Information based on query as of Sunday, May 5, 2024.
Permit Information
Permit NumberBLD19-01828
StatusFinaled
Name NORTHWEST VALOR POINTE LLC
Site Address 4203 W STATE ST
Project NameValor Pointe
Customer Number 
ePlanReviewYes
Description
(VALOR POINTE APARTMENTS) **(Project Management- Ron Hill)** Permit for the construction of a new 27 unit, 25,959 sq, ft., 4 story apartment building with work to include general site work and construction of the building. This building is fully fire sprinklered for R occupancy and story increase.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/31/20207/31/20207/31/2020PPASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Brock Landon
BLD-Final7/30/20207/31/20207/31/2020APASS
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Brock Landon
FIRE-Final Inspection7/31/20207/31/20207/31/2020PPASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire exrtingiushers are placed with current inspection tags. Final life fire safety inspection is complete.
BLD-Final7/30/20207/30/20207/30/2020PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Brock Landon// ok pending others,, temp occupancy ok
FIRE-Final Inspection7/30/20207/30/20207/30/2020APART
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete but city approved drawings need updated showing required cahnges, fire extinguishers are placed with current inspection tags, knox box is located by south stairwell entry, fire emergency guide has been reviewed and approved by Joe Bruce, fire section supervisor and emergency guide will be provided too tenants. 14 day TCO authorized for life fire safety, final sign off is contigent upon fire alarm drawings getting updated and the associated permit being finaled. Sigantures provided on permit sign off card.
FIRE-Final Inspection7/29/20207/29/20207/29/2020PCANC
DetailsJim Page
Cancelled per conversation with point of contat due too fire alarm volume issues, alarm vendor is troublshooting to fix.

Phone #: ###-#### Inspection requested via web by Brock Landon
FIRE-Final Inspection7/24/20207/27/20207/27/2020PFAIL
DetailsJim Page
Fire alarm failed final inspection, FIR permit for fire alarm system must be finaled before life fire safety can be completed. Provide one of the 3 listed no parking fire lane options as noted under note 10 of the building permit fire code review comments. Provide stairwell signage that is compliant with note number 14 of the review comments.

Phone #: ###-#### Inspection requested via web by Brock Landon
BLD-Conference7/23/20207/24/20207/27/2020PPART
DetailsTony Young
Preliminary Building Final inspection conference for obtaining certificate of occupancy and permanent occupancy Phone #: ###-#### Inspection requested via web by ted woods// walk through,, door seals,, trades, etc.
BLD-Conference6/24/20206/25/20206/25/2020APART
DetailsTony Young
Conference for final inspection needs. Phone #: ###-#### Inspection requested via web by ted woods// walk through on 1st floor
BLD-Ceiling Grid Inspection6/24/20206/25/20206/25/2020APASS
DetailsTony Young
4th floor ceil grid. Phone #: ###-#### Inspection requested via web by ted woods
BLD-Final6/24/20206/24/20206/24/2020PCANC
DetailsTony Young
1st floor final Phone #: ###-#### >> Inspection requested via web by ted woods Inspection cancelled from web by: ted woods
BLD-Ceiling Grid Inspection6/17/20206/18/20206/18/2020APASS
DetailsTony Young
Second floor mop sink room
third floor laundry room Phone #: ###-#### Inspection requested via web by ted woods// prior corrections made ok
BLD-Ceiling Grid Inspection6/15/20206/17/20206/17/2020ADEFR
DetailsTony Young
Second floor mop sink room
third floor laundry room Phone #: ###-#### Inspection requested via web by ted woods// no access to site
BLD-Ceiling Grid Inspection6/11/20206/12/20206/12/2020APASS
DetailsJim Storey
2nd floor ceiling grid inspection. Call first. Phone #: ###-#### Inspection requested via web by Michael Zaccheo grid ok do not cover with out fire stopping insp.
