BLD-Final | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | PASS |
Tell Riley
|
|
|
PATT Phone #: ###-####//corrections made//window opening devices installed on windows under 36" sill--only a couple units//all other required inspections complete--verified online//signed card for all units//
|
Permanent Occupancy | | | 10/24/2019 | | DONE |
|
|
|
|
BLD-Final | 10/23/2019 | 10/23/2019 | 10/23/2019 | P | NR |
Tell Riley
|
|
|
Pat Phone #: ###-####//need to fire caulk around furnaces// need to adjust door hinge springs//
|
FIRE-Final Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Matt Phone #: ###-####
|
FIRE-Final Inspection | 10/18/2019 | 10/21/2019 | 10/21/2019 | A | FAIL |
Troy Cobbley
|
|
|
The smoke alarm in 102 still has not been relocated.
Matt Phone #: ###-####
|
FIRE-Final Inspection | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety on units 101 202 203 302 303 103 104 203 204 303 304 is complete. 102 had a smoke alarm too close to the restroom door. // Matt ###-####
|
BLD-Final | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PART |
Tell Riley
|
|
|
partial final for apartments 105, 106, 205, 206, 305 and 306// Matt ###-####//the six listed above ok for temp occupancy//
|
FIRE-Final Inspection | 10/14/2019 | 10/15/2019 | 10/15/2019 | A | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 105, 106, 205, 206, 305 and 306.
matt Phone #: ###-####
|
PubWorks Occupancy Approval | 10/14/2019 | 10/14/2019 | 10/14/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 10/11/2019 | 10/11/2019 | 10/11/2019 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 10/10/2019 | 10/10/2019 | 10/10/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for apartments 107,108, 207, 208, 307 and 308.- Pat Phone #: ###-####
|
BLD-Energy code compliance | 9/10/2019 | 9/10/2019 | 9/10/2019 | P | PASS |
Tell Riley
|
|
|
mATT Phone #: ###-####//last six units//101,102,201,202,301,303//ok to cover//
|
FIRE-Final Inspection | 9/6/2019 | 9/9/2019 | 9/9/2019 | A | FAIL |
Jim Page
|
|
|
As noted in Troy Cobbleys entry on the 29AUG2019 inspection request, tenting inspection for fire sprinklers needs to be requested under the associated FIR permit, not the BLD permit.
tinting.... last six // Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Tell Riley
|
|
|
pat Phone #: ###-####/last six units ok to insulate//will check minor corrections at insulation inspection//
|
BLD-Energy code compliance | 8/30/2019 | 9/3/2019 | 9/3/2019 | A | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//corrections made//ok to cover//fire sprinklers were approved per troy//103,104,203,204,303,304//
|
BLD-Other | 8/28/2019 | 8/29/2019 | 8/29/2019 | A | FAIL |
Troy Cobbley
|
|
|
Wrong inspection number scheduled. Should be a FIR. Tenting is not approved. tenting // Pat Phone #: ###-####
|
BLD-Framing/Rough-in | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | PART |
Tell Riley
|
|
|
Matt Phone #: ###-####//corections onsite//ok to insualate walls only//need tenting and sprinkler inspection prior to energy inspection//do not cover or insulate any sprinklers or associated piping//103,104,203,204,303,304//
|
BLD-Energy code compliance | 8/20/2019 | 8/21/2019 | 8/21/2019 | P | PART |
Tell Riley
|
|
|
Matt- Phone #: ###-####//105,106,205,206,305,306//
|
BLD-Framing/Rough-in | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | PASS |
Tell Riley
|
|
|
2nd six // Pat Phone #: ###-####//framing for 105.106.205.206.305.306//add bearing blocks under trusses//ok to insulate//
|
BLD-Energy code compliance | 8/8/2019 | 8/8/2019 | 8/9/2019 | P | PASS |
Tell Riley
|
|
|
Matt Phone #: ###-####//framing corrections made//107,108,207,208,307,308 only//
|
BLD-Framing/Rough-in | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PART |
Tell Riley
|
|
|
Pat Phone #: ###-####//first six 7's and 8's ok to insulate//get fire sprinkler rough prior to insulation//check list of corrections with Pat onsite.//
|
PubWorks Temp Occupancy Appr | 7/18/2019 | 7/18/2019 | 7/18/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Wall Bracing | 6/18/2019 | 6/18/2019 | 6/18/2019 | P | PASS |
Tell Riley
|
|
|
shear // bill Phone #: ###-####//shear nailing and holddowns ok per plans//
|
BLD-Foundation | 3/18/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 3/15/2019 | 3/18/2019 | 3/18/2019 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 3/13/2019 | 3/14/2019 | 3/14/2019 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 3/13/2019 | 3/14/2019 | 3/13/2019 | A | PASS |
Dave Hannah
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/12/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 3/12/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/1/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 9/26/2018 | 9/26/2018 | 3/1/2019 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 4th Rev Comp - 506 Fairview Apartments Bldg 3
|
Routing - PLAN CHECK | 3/1/2019 | | 3/1/2019 | | PASS |
Julie Romig
|
|
|
4th Review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/1/2019 | | DONE |
|
|
|
NEED- ALL MET
RP (EXPIRED)
GC FORM
REVISED VALUE
|
Routing - PLAN CHECK | 2/19/2019 | | 2/28/2019 | | FAIL |
Julie Romig
|
|
|
4th Review - Stamp covers framing plan on sheet S1.05. Please reupload with stamp relocated off drawing.
