INSP-Final Inspection | 11/26/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection is complete.
Contact Ken Orahood ###-#### 30 min prior to Final Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
Fees Due Hold | 10/30/2019 | | 11/26/2019 | | DONE |
|
|
|
|
INSP-Final Inspection | 10/28/2019 | 10/29/2019 | 10/29/2019 | A | FAIL |
Jim Page
|
|
|
Install missing head in entry room 101, heads in kitchen area overspaced off of wall room 101. head painted in room 102, sprinkler head to close to ceiling fan room 102. Missing escutcheon on balcony, room 103. Sprinkler head to close to ceiling fan room 104. sidewall deflector above wood beam room 202 balcony, head sticking to far down through ceiling room 202. Inspection stopped due to defecincies.
Contact Noemi Carrero ###-#### 30 min prior to Final Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 10/24/2019 | 10/25/2019 | 10/25/2019 | A | CANC |
Jim Page
|
|
|
Contact Noemi Carrero - ###-#### 30 min prior to Final Insp start please
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Final Inspection | 10/23/2019 | 10/23/2019 | 10/23/2019 | P | FAIL |
Jim Page
|
|
|
Provide restricted orifice for inspectors test. Provide annual inspection for backflow assembly. Repair visible leak on riser piping.
Contact Noemi Carrero ###-#### 30 min prior to Final Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 10/14/2019 | 10/18/2019 | 10/18/2019 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Noemi due to the project related fire alarm not being ready. Contact Noemi Carrero ###-#### 30 min prior to Final Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for FDC witnessed, no pressure loss observed.
Contact Noemi Carrero ###-#### 30 Min Prior to Hydro on FDC Insp please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Final Inspection | 6/20/2019 | 6/24/2019 | 6/24/2019 | A | CANC |
Jim Page
|
|
|
Contact Ken Orahood ###-#### 30 min prior to Final Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 6/17/2019 | 6/17/2019 | 6/17/2019 | P | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, overhead fire sprinkler piping approved for cover.
Point of contact is Ken Orahood ###-#### please contact him 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2019 | 5/21/2019 | 5/21/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
Contact Leroy Anderson ###-#### 30 Min Prior to Hydro Insp start please
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 5/9/2019 | 5/13/2019 | 5/13/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for levels 1 and 2 complete, levels 1 and 2 approved for cover. Level 3 rough in inspection complete, tenting/insulation to be installed at a later date, an inspection for tenting is required before cover can be approved, level 3 cover is not approved as of this inspection.
Contact Noemi Carrero ###-#### 30 Min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
Plan Modification Accepted | | | 4/29/2019 | | DONE |
|
|
|
Teri with Phoenix fire Protection requested a plan mod
|
Plan Modification Accepted | | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/29/2019 | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/29/2019 | | 4/29/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/29/2019 | | DONE |
Mark Stumbaugh
|
|
|
No Fee
|
Permit Ready to Issue | | | 4/29/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/29/2019 | | DONE |
|
|
|
NO FEES PER MARK STU
|
INSP-Sprinkler Rough-in/Hydro | 4/25/2019 | 4/26/2019 | 4/25/2019 | A | CANC |
Jim Page
|
|
|
Contact Tyler Loomis ###-#### 30 Min Prior to Hydro Insp start please.
Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in | 4/24/2019 | 4/25/2019 | 4/25/2019 | P | FAIL |
Jim Page
|
|
|
Need to verify that the dry flex heads used will be supported by the system calcs.
Contact Tyler Loomis ###-#### 30 min prior to RTC Insp start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Supply line flush | 4/23/2019 | 4/25/2019 | 4/25/2019 | A | CANC |
Jim Page
|
|
|
Underground supply is on different permit, this request is cancelled.
Contact Tyler Loomis - ###-#### 30 min prior to Flush Insp. start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
Issue and Print Permit | | | 2/21/2019 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/19/2019 | | 2/20/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/20/2019 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 2/19/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/19/2019 | | 2/19/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/14/2019 | | 2/15/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Corrections needed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/14/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 14 2019 11:47AM
|
Intake Approval | | | 2/14/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/14/2019 | | 2/14/2019 | | DONE |
Mark Stumbaugh
|
|
|
|