Site Final | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 5/16/2018 | 5/16/2018 | 5/16/2018 | | PASS |
Michael Zawacki
|
|
|
Site nearly complete. Grass is growing on most exposed areas. Job trailer and most construction equipment is gone. Still a few workers finishing up.
|
General Inspection | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Michael Zawacki
|
|
|
Site is mostly complete and undergoing stabalization. No ESC issues.
|
General Inspection | 4/17/2018 | 4/17/2018 | 4/17/2018 | | PASS |
Michael Zawacki
|
|
|
Area clean. Some work in the Eagle sections.
|
General Inspection | 3/29/2018 | 4/2/2018 | 4/3/2018 | A | PASS |
Andy J. Long
|
|
|
Minimal activity. No violations observed in Pamela Baker park section of project.
Rest of adjacent subdivision project is in Eagle. Bankside vegetation of Thurman Mill ditch passing through site has started to grow. No detectable impact on turbidity of water passing through site.
No corrections issued.
|
General Inspection | 3/27/2018 | 3/27/2018 | 3/29/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | FAIL |
Andy J. Long
|
|
|
No trackout, perimeter silt fence and clearing limits next to Thurman Mill are in place. Site has extended westward to have staging area.
Correction action needed at site: - pick up the significant amount of wind blown trash caught in silt fence and vegatation next to Thurman Mill canal. - empty or cover dumpster to prevent wind blown trash - if dry weather continues, fugitve dust control water truck will need to be active if earthwork is occuring. Some dust onsite due moving stockpiles out of staging area.
|
General Inspection | 2/22/2018 | 2/27/2018 | 2/28/2018 | P | PASS |
Michael Zawacki
|
|
|
Most ground disturbance complete. Current construction is all on the existing buildings. Job trailer and central storage has been removed, now is graded road mix. No issues on site.
|
General Inspection | 2/20/2018 | 2/22/2018 | 2/22/2018 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/19/2018 | 2/19/2018 | 2/20/2018 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 2/2/2018 | 2/2/2018 | 2/2/2018 | | PASS |
Michael Zawacki
|
|
|
Exterior work about complete on 3 of 4 buildings. Workers relocated mortar mixer closer to active building and are in process of cleaning old area. Washout on site for trucks. Majority of area is paved, no trackout leaving site.
|
General Inspection | 1/18/2018 | 1/18/2018 | 1/18/2018 | | PASS |
Michael Zawacki
|
|
|
Some mud in site, nothing leaving. No trackout or loose trash. Site is well maintained, most workers parking on paved area.
|
General Inspection | 1/3/2018 | 1/3/2018 | 1/3/2018 | | PASS |
Michael Zawacki
|
|
|
WIP. Washouts in use, someone was cleaning them during inspection. Site kept clean and no issues observed during inspection.
|
General Inspection | 12/19/2017 | 12/19/2017 | 12/19/2017 | | PASS |
Michael Zawacki
|
|
|
2 of the Eco-Pans are full and need to be removed, another washout on site is ok. Site clean and free from trash.
|
General Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | | PASS |
Michael Zawacki
|
|
|
No trackout leaving site. Stockpile has been treated with tackifier. Eco pans on site and in use and maintained. Majority of work is buildings and ground disturbing activities are no toccuring.
|
General Inspection | 11/15/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Michael Zawacki
|
|
|
Site clean, crew was cleaning up loose trash when I arrived. Perimeter controls in place along canals, goats being used for over growth on canal bank. Multiple washouts, no trackout.
|
General Inspection | 11/10/2017 | 11/10/2017 | 11/15/2017 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 10/26/2017 | 10/26/2017 | 10/27/2017 | | PART |
Michael Zawacki
|
|
|
Inspected 10/23/17. Area clean and well maintained. No issues.
|
General Inspection | 10/11/2017 | 10/11/2017 | 10/13/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/22/2017 | 9/26/2017 | 10/4/2017 | A | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/20/2017 | 9/20/2017 | 9/22/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/31/2017 | 9/5/2017 | 9/13/2017 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/31/2017 | 8/31/2017 | 8/31/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/14/2017 | 8/16/2017 | 8/18/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/8/2017 | 8/10/2017 | 8/14/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/4/2017 | 8/7/2017 | 8/8/2017 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/28/2017 | 8/1/2017 | 8/4/2017 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/28/2017 | 7/28/2017 | 7/28/2017 | | CANC |
Andy J. Long
|
|
|
rescheduled for 8/1
|
General Inspection | 7/12/2017 | 7/13/2017 | 7/13/2017 | P | PASS |
Melissa Jannusch
|
|
|
WIP. concrete washout in use getting near full. There is an addition concrete washout with secondary containment if the first gets fulls. The silt fence along the creek is in good condition. The SCE is in good condition. There is no trackout. The trash is contained. No wind blown trash. A water truck is on site. No dust observed during the inspection.
|
General Inspection | 7/12/2017 | 7/12/2017 | 7/12/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/24/2017 | 5/24/2017 | 5/24/2017 | P | PASS |
Melissa Jannusch
|
|
|
Work has started. Met with RP on site. Looked a SWPPP plan and talked about BMP plans. Public works is also inspecting.
|