Permit Information
Permit NumberESC19-00178
StatusFinaled
Name BRYAN MURDOCH
Site Address 3246 E WINDSONG DR
Project Name 
Customer NumberBLD19-00489 & GRD19-00008
ePlanReviewNo
Description
Site preparation inspection is required prior to excavation. Initial BMPs and perimter controls should be onsite for inspection. BMPs include stabilized rock construction entrance. Divert water from surrounding areas away from the disturbed portions of parcel. Install wattle as indicated on ESC plan on downhill side of the project. Post permit sign, control trash to prevent wind blown trash issues. Concrete washout containment required, any uncontained rinsing will be subject to violation.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final7/15/20207/16/20207/22/2020PPASS
DetailsMichael Zawacki
General Inspection7/15/20207/15/20207/15/2020 CANC
DetailsAndy J. Long
rescheduled for Site Final
General Inspection6/30/20206/30/20206/30/2020 PASS
DetailsMichael Zawacki
Completed and landscaped, siltfence still at bottom of hill.
General Inspection6/15/20206/15/20206/15/2020 PASS
DetailsAndy J. Long
General Inspection5/29/20205/29/20206/1/2020 PASS
DetailsMichael Zawacki
Pool completed. Landscapers on site.
General Inspection5/14/20205/14/20205/14/2020 PASS
DetailsAndy J. Long
General Inspection4/29/20204/29/20204/29/2020 PASS
DetailsMichael Zawacki
Pool is done, still doing work on concrete patio and around pool. Site still needs landscaping. Nothing leaving site, no issues.
General Inspection4/14/20204/14/20204/14/2020 CANC
DetailsAndy J. Long
General Inspection3/27/20203/27/20203/27/2020 PASS
DetailsMichael Zawacki
Needs pool area and landscaping completed. Has revegetation bond.
General Inspection3/12/20203/12/20203/12/2020 PASS
DetailsMichael Zawacki
Brundage Bone pump truck on site. No issues at time of inspection.
General Inspection2/26/20202/26/20202/28/2020 PASS
DetailsMichael Zawacki
Site still needs to be landscaped, has revegetation bond.
Site Final2/10/20202/11/20202/11/2020PDEFR
DetailsMichael Zawacki
Project has revegetation bond, will continue to monitor.
General Inspection2/10/20202/10/20202/10/2020 CANC
DetailsAndy J. Long
rescheduled for site final
General Inspection1/24/20201/24/20201/24/2020 PASS
DetailsMichael Zawacki
No issues at site. Waiting for spring to stabilize
General Inspection1/9/20201/9/20201/9/2020 PASS
DetailsMichael Zawacki
No activity. Home has revegetation bond.
General Inspection12/25/201912/25/201912/30/2019 PASS
DetailsMichael Zawacki
WIp on pool. Talked to rp at previous inspection, will be getting bond for home and landscape in spring.
General Inspection12/10/201912/10/201912/10/2019 PASS
DetailsMichael Zawacki
WIP on pool.
Talked to Bryan at site, plan on getting bond, will not be stabalized over winter.
General Inspection11/13/201911/13/201911/13/2019 PEND
DetailsMichael Zawacki
Met with Bryan on site. Driver overflowed washout. Concrete work is done and will take skid steer and clean up mess. Driveway is scheduled to be paved, no date, paver is busy and will get there when they can.
General Inspection5/2/20195/2/20195/2/2019PPASS
DetailsMichael Zawacki
Crew putting backfill back in foundation. Two kiddie pool washouts on site. No ESC issues.
BMP Violation4/24/20194/26/20195/1/2019PPASS
DetailsAndy J. Long
Corrections completed:

- permit sign posted
- silt fence installed downslope of excavation
- concrete washout washwater containment set up on site.
BMP Violation4/24/20194/24/20194/24/2019PFAIL
DetailsAndy J. Long
Mult iple violations at site.

- No ESC permit sign visible.
- No concrete washout containment, washwater dumped on ground.
- No downslope perimter controls

Washout violation. Lasher construction has already been warned about washout requirements. Final warning. Washout containment or solution must be planned ahead of placement of concrete.

corrections:
- provide new washout containment
- post new ESC permit sign on a stake or board at entrance to site.
- install wattle or silt fence along the bottom slope of site around the excavated backfill, in particular above the stormwater pond below.
- pick up any loose trash or material after concrete crew and before the trash box is built

Re-inspection required, notify ESC inspectors when corrections are complete. Compliance date is next wednesday May 1st PM
General Inspection4/17/20194/17/20194/17/2019PPART
DetailsMichael Zawacki
Work on installing forms and rebar.
No concrete washout on site. Needed before pour.
General Inspection4/2/20194/2/20194/2/2019PPASS
DetailsMichael Zawacki
Met with builder on site. No new activity, concrete crew supposed to start installing forms later this week, expecting to have building permit soon.
General Inspection3/22/20193/22/20193/22/2019PFAIL
DetailsMichael Zawacki
Excavation began without site prep. No installed perimeter controls, rill runs down to birdsong. Message sent to RP.