Information based on query as of Monday, May 13, 2024.
Permit Information
Permit NumberBLD18-01425
StatusFinaled
Name MJ HARRIS CONSTRUCTION SERVICES LLC
Site Address 711 N CURTIS RD
Project NameSt. Alphonsus Rehab Hospital
Customer NumberGRD18-00042
ePlanReviewYes
Description
(ST. ALPHONSUS REHABILITATION HOSPITAL – NEW BUILDING) (DRH17-00423 and DRH18-000138) (CAR17-00017 and CUP17-00060) (Project Management-Ron Hill) (9-13-19 PLAN MODIFICATION TO INSTALL A GATE IN AN EXISTING OPENING IN THE FENCE THAT ENCLOSES THE THERAPY COURTYARD. FREE EGRESS THROUGH THE GATE IS REQUIRED TO ALWAYS BE AVAILABLE FROM THE EGRESS SIDE OF THE GATE. AN ACCESS CONTROL DEVICE WITH A KEYPAD WILL BE PROVIDED ON THE NON-EGRESS SIDE TO CONTROL ACCESS INTO THE COURTYARD. ALL EQUIPMENT IS REQUIRED TO BE SUITABLE FOR EXTERIOR LOCATIONS.) (1-12-19 PLAN MODIFICATION TO CONSTRUCT A FENCE WITH A GATE TO ENCLOSE THE EXTERIOR COURTYARD AREA. THE PATH OF EGRESS FROM THE COURTYARD WILL BE RELOCATED FROM WHAT WAS PREVIOUSLY PROPOSED. CARD READERS OR KEY PADS SHALL NOT OBSTRUCT EGRESS FROM THE FENCED AREA. EXCEPT AS ALLOWED FOR A DELAYED EGRESS SYSTEM WHEN INSTALLED, UNOBSTRUCTED EGRESS FROM THE COURTYARD AREA IS REQUIRED FOR ALL BUILDING OCCUPANTS AT ALL TIMES. IN ADDITION, TO INSTALL CARD READERS OR KEY PADS WITH DELAYED EGRESS LOCKING SYSTEMS ON SOME OTHER EGRESS DOORS. COMPLIANCE WITH ALL THE PROVISIONS OF 2015 IBC SECTION 1010.1.9.7 IS REQUIRED, INCLUDING THE DELAY DURATION NOT EXCEEDING 30 SECONDS.) The fire sprinkler system is used for occupancy and building area increase. To construct a 49,821 square foot one story rehabilitation hospital with 40 sleeping units located near the Southwest corner of the intersection of Emerald Street and Curtis Road. Every sleeping unit including the associated toilet/shower room, except for the bariatric toilet/shower rooms, is required to comply as an “accessible unit” for the disabled. Work is to include reinforced concrete footings (continuous and spot), reinforced concrete monolithic stem walls and slabs on grade, protected exterior slab edge insulation, reinforced concrete piers, steel columns with steel base plates, steel braced frames, steel beams, open web steel bar joists, steel roof deck, steel roof top mechanical screen walls, membrane roof covering over rigid insulation, primary and secondary roof drains, steel stud exterior nonbearing walls, sandstone exterior veneer, EIFS, exterior metal panels, exterior windows, exterior doors, metal sun shade awnings, interior nonbearing walls, interior doors, interior windows, a 2-hr fire barrier wall to function as a horizontal exit, 1-hr smoke barrier walls to create smoke compartments, I-2 rated corridors, a Type I grease hood and duct system, a grease trap, millwork, and interior finishes. Activities that require Special Inspection include soils, concrete, masonry, steel (including welding and bolting), and anchors post-installed in hardened concrete. The concrete floor slab will be recessed at the walk-in cooler and freezer and at floor tile areas. In addition, a 7 foot tall masonry trash enclosure with plaster finish and tube steel gates, a 17 foot tall masonry emergency generator enclosure with plaster finish and steel louvers, a 17 foot tall masonry bulk oxygen enclosure with plaster finish and steel louvers, and a therapy garden with an elevated pavilion structure will be constructed. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/26/20199/26/20199/26/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. OK for perm occ.
