Permit Information
Permit NumberESC15-00504
StatusFinaled
Name KIM W ELLIS
Site Address 7700 W STATE ST
Project NameKensington Apartments
Customer Number 
ePlanReviewNo
Description
Site Infrastructure for the Apartments and Commercial Development of the Project. Building permits for the buildings will be coming with a later submittable.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/20/20188/20/20188/20/2018 CANC
DetailsMichael Zawacki
DOC - Permit Finaled8/20/20188/20/20188/20/2018PPASS
DetailsMichael Zawacki
General Inspection7/19/20187/19/20187/19/2018 PASS
DetailsMichael Zawacki
Still a few vacant pads. Site is clean, no ESC issues.
General Inspection6/18/20186/18/20186/18/2018 PASS
DetailsMichael Zawacki
Few pads vacant and exposed. Witches hats still in DIs. Most of area is completed. Grading permit still open.
General Inspection5/17/20185/17/20185/17/2018 PASS
DetailsMichael Zawacki
Job trailer has been removed. Site is nearing final stabalization and almost completed.
General Inspection4/16/20184/16/20184/16/2018 PASS
DetailsMichael Zawacki
Some materials and landscape rocks still being stored on site of apartments. Job trailer still on site, vacant lot still be used for staging and storage. Inlet protection still installed by Black Bear diner.
Site Final3/9/20183/15/20183/16/2018PCANC
DetailsAndy J. Long
General Inspection3/8/20183/8/20183/9/2018 CANC
DetailsAndy J. Long
rescheduled for Site Final
General Inspection2/5/20182/5/20182/5/2018 PASS
DetailsMichael Zawacki
Crew finishing installing sprinklers and landscaping in apartment complex. Staging area across from Black Bear diner has some stock piling and an eco pan. Bo loose dirt or runoff on site.
General Inspection1/5/20181/5/20181/5/2018 PASS
DetailsMichael Zawacki
WIP on interior of a few apartments. Lot is all paved and dumpster on site. Sidewalk work on west side of apartment complex. Empty lot behind Black Bear Diner being used for storage, some stockpiles and an eco-pan on lot.
General Inspection11/20/201712/5/201712/5/2017PPASS
DetailsMichael Zawacki
Majority completed. Some area still need to be landscaped. Site clean, evidence of sweeping, someone was removing trash bins while I was there.
General Inspection11/20/201711/20/201711/20/2017 PASS
DetailsAndy J. Long
WIP on Kensington units in the NE and NW corners of complex. Trash and construction materials are contained. No trackout or discharges off site. Job trailer and staging yard with washouts for cement pathwork are located on Saxton. No corrections requested.
General Inspection10/19/201710/19/201710/19/2017PPASS
DetailsMichael Zawacki
Mojority of apartments done and leased. Most remaining construction is for interior and landscape. Area is clean and free of trackout.
General Inspection9/25/20179/25/20179/26/2017 CANC
DetailsAndy J. Long
General Inspection8/23/20178/23/20178/23/2017PPASS
DetailsAndy J. Long
Apartment units and garages are under construction along Gary Lane and in the northwest corner of Kensington. The central area is complete, occupied, and landscaped/stabilized. Permeable pavers in the construction area are to be cleaned or repaired at end of project prior to units being occupied.

No trackout from site, no discharges or spills observed. Trash is contained and site is generally clean.
General Inspection7/28/20178/1/20178/2/2017ACANC
DetailsAndy J. Long
General Inspection7/24/20177/27/20177/28/2017PCANC
DetailsAndy J. Long
rescheduled
General Inspection7/24/20177/24/20177/24/2017 CANC
DetailsAndy J. Long
rescheduled 7/27
General Inspection6/22/20176/22/20176/23/2017 CANC
DetailsAndy J. Long
General Inspection5/22/20175/22/20175/22/2017 PASS
DetailsAndy J. Long
WIP on east side of Kensington next to Gary Lane. Mostly vertical construction. No trackout to Saxton or Gary. No fugitive dust observed.

