Permit Information
Permit NumberBLD18-04521
StatusTemporary Occupancy
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 978 N MAPLE GROVE RD
Project NameRosewood Apartments Bldg 12
Customer NumberEPLAN BLD18-04520
ePlanReview 
Description
**2 BUILDING PERMITS IN EPLAN UNDER BLD18-04520** (ROSEWOOD APARTMENTS) (BUILDING #12) // 03/09/20 PLAN MOD #3 TO ADD FIRE DAMPER TO FRESH AIR INTAKE AT WEST STAIR. JAR //08/01/19 PLAN MOD TO UTILITY LINE LOCATIONS AND LANDSCAPE PLANS. JAR// Permit for the construction of a new 22,890 sq ft, 3-story, 18-unit apartment building (identified as Type VIII on plans). Work to include general site work including demolition of existing residential structures and the construction of the new building per the approved plans. Special inspections required per attached Form 310. Carports to be constructed under separate building permit. All buildings are to be fully fire sprinklered with an NFPA 13-R system as required for residential occupancy and story increase. Exterior decks and breezeways to be protected. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference7/7/20207/8/20207/8/2020APART
DetailsMike Jordan
Earliest available consultation meeting, Permit Card Phone #: ###-#### Inspection requested via web by Kris Linnell. Ok for temp occ.
BLD-Final7/5/20207/6/20207/6/2020APEND
DetailsMike Jordan
Building final for TCO Phone #: ###-#### Inspection requested via web by Kris Linnell. Will be ok for temp occ. once zoning signs off on bond and issues temp.
BLD-Final7/1/20207/2/20207/2/2020PNR
DetailsMike Jordan
Building Final inspection Phone #: ###-#### Inspection requested via web by Kris Linnell
FIRE-Final Inspection7/1/20207/2/20207/2/2020PPART
DetailsGreg Ruxton
Fire life safety inspection of building completed and code compliant. Contractor to finish hanging undercounter FE's on brackets prior to building final inspection. Area of concern is aerial fire apparatus access. Travel distance exceeds 150 ft and required approved turnaround code not be verified.

Fire Life ; Safety for Temp Occupancy to allow Tenant Touring of interiors of apartments. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Ceiling Grid Inspection3/13/20203/16/20203/16/2020ACANC
DetailsJim Storey
Chris Phone #: ###-####
BLD-Framing/Rough-in2/14/20202/14/20202/14/2020PPASS
DetailsMike Jordan
Building 12 East 12 unit drop ceiling locations framing and fire caulking. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Framing/Rough-in2/11/20202/12/20202/12/2020APART
DetailsMike Jordan
Drop Ceiling Framing inspections in 05 and 06 units in first, second, and third floors. Phone #: ###-#### Inspection requested via web by Kris Linnell. Fir downs ok to cover pending mech at fire damper areas.
BLD-Energy code compliance1/27/20201/27/20201/27/2020PPASS
DetailsMike Jordan
Building 12 - 1st Floor, Insulation, Vapor Barrier ; RC Channel inspection. Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Framing/Rough-in1/22/20201/22/20201/22/2020PPASS
DetailsMike Jordan
Building 12 - 1st Floor Energy Seal, Fire Caulking ; Framing
Building 12 - 2nd Floor Ceilings 1st layer gyp and 2nd layer gyp overlap Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Wall cover1/21/20201/21/20201/21/2020PCANC
DetailsMike Jordan
Building 12 - 2nd Floor Insulation and RC channel inspection for cover. Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Energy code compliance1/21/20201/21/20201/21/2020PPASS
DetailsMike Jordan
Building 12 - 2nd Floor Insulation and RC channel inspection for cover. Phone #: ###-#### Inspection requested via web by Bob Goodwin
BLD-Framing/Rough-in1/17/20201/17/20201/17/2020PPASS
DetailsMike Jordan
Re-inspection of Fire Stopping, Energy Code and Framing for Building 12 - 2nd Floor Units cover for Insulation ; Vapor Barrier install. As late as possible this afternoon.

6" OSA intakes at west units (105, 106, 205, 206, 305 ; 306) being addressed by Mech Eng, front of furnace alcoves not being covered until after ceiling drops framing inspection. Phone #: ###-#### Inspection requested via web by Bob Goodwin. Ok to insulate 2nd. floor only.
BLD-Framing/Rough-in1/16/20201/16/20201/17/2020PPART
DetailsMike Jordan
2nd. floor, neeeds to complee firecaulking at toilets and tub drains. Provide UL listed assembly for through penetrations of fresh air intakes at 1hr. fire barrier walls.