Also, please confirm that sheet 37.1 A-107 can be deleted.
|
Extend Review Timeline | | | 2/22/2019 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Meeting | | | 2/12/2019 | | DONE |
|
|
|
jeremy sent in request for extension
|
Routing PW Street Lights | 2/7/2019 | | 2/8/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 2/7/2019 | | 2/7/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing Off Site - STRUCTURAL | 1/10/2019 | | 1/17/2019 | | PASS |
Julie Romig
|
|
|
AHJ
|
Routing - PLAN CHECK | 1/10/2019 | | 1/17/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLANNING | 1/10/2019 | | 1/11/2019 | | PASS |
Susan Riggs
|
|
|
|
Route to Impact Fee Review | 11/13/2018 | 11/16/2018 | 11/14/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 9/26/2018 | 9/26/2018 | 11/13/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 11/13/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 9/26/2018 | | 11/8/2018 | | FAIL |
Julie Romig
|
|
|
Plan Review report emailed to applicant.
|
Routing Off Site - STRUCTURAL | 9/26/2018 | | 10/10/2018 | | FAIL |
Julie Romig
|
|
|
AHJ - Corrections Required per ePlanReview
|
Routing - MECHANICAL | 9/26/2018 | | 10/3/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 9/26/2018 | | 10/2/2018 | | PASS |
Dan Ediger
|
|
|
Per ISPC
|
Routing - Design Review | 9/26/2018 | | 10/2/2018 | | PASS |
Andrea Tuning
|
|
|
DRH17-532 Andrea
|
Routing - Addressing | 9/26/2018 | | 10/1/2018 | | PASS |
Doug Chausow
|
|
|
Updated parcel number and Address: 11715 W King St, Apts 101-103
|
Routing PW Street Lights | 9/27/2018 | | 10/1/2018 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 9/27/2018 | | 10/1/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Sewer Rating | 9/27/2018 | | 10/1/2018 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | 9/27/2018 | | 9/28/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 9/27/2018 | | 9/28/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 9/26/2018 | | 9/27/2018 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 9/26/2018 | | 9/27/2018 | | PASS |
Andy J. Long
|
|
|
SWPPP approved. Valid stormwater team designated. Site already started under GRD18-00035, no site prep required.
|
Routing - PLANNING | 9/26/2018 | | 9/26/2018 | | FAIL |
Susan Riggs
|
|
|
PUD17-22 Susan
APPLICANT MUST POST BOND FOR AMENITES
|
Intake Approval | | | 9/21/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/28/2018 | | FAIL |
Joe Bruce
|
|
|
1. Verification of legal lot or parcel form must be signed/dated by PDS subdivision staff.
2. Sheet A-1.1 does not call out or designate any fire hydrants. Resubmit with this information.
3. Provide architectural stamp / signature on (A-205, A-402, A402.1, A-403, A-404, A-405, A-406)
4. Provide and upload form #310 - Statement of Special Inspections completed and stamped by the design engineer for all special inspections noted on sheet S0.01
5. Incorrect codes are referenced on sheet G002. Resubmit with currently adopted codes by City of Boise. (see redlines)
6. Incorrect version of IECC is used on G008 and G009. Resubmit with 2015 IECC
7. I did not see the Manual J report in the "Documents" folder or referenced on the drawings. Please upload the Manual J , Manual D, and Manual S reports noted on the checklist.
|
Application received | | | 8/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 27 2018 10:27AM
|
First Notice | | 11/3/2019 | | | |
|
|
|
|