Western side of site including clubhouse and pool area has been completed, landscaped, and occupied units. ESC permits closed out accordingly.
General Inspection4/21/20174/21/20174/21/2017PPASS
DetailsMelissa Jannusch
Interior and exterior WIP. Clean up trackout on interior streets. Empty dumpster to prevent windblown and uncontained trash. Clean DIs. SWPPP inspections up to date. Corrections are noted in SWPP as well.
General Inspection4/3/20174/3/20174/4/2017 CANC
DetailsAndy J. Long
General Inspection3/1/20173/1/20173/1/2017PFAIL
DetailsAndy J. Long
No trackout or discharges out side of Kensingtion site. Perimeter silt fence installed to contain new construction along Gary. DIs have sediment filter bags installed.

RP Barry previous informed that all permeable pavers are to be cleaned upon completion of apartment units. Significant amount of loose dirt in paved areas draining to permeable pavers.

Correction needed:

Need to have crew collect wind blown trash and debris around perimeter of site to prepare for windy March as well as empty any full trash containers.
General Inspection2/16/20172/16/20172/21/2017 CANC
DetailsMelissa Jannusch
General Inspection1/16/20171/16/20171/17/2017 CANC
DetailsAndy J. Long
General Inspection12/16/201612/16/201612/16/2016 CANC
DetailsAndy J. Long
General Inspection11/10/201611/15/201611/14/2016APART
DetailsAndy J. Long
Vertical construction in progress on apartment buildings on the east and west ends of Kensington. No trackout outside of site to Saxton, State or Gary. Silt fence perimeter BMP installed on northern property limts. Onsite drop inlets have sediment protection. Trash containment provided throughout site. No major windblown trash issues observed.

Correction request:
- sweep up lanes surrounding the unprotected permeable pavers to prevent clogging/failure. Prohibit / conduct training to works to park in designated areas and to not store stockpiles on impervious parking surfaces that drain to the pavers.

Notified Barry with Bach.
General Inspection11/7/201611/7/201611/10/2016 CANC
DetailsAndy J. Long
General Inspection10/7/201610/7/201610/7/2016APASS
DetailsAndy J. Long
Vertical construction in progress on apartment buildings. Site access drive, parking and stormwater system is installed. DIs have sediment bag protection. RP Barry working to keep stock piling and dirt off hard surfaces that drain to the permeable pavers that have been installed. Significant activity and numerous sub-contractors on site makeing management hard.

No trackout to Saxton or State or into complete retail area. Concrete washout and liquid waste pans are provided. Silt fence along northwest property line is still installed and trenched properly. Large stockpile has now been removed.
General Inspection9/12/20169/12/20169/12/2016PPASS
DetailsEvan Jenkins
General Inspection8/18/20168/18/20168/18/2016 PASS
DetailsEvan Jenkins
WIP: no trackout at this time nor dust issues.
General Inspection7/18/20167/18/20167/18/2016 PASS
DetailsEvan Jenkins
General Inspection6/15/20166/16/20166/16/2016PPASS
DetailsAndy J. Long
Site walk through with RP-GC Barry with Bach Homes.

No trackout or discharges offsite, large designated lined washout containment is provided and approximately 50% full. Heavy duty construction entrance to Gary with lava rock is still in good condition. Perimeter silt fence on north property line is in place. No complaints or issues from neighbors directed to ESC division.

The road base of sand is prepped for asphalt, and pervious pavers are already installed and are off limits for driving and staging.

Correction request to have crew walk site and clean up loose trash, consolidate and contain/remove from site.. Barry said it would be done this week.

