Site Final | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Andy J. Long
|
|
|
HOme complete, landscaped, trash piles have been picked up as requested.
No further ESC correction request, ESC permit finaled.
|
General Inspection | 7/12/2019 | 7/12/2019 | 7/12/2019 | | PASS |
Michael Zawacki
|
|
|
Will do site walk before final to make sure everything is clean.
|
Site Final | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | NR |
Andy J. Long
|
|
|
Need to clean up trash pile next to house.
|
General Inspection | 6/26/2019 | 6/26/2019 | 6/27/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/11/2019 | 6/11/2019 | 6/11/2019 | | PASS |
Michael Zawacki
|
|
|
Landscapers on site. Home is nearly completed. Looks like trash cleaned off hillside below.
|
General Inspection | 5/27/2019 | 5/27/2019 | 5/28/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/2/2019 | 5/9/2019 | 5/8/2019 | A | PASS |
Michael Zawacki
|
|
|
WIP on front facade and landscaping. Topsoil is now on site. Lot will need walk through and all trash picked up before final.
|
General Inspection | 5/2/2019 | 5/2/2019 | 5/2/2019 | | PART |
Michael Zawacki
|
|
|
Home completed, sprinkler company on site, still needs landscaping. Large pile of trash out front that needs to be picked up, dirt ramp in road going onto sidewalk. Follow up scheduled for next week.
|
General Inspection | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | PART |
Michael Zawacki
|
|
|
Some mud clods on road.
|
General Inspection | 4/8/2019 | 4/8/2019 | 4/8/2019 | | PASS |
Michael Zawacki
|
|
|
Workers parked in road, no trackout. Forms beginning to be installed for driveway.
|
General Inspection | 3/22/2019 | 3/22/2019 | 3/22/2019 | | PASS |
Michael Zawacki
|
|
|
Lots of activity at site, no dirt or trackout.
|
General Inspection | 2/20/2019 | 2/20/2019 | 2/26/2019 | | PASS |
Michael Zawacki
|
|
|
Site is snow covered, no ESC issues.
|
General Inspection | 2/4/2019 | 2/4/2019 | 2/4/2019 | P | PASS |
Michael Zawacki
|
|
|
No runoff, workers parked on road.
|
General Inspection | 1/23/2019 | 1/23/2019 | 1/23/2019 | | PASS |
Michael Zawacki
|
|
|
Workers all parked in street. No garbage or ESC issues at site.
|
General Inspection | 1/3/2019 | 1/3/2019 | 1/4/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/19/2018 | 12/19/2018 | 12/19/2018 | P | FAIL |
Michael Zawacki
|
|
|
One truck parking in mud and tracking onto street.
|
General Inspection | 12/5/2018 | 12/5/2018 | 12/7/2018 | | PASS |
Michael Zawacki
|
|
|
All work interior, site is snow covered.
|
General Inspection | 11/5/2018 | 11/5/2018 | 11/6/2018 | | PART |
Michael Zawacki
|
|
|
Lots of loose trash around site that needs to be cleaned.
|
General Inspection | 10/19/2018 | 10/19/2018 | 10/19/2018 | | PASS |
Michael Zawacki
|
|
|
Site is exposed but has buffer. Most of the garbage and small trash has been picked up. Old washouts have been removed.
|
General Inspection | 10/4/2018 | 10/4/2018 | 10/4/2018 | | PART |
Michael Zawacki
|
|
|
Workers pulling into mud and tracking out onto road. Lots of random trash around site.
|
General Inspection | 9/19/2018 | 9/19/2018 | 9/20/2018 | | PART |
Michael Zawacki
|
|
|
SIte has natural buffer. Pool crew overfilled washout and haven't cleaned up spill, second washout has been brought on site and has plenty of room. Some small trash has blown into weeds around home. Street is clean, no trackout.
|
General Inspection | 8/31/2018 | 9/4/2018 | 9/5/2018 | A | PASS |
Michael Zawacki
|
|
|
No new BMP installations. Area has natural buffer, hillside has been tracked. No loose stockpiles.
|
General Inspection | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Michael Zawacki
|
|
|
Outside is framed out. Site is clean, graded, and free from garbage. No workers currently on site.
|
General Inspection | 6/18/2018 | 6/18/2018 | 6/18/2018 | P | PASS |
Andy J. Long
|
|
|
No trackout. Working with in clearing limits, no trackout or offisite discharges observed. Workers parking on culdesac pavement, trash contained. ESC permit sign posted.
|
Tracking Control | 4/6/2018 | 4/6/2018 | 4/6/2018 | P | FAIL |
Andy J. Long
|
|
|
No construction entrance. Trackout and mud on road from site.
Correction request: - install rock construction entrance - clean up trackout
|
Random Inspection | 3/23/2018 | 3/23/2018 | 3/23/2018 | P | PEND |
Michael Zawacki
|
|
|
WIP, excavator and two front end loaders on site. Lots of trackout onto road, excavator has been good about cleaning trackout, will follow up.
|
Random Inspection | 1/25/2018 | 1/25/2018 | 1/25/2018 | P | PASS |
Michael Zawacki
|
|
|
Superior Blasting on site. No trackout leaving site. Stockpiled dirt on side of property.
|
Site Preparation | 1/8/2018 | 1/10/2018 | 1/10/2018 | A | PART |
Michael Zawacki
|
|
|
Grading has begun. Vegetation buffer in use, no wattle or perimeter BMPs in use. Entrance hasn't been constructed, equipment hasn't lef site, no trackout yet. Permit is on site.
|
General Inspection | 1/8/2018 | 1/8/2018 | 1/8/2018 | P | PASS |
Michael Zawacki
|
|
|
Central paving just showed up on site to begin grading lot. Neighborhood BMPs in place. Natural buffer surrounds area. Will need to monitor for trackout and entrance. Will follow up on 1/10.
|
General Inspection | 3/7/2019 | 3/7/2019 | | | |
Andy J. Long
|
|
|
|
General Inspection | 11/20/2018 | 11/20/2018 | | | |
Andy J. Long
|
|
|
|