FIRE-Final Inspection | 8/7/2020 | 8/10/2020 | 8/10/2020 | A | CANC |
Troy Cobbley
|
|
|
Need the project related fire alarm and fire sprinkler permits finaled prior to a life safety inspection. ] crrened- Matt Phone #: ###-####
|
BLD-Energy code compliance | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PART |
Tell Riley
|
|
|
Matt *screened* Phone #: ###-####//ok pending tenting approval for fire sprinklers prior to cover//
|
BLD-Framing/Rough-in | 7/16/2020 | 7/17/2020 | 7/17/2020 | A | PART |
Tell Riley
|
|
|
Matt - */Screened*/ Phone #: ###-####last two units first floor//add blocking between joists a bearing wall//ok to insulate//
|
BLD-Framing/Rough-in | 7/16/2020 | 7/16/2020 | 7/17/2020 | P | PART |
Dave Hannah
|
|
|
Screened- Mat- call before arrival Phone #: ###-#### 2econ and third floors ok insulate
|
BLD-Energy code compliance | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PART |
Tell Riley
|
|
|
SCREENED // Matt Phone #: ###-####//3rd set of 6 from east end//2 top units still need tenting inspection//other 4 units appear to be ok//
|
BLD-Framing/Rough-in | 7/10/2020 | 7/13/2020 | 7/13/2020 | A | PASS |
Tony Young
|
|
|
screened // Pat Phone #: ###-####// ok to insulate//
|
BLD-Framing/Rough-in | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | FAIL |
Tell Riley
|
|
|
Matt - /*screened*/ Phone #: ###-####//corrections have not been completed to meet plans and specifications//See Matt onsite for CN//
|
BLD-Framing/Rough-in | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | NR |
Tell Riley
|
|
|
Matt - /*screened*/ Phone #: ###-####//corrections are not complete//moved to PM//
|
BLD-Framing/Rough-in | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | FAIL |
Tell Riley
|
|
|
SCREENED // Matt Phone #: ###-####//2nd six units still need corridor fire wall to meet listing on plans//3rd six units correction notice issued for framing corrections, see Matt onsite for list--also corridor fire wall on these six units needs to meet listing on plans//
|
BLD-Wall cover | 6/30/2020 | 6/30/2020 | 7/1/2020 | P | CANC |
Tell Riley
|
|
|
screened // Matt Phone #: ###-####
|
BLD-Wall cover | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PART |
Tell Riley
|
|
|
areas in fire wall to roof deck over center stairways were filled with gyp board and penetrations fire caulked//this was verified by photos sent by contractor//
|
BLD-Energy code compliance | 6/26/2020 | 6/29/2020 | 6/29/2020 | A | PART |
Tell Riley
|
|
|
ok to cover units 2nd six from east end areas not affected by CN//CN issued for fire wall 1 hr at corridor--does not refelct listing as it current create a cavity above panty areas, fire caulk penetrations//note see detail C3 for corridor ceiling 1 hr construction//
|
BLD-Energy code compliance | 6/25/2020 | 6/26/2020 | 6/26/2020 | A | CANC |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Matthew Bundy
|
BLD-Wall cover | 6/23/2020 | 6/23/2020 | 6/23/2020 | P | PART |
Tell Riley
|
|
|
Matt Phone #: ###-#### Inspection requested via web by Matthew Bundy//6 units on west end for fur-downs only//framing in these areas ok//pending trades inspections//fire caulk as discussed//
|
BLD-Framing/Rough-in | 6/23/2020 | 6/23/2020 | 6/23/2020 | P | PART |
Tell Riley
|
|
|
Matt Phone #: ###-#### Inspection requested via web by Matthew Bundy//2nd six units east end//see CN onsite//ok ot insulate only//corrections will need completed prior to cover//
|
BLD-Energy code compliance | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PART |