BLD-Ceiling Grid Inspection5/28/20205/29/20205/29/2020PPART
DetailsTony Young
1st floor ceiling grid inspection. Please call first. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// ok after firecaulking minor areas
BLD-Other5/22/20205/22/20205/26/2020PPASS
DetailsDave Hannah
Hard lid framing 1st floor corridor. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Other5/1/20205/4/20205/4/2020APART
DetailsTony Young
Drop ceiling inspection for 4th floor unit hallways ; 1st floor unit bathrooms Phone #: ###-#### Inspection requested via web by Michael Zaccheo// ok after fire caulking
BLD-Other4/9/20204/10/20204/10/2020APASS
DetailsTony Young
Hard lid framing inspection individual unit hallways 1st ; 2nd floors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Other2/28/20203/2/20203/2/2020PPASS
DetailsTony Young
4th floor Interior wall fire caulking. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Energy code compliance2/27/20202/28/20202/28/2020PPART
DetailsDave Hannah
4th floor energy seal inspection Phone #: ###-#### Inspection requested via web by Michael Zaccheo ok to insulate ext walls
BLD-Other2/28/20202/28/20202/28/2020PPASS
DetailsDave Hannah
RC ; drywall install 3rd floor. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Wall cover2/21/20202/24/20202/24/2020APASS
DetailsTony Young
3rd floor exterior wall insulation ; vapor barrier. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Other2/21/20202/24/20202/24/2020APASS
DetailsTony Young
Continued drywall install inspection 1st ; 2nd floors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Energy code compliance2/19/20202/20/20202/21/2020PPART
DetailsTony Young
3rd floor energy seal inspection. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, work in progress,, ok to insulate
BLD-Other2/19/20202/20/20202/21/2020PPART
DetailsTony Young
Periodic drywall install inspection 1st ; 2nd floors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, work in progress,, ok
BLD-Wall cover2/19/20202/20/20202/20/2020APART
DetailsTony Young
Two layer drywall install inspection 2nd floor units. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// work in progress
BLD-Other2/18/20202/19/20202/19/2020APART
DetailsTony Young
Two layer drywall install inspection 1st floor units. Phone #: ###-#### Inspection requested via web by Michael Zaccheo/// work in progress,, ok
BLD-Other2/17/20202/18/20202/18/2020APART
DetailsTony Young
Two layer drywall install inspection 1st floor units. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, work in progress,, ok
BLD-Other2/14/20202/14/20202/14/2020PPASS
DetailsTony Young
Ceiling resilient channel install inspection 1st floor units. Late afternoon if possible. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, 2nd floor ok also
BLD-Energy code compliance2/6/20202/7/20202/7/2020PPASS
DetailsTony Young
Exterior wall insulation ; vapor barrier for 1st ; 2nd floor approval to cover. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Wall cover2/6/20202/7/20202/7/2020PPASS
DetailsDave Hannah
1st ; 2nd floor ceiling/floor approval to insulate ; cover. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Wall cover2/5/20202/6/20202/6/2020PCANC
DetailsTony Young
Ceiling penetration fire caulking 1st & 2nd floors approve for insulation. Phone #: ###-#### >> Inspection requested via web by Michael Zaccheo Inspection cancelled from web by: Michael Zaccheo
BLD-Energy code compliance2/5/20202/6/20202/6/2020PCANC
DetailsTony Young
Exterior wall insulation and moisture barrier 1st & 2nd floors. Phone #: ###-#### >> Inspection requested via web by Michael Zaccheo Inspection cancelled from web by: Michael Zaccheo
BLD-Framing/Rough-in2/4/20202/5/20202/5/2020APART
DetailsTony Young
Exterior wall foam 1st ; 2nd floors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// (fire caulking)// ok to insulate the exterior walls on the main and 2nd floor
BLD-Wall cover2/3/20202/4/20202/4/2020PNR
DetailsTony Young
1st and 2nd floors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, needs fire caulking
BLD-Energy code compliance2/3/20202/4/20202/4/2020PNR
DetailsTony Young
Exterior wall foam 1st ; 2nd floors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, need to add sill plate bolts as needed,, needs fire caulking
FIRE-Conference1/31/20201/31/20201/31/2020ADONE
DetailsJim Page
Spoke with GC about level 4 insulation for sprinkler piping. According to the GC the roof has an insulation value of R-30, as shown on the city approved fire sprinkler drawings a minimum of R-38 is required, more insulation will need to be provided and installed per detail on the fire sprinkler approved drawings. Cover will not be authorized on the level 4 fire sprinkler piping until a minimum combined value of R-38 is provided.
BLD-Other1/14/20201/15/20201/15/2020APART
DetailsTony Young
3rd floor ceiling hallways,,
BLD-Wall cover1/13/20201/14/20201/14/2020APART
DetailsTony Young
RC and drywall in corridors. Late morning or early afternoon preferred inspection. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// 2nd floor ok,, work in progress
BLD-Other1/10/20201/13/20201/13/2020APART
DetailsTony Young
RC and drywall in corridors. Late morning or early afternoon preferred inspection. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, 1st floor,, work in progress,, ok after sealing up
BLD-Wall cover1/10/20201/10/20201/10/2020PPART
DetailsTony Young
RC and drywall in corridors. Late morning or early afternoon preferred inspection. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, R.C channel ok
BLD-Energy code compliance1/8/20201/9/20201/9/2020APART
DetailsTony Young
Insulation in 1st, 2nd, ; 3rd floor corridors. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, ok to cover ceilings to do trades under
BLD-Energy code compliance1/8/20201/9/20201/8/2020PCANC
DetailsTony Young
Corridor ceiling insulation on 1st, 2nd, & 3rd floors. Phone #: ###-#### >> Inspection requested via web by Michael Zaccheo Inspection cancelled from web by: Michael Zaccheo
BLD-Framing/Rough-in12/23/201912/24/201912/24/2019APART
DetailsTony Young
Corridor framing before insulation. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, ceilings in the corridors all levels ok to cover so trades can come in,,
BLD-Energy code compliance12/23/201912/26/201912/24/2019ACANC
DetailsTony Young
Corridor insulation. Phone #: ###-#### >> Inspection requested via web by Michael Zaccheo Inspection cancelled from web by: Michael Zaccheo
BLD-Wall Bracing12/16/201912/19/201912/19/2019PPASS
DetailsTony Young
Shear wall nailing and hold downs. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// exterior nailing ok after adding some in various areas
BLD-Wall Bracing12/12/201912/16/201912/16/2019PCANC
DetailsTony Young
Shear wall nailing and hold downs. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Framing/Rough-in12/11/201912/12/201912/12/2019ANR
DetailsTony Young
Shear wall nailing and hold downs. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// walk through,, ok to install windows after completing nailing plywood
BLD-Foundation11/4/201911/5/201911/5/2019PPEND
DetailsTony Young
CMU rebar on north stair tower ; elevator shaft. Grout pour is scheduled for 1:45 pm Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, pending s.i.
