
|
Please show and label existing 3" pressure sewer pipeline that crosses east/west through the parking lot to connection manhole on sheet C-5 and all other applicable utility/demo sheets. This pipeline passes under the new 6" fire water line. I can provide record drawings (drbrown@cityofboise.org).
|
Routing PW Street Lights | 8/22/2018 | | 8/22/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 8/22/2018 | | 8/22/2018 | | FAIL |
Brian Murphy
|
|
|
need perc test
|
Routing - Addressing | 8/21/2018 | | 8/22/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/21/2018 | | 8/22/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Erosion and Sediment | 8/21/2018 | | 8/21/2018 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC18-01130 which was issued with GRD18-00064
|
Routing - PLANNING | 8/21/2018 | | 8/21/2018 | | FAIL |
Andrea Tuning
|
|
|
Light poles must be lcoated outside the setbacks.
Planter islands must be 9-feet wide.
|
Plans ACCEPTED BY PLAN TECH | | | 8/21/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/21/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/16/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/7/2018 | | FAIL |
Julie Romig
|
|
|
1. Owner's signature on form 310.
2. Shallow Injection Well Inventory form indicated on checklist but not provided - please upload.
3. Sheet 11-CSUEZ-1_SUEZ WATER PLAN" is missing stamp/signature.
4. Mechanical Sheets M002 and M003 are too large to open. Reduce file size to less than 1 MB and reupload.
5. Per submittal standards, a 4” x 2” space located 3” off the right sheet edge is to be left blank for the city stamp. Reupload sheets that do not have this blank space.
Thank you,
|
Application received | | | 8/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2018 11:51AM
|