Tell Riley
|
|
|
Matt *screened* Phone #: ###-####//107, 108,207,208,307,308// energy requirements updated by designer via res check//attic insulation in these units will Be r50//fire caulk complete//
|
BLD-Energy code compliance | 6/15/2020 | 6/16/2020 | 6/16/2020 | A | FAIL |
Tell Riley
|
|
|
screened // Matt Phone #: ###-####//label fire walls in attic--fire caulk penetrations//wall insulation does not meet rescheck//window u-values do not meet rescheck//1 hour rated laydown parapet was not installed for 4' from separation walls at deck//need fire sprinkler tenting inspection//
|
BLD-Framing/Rough-in | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PART |
Brandon Shaw
|
|
|
Units 107,108, 207, 208, 307, 308
|
BLD-Wall cover | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PART |
Tell Riley
|
|
|
screened // Matthew Phone #: ###-####//3rd 6 units 2nd floor drops--corrections made//architect approved fire blocking fix for first 4 2nd floor drops//remaining drops will have gyp on walls//
|
BLD-Wall cover | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | PART |
Tell Riley
|
|
|
screened // Matt Phone #: ###-####//3rd set of 2nd floor units for pre-rock areas//need to fire caulk areas discussed//looked at gyp on first 4 units--need to extend down walls on rated wall side and exterior walls, or provide detail from architect//
|
BLD-Wall cover | 6/2/2020 | 6/3/2020 | 6/3/2020 | A | CANC |
Tell Riley
|
|
|
screened // Matt Phone #: ###-####//moved to pm//no one onsite//
|
BLD-Wall Bracing | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Brandon Shaw
|
|
|
screened// exterior shear and fire caulk 2nd fix fir down// Pat Phone #: ###-####
|
BLD-Other | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Tell Riley
|
|
|
rough to cover .. screened // Matt Phone #: ###-####//2nd floor east end 2 apartments//cover ceiling for fur downs only//
|
BLD-Wall Bracing | 5/18/2020 | 5/18/2020 | 5/18/2020 | P | FAIL |
Tell Riley
|
|
|
Matt *screened* Phone #: ###-####//Still need RFI for densglass shear walls in corridors//plans show all shear walls to be wood structural panels, and plans do not have nailing or shear schedule for densglass//
|
BLD-Wall Bracing | 5/11/2020 | 5/12/2020 | 5/12/2020 | A | FAIL |
Tell Riley
|
|
|
Matt Phone #: ###-####//CN issued see onsite//
|
BLD-Other | 5/8/2020 | 5/8/2020 | 5/8/2020 | P | CANC |
Tell Riley
|
|
|
rough to cover // Matt Phone #: ###-####//not ready, need to have rough ins inspected in areas wanting to cover for soffits//
|
BLD-Wall Bracing | 4/16/2020 | 4/17/2020 | 4/17/2020 | P | PART |
Dave Hannah
|
|
|
Screened- Matt Phone #: ###-#### thrid floor int sheer walls ok to cover
|
BLD-Wall Bracing | 4/3/2020 | 4/3/2020 | 4/3/2020 | P | PART |
Tell Riley
|
|
|
*cleared* Please call ahead so site can cleared Pat Phone #: ###-####///second story interior shear walls prior to gyp cover//
|
BLD-Wall Bracing | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | PART |
Tell Riley
|
|
|
please call .... shear // Pat Phone #: ###-####/interior shear on level one ok to cover with gyp//
|
BLD-Framing/Rough-in | 2/18/2020 | 2/18/2020 | 2/18/2020 | P | FAIL |
Tell Riley
|
|
|
Pat - Sheer Wall Inspection Phone #: ###-####//interior fire walls and shear walls--do not meet specifications on plans for UL assembly and sound//discussed with contractor UL assembly per plans and shear walls per structurals//
|
FIRE-Final Inspection | 8/13/2020 | 8/14/2020 | | A | |
Jim Page
|
|
|
Matt *screened Phone #: ###-####
|