BLD-Foundation11/4/201911/4/201911/4/2019PPEND
DetailsTony Young
CMU rebar on north stair tower ; elevator shaft. Grout pour is scheduled for 1:45 pm Phone #: ###-#### Inspection requested via web by Michael Zaccheo// pending Special inspection report
BLD-Foundation10/29/201911/1/201911/1/2019PPART
DetailsTony Young
CMU rebar. Grout pour scheduled for 3:00 p.m. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, south tower upper final section of tower,, pending special inspection report
BLD-Foundation10/29/201910/31/201910/31/2019PPART
DetailsTony Young
CMU rebar. Grout pour scheduled for 3:00 p.m. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// pending special inspection reports,, stair towers
BLD-Foundation10/29/201910/30/201910/30/2019PPEND
DetailsMike Jordan
CMU rebar. Grout pour scheduled for 3:00 p.m. Phone #: ###-#### Inspection requested via web by Michael Zaccheo. Stair towers, pending special inspection.
BLD-Foundation10/29/201910/29/201910/29/2019PPEND
DetailsTony Young
CMU rebar. Grout pour scheduled for 1:45 pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Foundation10/28/201910/28/201910/28/2019PCANC
DetailsTell Riley
CMU rebar. Grout pour is scheduled for 1:45 pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Foundation10/24/201910/25/201910/25/2019PPART
DetailsMike Jordan
Rebar in CMU. Gout pour scheduled for 1:45 pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo. Stair towers, pending special inspection.
BLD-Foundation10/23/201910/24/201910/24/2019PPART
DetailsBrandon Shaw
CMU rebar. Grout pour is scheduled for 1:45 pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Foundation10/22/201910/23/201910/23/2019PPEND
DetailsDave Hannah
Continuing CMU rebar inspection. Grout pour scheduled for 1:45 pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo ok after spec inspection sign off
BLD-Foundation10/21/201910/22/201910/22/2019PPART
DetailsTony Young
CMU rebar on north and south stair towers and at the elevator shaft. Grout pour is scheduled for 1:45 pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Foundation10/21/201910/21/201910/21/2019APART
DetailsTony Young
CMU rebar. Pour is scheduled for 10am. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, special inspector on site,, pending report
BLD-Foundation10/17/201910/18/201910/18/2019PFAIL
DetailsBrandon Shaw
Gate locked, no one on site...
BLD-Foundation10/17/201910/18/201910/18/2019ADONE
DetailsJim Storey
Trash enclosure stem walls. Pour is scheduled for 11am. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Foundation10/16/201910/17/201910/17/2019PPART
DetailsTony Young
CMU Rebar. Pour is @ 2pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo// work in progress on towers,, cautioned to keep cells cleaner of excess mortar
BLD-Footing10/16/201910/17/201910/17/2019ADONE
DetailsTony Young
Trash Enclosure Footing Rebar. Pour is at 10am. Phone #: ###-#### Inspection requested via web by Michael Zaccheo
BLD-Footing10/15/201910/16/201910/16/2019PPEND
DetailsTony Young
CMU rebar. Grout pour is scheduled for 2:15pm. Phone #: ###-#### Inspection requested via web by Michael Zaccheo,, re-scheduled
BLD-Concrete10/3/201910/4/201910/4/2019PPART
DetailsTell Riley
Slab on grade and thickened footing rebar inspection Phone #: ###-#### Inspection requested via web by Michael Zaccheo//vapor barrier ok//rebar ok pending specials//
BLD-Wall Bracing8/28/20198/29/20198/29/2019APEND
DetailsTony Young
late AM // stem wall rebar // Mike Phone #: ###-####,, foundation pending special inspections
BLD-Footing8/22/20198/23/20198/23/2019APART
DetailsTony Young
late am - rebar // Mike Phone #: ###-####,, work in progress on elevator pit area,, pumping ground water out,, will need engineer approval on method of pouring and will have special inspector testing and inspection
BLD-Footing8/20/20198/21/20198/21/2019APART
DetailsTony Young
late morning if possible // Mike Phone #: ###-####,, set backs are surveyed,, special inspections on rebar, slump, soils, etc,, walked job with Mike