BLD-Final | 7/18/2019 | 7/19/2019 | 7/19/2019 | A | PASS |
Mike Jordan
|
|
|
Chad Phone #: ###-####
|
BLD-Final | 7/2/2019 | 7/8/2019 | 7/8/2019 | P | CANC |
Mike Jordan
|
|
|
Frankie-elevator only Phone #: ###-####
|
FIRE-Final Inspection | 7/2/2019 | 7/5/2019 | 7/5/2019 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
Frankie-elevator only Phone #: ###-####
|
FIRE-Final Inspection | 7/3/2019 | 7/3/2019 | 7/3/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Franky Phone #: ###-####
|
BLD-Final | 6/19/2019 | 6/20/2019 | 6/20/2019 | A | PASS |
Mike Jordan
|
|
|
Franky- Phone #: ###-####. OK for temp occ. Will be ok or perm occ. once trades sign perm.
|
FIRE-Final Inspection | 6/18/2019 | 6/19/2019 | 6/19/2019 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is ok with Chief Ron's permission until the elevator has been installed and tested. Chad Phone #: ###-####
|
BLD-Final | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 6/11/2019 | 6/11/2019 | 6/11/2019 | P | DONE |
Mike Jordan
|
|
|
Walk through. Needs to complete fire caulking and lower breakroom counter. for ADA.
|
BLD-Final | 6/10/2019 | 6/11/2019 | 6/11/2019 | A | CANC |
Mike Jordan
|
|
|
Chad Phone #: ###-####
|
FIRE-Final Inspection | 6/7/2019 | 6/7/2019 | 6/7/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide sign offs for the project related fire sprinkler and fire alarm permits, Provide emergency light for the Fire Pump Room, Provide testing/inspection for the elevator, Provide singage for the Fire Pump/Riser Room.
Chad- Phone #: ###-####
|
FIRE-Conference | 5/24/2019 | 5/24/2019 | 5/24/2019 | P | DONE |
Troy Cobbley
|
|
|
Chad and I spoke about fire dept signage, addressing and inspection scheduling for fire pump certification.
|
BLD-Ceiling Grid Inspection | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Mike Jordan
|
|
|
Chad Phone #: ###-####. 1st. floor ceiling grid ok.
|
BLD-Framing/Rough-in | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | PASS |
Mike Jordan
|
|
|
Chad Phone #: ###-####. fireblocking around duck work at 2nd. floor penetrations.
|
BLD-Framing/Rough-in | 5/1/2019 | 5/2/2019 | 5/2/2019 | A | PART |
Jim Sly
|
|
|
chad Phone #: ###-#### Roof screenwall framing.....OK.
|
BLD-Wall Bracing | 5/1/2019 | 5/1/2019 | 5/1/2019 | P | FAIL |
Mike Jordan
|
|
|
chad Phone #: ###-####Steel stud framing for screen walls on roof. Needs to provide more screws as per the approved plans.
|
BLD-Wall cover | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PART |
Dave Hannah
|
|
|
Chad Phone #: ###-#### inter layer of sheet rock at stairs ok
|
BLD-Framing/Rough-in | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PASS |
Mike Jordan
|
|
|
chad Phone #: ###-####. Interior steel stud framed walls 1st. floor ok.
|
BLD-Foundation | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PASS |
Mike Jordan
|
|
|
rebar Phone #: ###-####. Reinforcement for interior slab on grade at 2nd floor.
|
FIRE-Conference | 4/5/2019 | 4/9/2019 | 4/9/2019 | A | DONE |
Troy Cobbley
|
|
|
Chad and I went over fire extinguisher placement, knox box location (deferred to Fire Dept), fire pump room requirements and sprinkler obstructions and small safety factor for the overhead system.
Chad Phone #: ###-####
|
FIRE-Conference | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | CANC |
Jim Page
|
|
|
Rescheduled conference for 09APR2019 per conversation with point of contact.
Chad Phone #: ###-####
|
BLD-Conference | 4/2/2019 | 4/3/2019 | 4/3/2019 | A | DONE |
Mike Jordan
|
|
|
Chad ###-####
|
BLD-Other | 3/29/2019 | 4/1/2019 | 4/1/2019 | A | PART |
Mike Jordan
|
|
|
welding for mezzanine // Chad Phone #: ###-####. Work in progress on puddle welds on mezz. decking. Ok for concrete pending special inspection.
|
BLD-Foundation | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | CANC |
Mike Jordan
|
|
|
rebar // chad Phone #: ###-####
|
BLD-Concrete | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PART |
Mike Jordan
|
|
|
Chad- Rebar inspction Phone #: ###-####. Cmu wall, FF to 4ft. elevation. Ok pending special inspection.
|
BLD-Foundation | 3/4/2019 | 3/4/2019 | 3/4/2019 | P | DEFR |
Mike Jordan
|
|
|
masonry rebar // Chad Phone #: ###-####
|
BLD-Foundation | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Mike Jordan
|
|
|
Chad Phone #: ###-####. MAsonry elevator shaft, top of stemwall to 4ft. elevation. Will do hight lift, cleanouts ok, engineer of record ok. Ok pending special inspection.
|
BLD-Other | 2/25/2019 | 2/26/2019 | 2/26/2019 | A | DEFR |
Mike Jordan
|
|
|
welding // Chad Phone #: ###-####.
|
BLD-Foundation | 2/19/2019 | 2/20/2019 | 2/20/2019 | P | CANC |
Mike Jordan
|
|
|
rebar - pouring at 2pm // Chad Phone #: ###-####
|
BLD-Foundation | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | PART |
Mike Jordan
|
|
|
Chad Phone #: ###-####. Work in progress on rebar for tilt panels. Engineer of record to provide RFI for panels #27 and #29 noting in place reinforcement is ok. Special inspector on site. ok to place concrete pending special inspection.
|
BLD-Foundation | 1/29/2019 | 1/30/2019 | 1/30/2019 | P | PART |
Mike Jordan
|
|
|
Chad Phone #: ###-####. Panels 22 through 30. panels 27 and 29 rebar is incorrect. Ok to place concregte pending special inspection.
|
BLD-Footing | 12/20/2018 | 12/20/2018 | 12/20/2018 | P | PART |
Mike Jordan
|
|
|
Chad-footings & panel Phone #: ###-#### Work in progress. Special inspector on site. Ok to place concrete pending special inspection.
|
BLD-Foundation | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | DEFR |
Mike Jordan
|
|
|
rebar // Chad Phone #: ###-####
|
BLD-Foundation | 12/12/2018 | 12/13/2018 | 12/13/2018 | P | PASS |
Mike Jordan
|
|
|
rebar // chad Phone #: ###-####. Panels 1,2,3,4,5 and 6 ok.
|
BLD-Other | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PART |
Dave Hannah
|
|
|
rebar // Chad Phone #: ###-#### wire mess ok
|
BLD-Foundation | 11/8/2018 | 11/9/2018 | 11/9/2018 | P | PART |
Mike Jordan
|
|
|
Chad=-slab Phone #: ###-####. Work in progress on interior thickend footings and interior slab on grade. Will have special inspection.
|
BLD-Foundation | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | CANC |
Mike Jordan
|
|
|
Chad-slab-would like as late as possible Phone #: ###-####
|
BLD-Foundation | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
Mike Jordan
|
|
|
rebar // Chad Phone #: ###-####. Interior and exterior column pad footings.
|