BLD-Energy code compliance1/15/20201/15/20201/15/2020PPASS
DetailsMike Jordan
Third Floor Insulation vapor barreir and RC Channel on Ceiling and walls. Phone #: ###-#### Inspection requested via web by Kris Linnell. 3rd floor only ok to rock.
BLD-Framing/Rough-in1/14/20201/14/20201/14/2020PPASS
DetailsMike Jordan
Late A.M. Early P.M. to allow for Mechanical inspection on exhaust fan GWB Fire boxes. Framing Corrections and Mechanical failures from last walk have been corrected. Framing and Energy seal inspection for cover on third floor only. Phone #: ###-#### Inspection requested via web by Kris Linnell. 3rd. floor only ok to insulate.
BLD-Framing/Rough-in1/13/20201/14/20201/14/2020ANR
DetailsMike Jordan
Late A.M. Early P.M. to allow for Mechanical inspection on exhaust fan GWB Fire boxes. Framing Corrections and Mechanical failures from last walk have been corrected. Framing and Energy seal inspection for cover on third floor only. Phone #: ###-#### Inspection requested via web by Kris Linnell. Moved to pm inspection.
BLD-Framing/Rough-in1/9/20201/10/20201/10/2020AFAIL
DetailsMike Jordan
Energy Seal, Fire caulking and Framing for Cover Third Floor.
Preferably as early as possible. Phone #: ###-#### Inspection requested via web by Kris Linnell. Needs to resolve vent fan install, install missing H2.5, LPT4 and missed fire caulking.
BLD-Energy code compliance12/26/201912/26/201912/26/2019PPART
DetailsTony Young
Energy Code inspection of pre-insulation areas for pre-rock installations in Buidling 12. Phone #: ###-#### Inspection requested via web by Bob Goodwin,, ok to cover insulated areas for pre-rock
BLD-Framing/Rough-in12/19/201912/19/201912/19/2019PPART
DetailsMike Jordan
Framing inspection in pre-rock areas. Phone #: ###-#### Inspection requested via web by Kris Linnell. Pre rock and fire caulking. work in progress.
BLD-Framing/Rough-in11/18/201911/19/201911/19/2019ACANC
DetailsMike Jordan
Earliest availability preferred. Inspect remaining Sheathing nailing on SE Corner of Building 12. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Wall Bracing11/19/201911/19/201911/19/2019APASS
DetailsMike Jordan
Earliest availability preferred. Inspect remaining Sheathing nailing on SE Corner of Building 12. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Framing/Rough-in11/8/201911/12/201911/12/2019ACANC
DetailsMike Jordan
Exterior Nail inspection Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Wall Bracing11/12/201911/12/201911/12/2019APASS
DetailsMike Jordan
Exterior Nail inspection Phone #: ###-#### Inspection requested via web by Kris Linnell. Exterior and interior shear walls, floors 1 to 3 ok to cover.
BLD-Framing/Rough-in10/18/201910/21/201910/21/2019PFAIL
DetailsMike Jordan
First Floor Shear Inspection Phone #: ###-#### Inspection requested via web by Kris Linnell. 1st floor shear, missing fateners and holddowns.
BLD-Conference9/17/20199/18/20199/18/2019ADONE
DetailsMike Jordan
Per Mike Jordan, Framing Consultation prior to framing for building 12. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Concrete9/10/20199/11/20199/11/2019PPART
DetailsTell Riley
Building Slab and interior footing pour scheduled for 6A.M. Thursday Morning. Phone #: ###-#### Inspection requested via web by Kris Linnell//vapor barrier ok//add bar to footings as discussed onsite// ok pending specials//
BLD-Foundation8/23/20198/26/20198/26/2019PPASS
DetailsMike Jordan
Building 11 North Half Stem Walls Rebar inspection. Concrete pour set for Tuesday 0730. Phone #: ###-#### Inspection requested via web by Kris Linnell
BLD-Energy code compliance8/1/20198/2/20198/2/2019APASS
DetailsMike Jordan
chris Phone #: ###-####. Rifid insulation on interior of stemwall under slab on grade.
BLD-Foundation7/25/20197/26/20197/26/2019APART
DetailsTell Riley
Bob-stem wall-says plan mod is for sewer not for this inspection Phone #: ###-####//north end building//walls ok pending specials// adjust wall rebar at location discussed onsite//
BLD-Footing7/22/20197/23/20197/23/2019APART
DetailsMike Jordan
Concrete at 1230 // bob Phone #: ###-####. Perimeter footings and column pad footings. Will have special inspection. Noted several areas were rebar does not have the 3 inch minimum clearance required. Special inspector to verify 3inch min. clearance prior to concrete placement.