Permit Information
Permit NumberFIR19-00263
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 139 E WARM SPRINGS AVE
Project NameRonald McDonald House
Customer Number 
ePlanReviewYes
Description
New 2 story approximately 40000sqft structure. Fully sprinkled NFPA 13 system. Dry system serving the attic and outside overhangs. Residential sprinklers serving the guest room areas.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/12/201912/13/201912/13/2019APASS
DetailsJim Page
Final fire sprinkler inspection complete.

Rob Chambers is the contact. Thanks for all yo do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in12/11/201912/12/201912/12/2019ADONE
DetailsJim Page
Hydrostatic test for dry system complete, no pressure loss observed.

Rob Chambers is the contact. Need a 24 HR Air Test on the dry system. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro12/11/201912/12/201912/12/2019ADONE
DetailsJim Page
24 hour air test witnessed for dry system, no pressure loss observed.

Rob Chambers is the contact. this is a hydro on the dry system. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro12/9/201912/11/201912/11/2019PPART
DetailsJim Page
Hydrostatic test for level 1 witnessed, no pressure loss observed. 24 hour air test on dry system started at 1PM @ 41psi.

Rob is the contact. There will be 2 hydro''s to be done 1 wet and 1 dry. There is also a 24 hr air test that needs to be done for the dry system. Thanks for all you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro10/14/201910/14/201910/14/2019PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above suspended ceiling, southwest level 1 complete, southwest level 1 approved for cover.

Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro8/7/20198/8/20198/8/2019PPART
DetailsJim Page
Hydrostatic test for level 2 overhead fire sprinkler piping witnessed, no pressure loss observed.

Robert Chambers is the contact. This Hydro is for the 1st and 2nd floors. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro8/5/20198/5/20198/5/2019PPART
DetailsJim Page
Hydrostatic test for FDC piping witnessed, no pressure loss observed.

Robert Chambers is the contact. He would like to do an FDC Hydro at the same time. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in8/5/20198/5/20198/5/2019PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in corridor soffits, level 2B complete, corridor soffits on level 2B approved for cover.
INSP-Sprinkler Rough-in7/30/20197/31/20197/31/2019APART
DetailsJim Page
Remaining sprinkler piping above hardlids in level 2A corridor inspected, remaining level 2A corridor piping approved for cover. Corridor soffits in north hallway siffts inspected and approved for cover, east corridor soffits were not complete, east side hallway soffits not approved for cover until finished and inspected.

Robert Chambers is the contact. This rough-in is for the 2nd floor common areas. He would like this inspection first thing in the morning, if possible. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/29/20197/30/20197/30/2019AFAIL
DetailsJim Page
Soffits on level 2B were not completed, inspection was stopped due to this being the area of cover requested.

.

Robert Chambers is the contact. This rough-in is for the soffits on the 1st and 2nd floors. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/26/20197/26/20197/26/2019APART
DetailsJim Page
Tenting over sprinkler piping in the dumpster area has been corrected, dumpster area approved for cover.
INSP-Sprinkler Rough-in7/16/20197/17/20197/17/2019PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 1B corridor and corridor soffits complete, level 1B corridor approved for cover. Tenting in place at time of inspection for level 2B southeast stairs, southeast stair hard-lid approved for cover. Dumpster room will need the tenting adjusted to cover T to dry sidewall heads, this area cannot be covered until tenting has been corrected and inspected for compliance.

Robert Chambers is the contact. He would like this inspection for the 1st floor area B. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/16/20197/17/20197/16/2019PCANC
DetailsJim Page
Robert Chambers is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in7/10/20197/12/20197/12/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/tenting on wet system, level 2B complete to include remaining interior piping for dry system complete, areas inspected are approved for cover. Southeast stairwell will need to be inspected at a later date, no tenting installed in this area at time of inspection, cover is not approved for southeast stairwell.

Robert Chambers is the contact. This rough-in is for the 2nd floor area B Tinting.
Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/9/20197/10/20197/10/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above drop ceiling on level 1B complete resident rooms complete, levl 1B resident rooms approved for cover. ROugh to cover ispection for hallway soffits on level 2A complete, hallway soffits on level 2A approved for cover.

Robert Chambers is the contact. This rough-in inspection is for the 1st and 2nd floor soffits. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/1/20197/2/20197/2/2019PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/tenting above northwest stairs complete, area inspected approved for cover.

Robert Chambers is the contact. This rough-in inspection is for the 2nd floor area A. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/26/20196/27/20196/27/2019PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above lowered hardlids in kitchen/dining/living room complete, area inspected approved for cover. Exterior battered wall on southwest corner of Area A is filled with non-combustible insulation, area inspected approved for cover. As-builts need to show deleted heads that will no longer be in the area filled with insulation.

Robert Chambers is the contact for this inspection. This rough-in is for the 1st floor area A section 2. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/19/20196/20/20196/20/2019APART
DetailsJim Page
Rough to ocver inspection for level 2 A overhead fire sprinkler piping/tenting complete, dry system inspection for 2A has been inspected as well, section 2A approved for cover.

Robert Chambers is the contact. He asked for a 9AM inspection if possible and to please call him. This Final is for the 2nd Floor-Area A- RTC Tinting Inspection. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/14/20196/18/20196/18/2019APART
DetailsJim Page
Rough to cover ispection for remaining piping above hardlids on level 1 complete, hardlids on level 1 approved for cover.

Robert Chambers is the contact for this RTC/ Hydro inspection on the 1st Floor. He is hoping for an appointment around 9AM. We appreciate your help. Have a nice day Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/14/20196/17/20196/14/2019ACANC
DetailsJim Page
Robert Chambers is the contact for this RTC/ Hydro inspection on the 1st Floor. He is hoping for an appointment around 9AM. We appreciate your help. Have a nice day. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in6/11/20196/12/20196/12/2019APART
DetailsJim Page
Partial rough to cover inspection for attic dry system complete, notated city approved drawings with yellow highlighter areas approved for cover on the dry system.

Daniel Arce is the contact for this RTC inspection. He is requesting it to be done on the dry system. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Conference6/3/20196/5/20196/5/2019ADONE
DetailsJim Page
Fire conference complete. Hardlids in level 2 bathrooms can be installed before tenting, will verify tenting is in place after other trades install is complete.

Colton Cox is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/17/20195/20/20195/20/2019PPART
DetailsJim Page
Rough in inspection for Section A Phase 2 complete, notated city approved drawings with yellow highlighter areas approved for cover.

Colton Cox is the contact. This rough-in is for Section A Phase 2, and Colton would like it at 2PM if possible. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/10/20195/13/20195/13/2019PPASS
DetailsJim Page
OK to cover area "A" only, notes made to plan mod #1 plan on site.***MAS**
Colton Cox is the contact. This rough-in is for section A of the building. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus