General Inspection | 4/12/2017 | 4/12/2017 | 4/12/2017 | | PASS |
Andy J. Long
|
|
|
All work complete, bridge and path open for use. No loose dirt or materials. Creek bank vegetation in good condition and path shoulders have vegetated with grasses and some invasive weeds, white top mainly. .No temporary BMPs or construction trash. Grassy swale established and in good condition.
No ESC corrections needed. Permit conditions satisfied. Permit finaled.
|
DOC - Permit Finaled | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 3/28/2017 | 3/28/2017 | 3/28/2017 | | PASS |
Melissa Jannusch
|
|
|
Vegetation not at 70% cover yet.
|
General Inspection | 3/13/2017 | 3/13/2017 | 3/13/2017 | | PASS |
Melissa Jannusch
|
|
|
Bridge is complete. Vegetation cover is nearly complete. okay
|
General Inspection | 2/24/2017 | 2/24/2017 | 2/24/2017 | | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 2/9/2017 | 2/9/2017 | 2/9/2017 | | PASS |
Melissa Jannusch
|
|
|
Final stabilization has not been reached. Not ready to final.
|
General Inspection | 1/25/2017 | 1/25/2017 | 1/30/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/10/2017 | 1/10/2017 | 1/11/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/26/2016 | 12/26/2016 | 12/28/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/9/2016 | 12/9/2016 | 12/9/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/24/2016 | 11/24/2016 | 11/25/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/9/2016 | 11/9/2016 | 11/9/2016 | | PASS |
Andy J. Long
|
|
|
Construction of path and bridge complete. Shoulders have been hydroseeded. No materials, debris, or equipment left onsite.
Corrections issued in prior inspection have been completed: - trash has been picked up along creek banks and walking path - orange silt fence temporary BMP removed
No new corrections. Will keep open to monitor vegetation growth and Peppermill #2 activity.
|
General Inspection | 10/21/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Andy J. Long
|
|
|
Pedestrian bridge is installed and open for use. Pathways connecting Peppermill to Peconic & Gatewood is complete and shoulders have been hydromulched. Silt fence perimeter is still installed along 8 mile creek, which is no longer carrrying irriagtion water. New grass swale is established and perimeter control removed.
Correction request to developer and CBH - pick up windblown trash from construction sites and activity along the creek bank and silt fence.
|
General Inspection | 10/20/2016 | 10/20/2016 | 10/20/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/5/2016 | 10/5/2016 | 10/5/2016 | | PASS |
Andy J. Long
|
|
|
Bridge construction complete. Walking path also installed. Permit open for re-vegetation and final stabilization. Silt fence needs to be removed. Project associated to ESC16-00156 for Peppermill Estates phase II.
|
General Inspection | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | PEND |
Evan Jenkins
|
|
|
No activity at time of inspection
|
General Inspection | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | PASS |
Andy J. Long
|
|
|
Bridge span is now installed but not yet open for use. No disturbed areas without buffer next to creek. New swale off Peconic has had perimteter sediment control installed.
Landscaping/stabilization around both sides of bride access is not complete. Request to John to make sure crew picks up any loose litter in area and to provide date of SF removal.
|
General Inspection | 7/18/2016 | 7/18/2016 | 7/18/2016 | P | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Pathways on both side of creek and bridge footing are installed. Bank vegetation buffer hasbeen preserved, No trackout from site to roads.
Approved. Need to remove damaged section of silt fence when bridge is installed.
|
General Inspection | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on grading for pathway on east side of the creek/irrigation channel. Footings for bridge span are poured and located outside the vegetative buffer. Bank vegetation has been preserved, no work occuring in creek. No violations.
|
Site Preparation | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | PASS |
Andy J. Long
|
|
|
Site walk through for pedestrian bridge crossing over Eight Mile Creek with RP. Creek has silt fence installed on both sides and vegetated buffer pre-served. Footings will be poured outside of the silt fence and the bridge is a pre-cast 65' span with no in channel work required.
Concrete washout will be contained in portable bin for proper disposal.
|