Permit Information
Permit NumberESC17-00203
StatusFinaled
Name JASON JONES
Site Address 6610 S ELITE DR
Project NameFed Ex shipping center.
Customer Number 
ePlanReviewNo
Description
New Package Distribution Center. SWPPP narrative and site map approved. RP to be designated. Construction entrance and perimeter controls specified. Site preparation inspection required, call 608-7070 to schedule
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final8/13/20188/16/20188/17/2018APASS
DetailsMichael Zawacki
Spoke with foreman. He will remove 2 witches hats fro Elite located by school bus yard.
General Inspection8/10/20188/10/20188/13/2018 CANC
DetailsAndy J. Long
Site Final6/25/20187/10/20187/10/2018PNR
DetailsAndy J. Long
Landscaping of parking lot and entrance near completion.

Corrections to get ESC site final:
- remove DI bags installed on Elite
- clean up area around job trailer.
General Inspection6/25/20186/25/20186/25/2018 PASS
DetailsAndy J. Long
WIP on interior. Exterior shell, parking lots, and stormwater pond are complete.

Site final follow up scheduled for 7/10 to request that DI bags installed on Elite be removed and to check for disturbed areas or stockpiles no stabilized.

No trackout, fugitive dust, or discharges observed.
General Inspection5/24/20185/24/20185/24/2018PPASS
DetailsMichael Zawacki
Knife River on site prepping west parking lot, water truck in use.
West lot has some runoff. Hills around lot are mostly vegetated, landscapers working and large bark piles on site. All DIs are protected.
General Inspection4/30/20184/30/20184/30/2018 PASS
DetailsMichael Zawacki
Site is all contained. All inlets through out site have protection. No fugitive dirt or dust. Landscapers on site. Majority of current work is inside shell.
General Inspection3/29/20183/29/20183/30/2018 PASS
DetailsMichael Zawacki
Concrete curb and islands laid out for parking lot. Lawnco on site doing landscaping. New sidewalks are in.New drain inlets are protected. Site about ready for paving. Storm retention pond has been installed. Job trailer is open, no one inside and no vehicles parked out front.
General Inspection2/26/20182/26/20182/26/2018 PASS
DetailsAndy J. Long
WIP on interior. No earthwork occuring, much of site is snow covered. No trackout to Elite.
General Inspection1/26/20181/26/20181/26/2018 PASS
DetailsAndy J. Long
WIP on site improvement. Structure is built, south parking lot and delivery area is complete. Shoulders of Elite towards Gowen have been hydroseeded. Road is clean, no trackout. No wind blown loose trash observed.
General Inspection12/26/201712/26/201712/28/2017 CANC
DetailsAndy J. Long
Random Inspection11/22/201711/22/201711/22/2017PPASS
DetailsAndy J. Long
Consruction entrance has been improved. Muddy areas have been blocked off to prevent trackout. Elite is free of mud or gravel trackout.
General Inspection11/15/201711/15/201711/15/2017PPEND
DetailsMichael Zawacki
Still doing dirt work. Electric contractor has cut a trench through the entrance. I asked foreman to repair exit when they are finished and to monitor trackout throughout the day.
Tracking Control11/7/201711/7/201711/7/2017PPASS
DetailsMichael Zawacki
Correction Notice issued to have trackout on Elite cleaned at the end of the day.
Foreman closed off and barricaded old exit. Everyone forced to use track pad now. Road has bee cleaned.
Complaint Inspection11/6/201711/6/201711/6/2017PFAIL
DetailsAndy J. Long
report of muddy trackout and lack of ESC controls around

Signicant tractkout due to muddy shoulder area. Parking area and south access drive are getting prepped for asphalt.

Correction request to sweep street before end of day 11/7.

Superintendent with Reudebuesch stated that roads will be swept today and tomorrow. GC said a loading truck drove through mud this morning.

Will follow up to address stabilization of muddy areas or controls to prevent.
General Inspection8/31/20179/21/20179/22/2017ACANC
DetailsAndy J. Long
General Inspection8/31/20178/31/20178/31/2017PPASS
DetailsAndy J. Long
WIP on frame. BMPs installed. Water truck onsite, not currently in use. No fugitive dust observed. No trackout. SWPPP binder onsite and inspection reports are logged. No corrections.
Random Inspection7/24/20177/24/20177/24/2017PPASS
DetailsAndy J. Long
Fugitvie dust inspection.

No fugitive dust issues observed. No complaints received. No trackout or discharges observed on Elite. Approved.
General Inspection7/12/20177/12/20177/12/2017PPASS
DetailsMelissa Jannusch
No WIP at time of inspection. Excavation stage. Roads are formed. SWPPP inspectinos are up to date. No dust. Minimal trackout.
General Inspection6/28/20176/28/20176/30/2017APASS
DetailsMelissa Jannusch
One plume of fugitive dust blew towards the west of the site during the inspection. Water truck is currently on site and working to water areas that are exposed. Talked with water truck driver about fugitive dust plume.
SWPPP is up to date with inspections. No other ESC issues observed onsite. No corrections issued
General Inspection5/31/20176/2/20176/2/2017APASS
DetailsMelissa Jannusch
Talked with Project manager Darrell. Has two water trucks and a sweeper ready when needed. Gave him information on PDS online.
Conference6/2/20176/2/20176/2/2017ADONE
DetailsAndy J. Long
note - onsite project manager Ruedebuesch Construction is Daryl ###-####

Stated he would have two water trucks provided on hot dry days where fugitve dust is an issue during this initial grading and earth moving. Currently only have one water truck in operation
BMP Violation5/30/20175/31/20175/31/2017APART
DetailsAndy J. Long
Onsite Project Manager Dave with Ruedebuesch Construction and Knife River foreman Brent have made corrections in area of excessive dust yesterday.

Dusty area of native material behind construction entrance was covered in pit run to supress dust and prevent mudzone. Water truck was not at site yesterday morning, now site has 1 designated water truck. Foreman also made contact with neighbor to discuss & resolve dust issue.

Was at site for approximately 15-20 mins while water truck was making a water run. Hydrant is 1.5 miles east on Gowen.

Dust plumes were not crossing site boundaries, but there is dust and activities continue while water truck is not at site.

Request to provide additional water truck so that the two trucks can rotate shifts so there is control at all times of excavation,grading and hauling.

Will check later in week for conditions at site.
Complaint Inspection5/30/20175/30/20175/30/2017PPEND
DetailsAndy J. Long
fugitive dust complaint

Report of inaequate dust control for grading and hauling activities. Site needs to have a designated water truck(s) for this phase of project.

Verbal warning to RP. RP stated he notified site and would inform them they have fugitive dust control requirements.

Will follow up with onsite inspection tomorrow.
Site Preparation4/27/20174/28/20174/28/2017APASS
DetailsMelissa Jannusch
Construction entrance installed. Perimeter controls installed. DI protection needed on DI on Elite dr next to entrance. SWPPP sign is posted. Posted City of Boise permit sign as none was posted yet. Approved to start.

Jason Phone #: ###-####