Approved.
General Inspection6/10/20166/14/20166/15/2016ACANC
DetailsAndy J. Long
rescheduled for RP walk-through
General Inspection5/16/20165/16/20165/16/2016 PASS
DetailsEvan Jenkins
General Inspection4/14/20164/14/20164/14/2016PPASS
DetailsEvan Jenkins
General Inspection3/24/20163/24/20163/24/2016 FAIL
DetailsEvan Jenkins
Significant trackout onto Saxton and State St. Called Kim Ellis (RP) left VM to get Saxton swept up today due to expected rains this afternoon. will follow up before end of day and again tomorrow morning
General Inspection2/16/20162/22/20162/23/2016APASS
DetailsAndy J. Long
No significant trackout onto Gary. No fugitive dust. WIP on Kensington complex.
General Inspection2/15/20162/15/20162/16/2016 CANC
DetailsAndy J. Long
rescheduled
Random Inspection1/15/20161/15/20161/15/2016PPASS
DetailsAndy J. Long
Streets recentlly swept, no trackout or dischareges observed at Kensington. DI bags installed on Saxton and Gary Lane.
General Inspection12/16/201512/16/201512/16/2015PPART
DetailsAndy J. Long
Construction entrance on Gary is installed and working well to prevent muddy trackout. Roads have recently been sanded by ACHD.

Significant amount of mud on Saxton. Storm drain inlet is a curb cut and cannot be fitting with a sediment control BMP. Sand bags placed earlier were causing flooding and traffic hazard.

Need to control traffic better in and out of site and put rock to stabilized the employee parking lot on Saxton.
General Inspection12/1/201512/1/201512/1/2015PPASS
DetailsAndy J. Long
Two new large angular rock construction entrances installed as requested last week. Stormdrain inlet on south side of Saxton has been blocked by sandbags

Site is to sweep Wednesday or Thursday before warmer/wet weather forecasted arrives this weekend and next week. No corrections at this time.
General Inspection11/2/201511/2/201511/2/2015APASS
DetailsEvan Jenkins
No ESC issues observed at this time
General Inspection9/10/20159/10/20159/10/2015PPASS
DetailsEvan Jenkins
Minimal activity. No ESC issues observed
General Inspection8/20/20158/24/20158/24/2015APASS
DetailsAndy J. Long
Minimal activity at time of inspection.

No dewatering occuring, indicating that utility installation work is complete. No trackout or discharges from site. Water tank on-site for fugitive dust control.

No corrections needed at site. No further activity for North Pointe Retail.
General Inspection8/4/20158/4/20158/4/2015PPASS
DetailsAndy J. Long
WIP at Kensington. Boise ESC permit sign and SWPPPs posted for Kensingtion at North Pointe, and North Pointe Retail. No trackout from construction exits, perimeter streets, gutters and sidewalks are clean.

Dewatering is in progress and is being pumped into a channel at east end of site that runs to a retention and filtering pond on the west end of site. Pumped water goes into a pipe that discharges into the canal at irrigation box on State Street.

No fugitive dust issues observed, water trucks and tanker are on site. RP-GC Barry with Bach Homes and conducted a walk through inspection.

No corrections at this time. Irrigation company is monitoring disharges.

Barry stated Knife River will be working on retail section and digging their own dewatering pond.
Complaint Inspection7/8/20157/8/20157/8/2015APART
DetailsEvan Jenkins
Dewatering for Sewer installation. Some water was leaving their site, but directed Barry to do a land application on their project to keep any water from leaving their site. Barry stated he will, and I'll follow up this afternoon to ensure in compliance
Site Preparation6/23/20156/24/20156/24/2015APASS
DetailsAndy J. Long
Kensington Apartments' infrastructure project

Site prep requested for 9:30 AM meeting and walk-through. Superintendant Barry ###-####

Site walkthrough and ESC plan review conducted with Barry of Bach Homes and Andy of Syman Co.

Construction entrances installed per ESC site map with large angular rock and lining per specifications. Silt fence perimeter control installed properly along north border to capture sediment in sheet flow. Gary Lane and irrigation easement and sidewalk will remain undisturbed and act as sediment barrier. Irrigation berm on west side of site creats sediment barrier as well. Drainage swale along State Street protected.

Request for trash containment and notification of dewatering if necessary Groundwater is at 6' per Barry & geotech.

Approved for site grubbing and grading.

Water tank and water truck onsite for fugitive dust control. All receiving MS4 drop inlets have sediment bags installed.