FIRE-Final Inspection9/18/20199/19/20199/19/2019APASS
DetailsTroy Cobbley
Life safety passed. Previous corrections have been addressed. Building inspector to verify gate plan mod. James Phone #: ###-####
FIRE-Final Inspection7/22/20197/24/20197/24/2019PPART
DetailsTroy Cobbley
A temporary for life safety is being given until the knox box is mounted, all signage mounted (Ox tank and fire doors), bollards installed and exit discharge lights tested as discussed.

Zach Phone #: ###-####
BLD-Conference7/23/20197/23/20197/23/2019PPEND
DetailsMike Jordan
zack Phone #: ###-####. Will be ok for Temp occ. once life/safety has given a temp occ. and the building official has approved the removal of the added gate from the court yard for proper egress width.
BLD-Final7/19/20197/22/20197/22/2019PPEND
DetailsMike Jordan
James Phone #: 205-908-480. Partial walk through on Area A. Needs to complete fire stopping at plumbing penetrations at rated walls, provide listing for clean out covers. Also area D provide rated fire extinguisher cabinant at rated walls in corridor next to mech room. Still need to ealk areas B, C , D and E.
BLD-Conference7/19/20197/19/20197/19/2019PDONE
DetailsMike Jordan
BLD-Ceiling Grid Inspection7/18/20197/19/20197/19/2019APASS
DetailsMike Jordan
James Phone #: ###-####
BLD-Final7/12/20197/15/20197/15/2019PNR
DetailsMike Jordan
James Phone #: ###-####
FIRE-Conference7/2/20197/3/20197/3/2019ADONE
DetailsTroy Cobbley
Per the agreement/discussion between myself/Chief Romeo and the general contractor equipment is allowed to be brought into the buidling for final installation as long as the fire sprinkler system is fully functional and the fire alarm system is monitoring the sprinkler system. Today I verified that the fire sprinkler riser devices are interconnected and tested to the new fire alarm system. Off site monitoring was verified. The monitoring is to remain active outside of normal work activities.

james Phone #: ###-####
FIRE-Conference7/2/20197/2/20197/2/2019PDONE
DetailsTroy Cobbley
The superintendant and I went over basic requirements for fire loading the building.
BLD-Ceiling Grid Inspection6/25/20196/26/20196/26/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. remainder of grid ok.
BLD-Ceiling Grid Inspection6/14/20196/17/20196/17/2019PPASS
DetailsMike Jordan
james Phone #: ###-####. Kitchen and freezer room only ok to install tile.
BLD-Ceiling Grid Inspection6/6/20196/7/20196/7/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. Areas D and E grids 16 to 10.
FIRE-Final Inspection6/4/20196/6/20196/6/2019PNR
DetailsTroy Cobbley
Fire Conference - I went over general life safety requirements such as addressing and the fire dept access.
James Phone #: ###-####
BLD-Ceiling Grid Inspection6/5/20196/6/20196/6/2019APASS
DetailsMike Jordan
james Phone #: ###-####. Area E North east portion only to grid 16 ok.
BLD-Ceiling Grid Inspection5/20/20195/21/20195/21/2019PPART
DetailsMike Jordan
James Phone #: ###-####. Area 2 ceiling grid. Noted areas at 1hr smoke barrier, 2hr. fire wall and at joints not ready for cover.
BLD-Ceiling Grid Inspection5/10/20195/10/20195/12/2019PPASS
DetailsDave Hannah
James- above celing insp Phone #: ###-####
BLD-Ceiling Grid Inspection5/8/20195/9/20195/9/2019ANR
DetailsMike Jordan
James Phone #: ###-####. Area A above grid not ready. Several assemblies not yet completd.
BLD-Framing/Rough-in5/2/20195/3/20195/3/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Walk through for double side at area H. Ok except for bathroom.
BLD-Framing/Rough-in4/29/20194/29/20194/29/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. Interior steel stud framed walls for area H ok.
BLD-Ceiling Grid Inspection4/24/20194/25/20194/25/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Restroom hardlids ok in area D.
BLD-Ceiling Grid Inspection4/19/20194/22/20194/22/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. Ok to start i stalling ceiing tile in ares A and B.
BLD-Framing/Rough-in4/16/20194/17/20194/17/2019APASS
DetailsMike Jordan
James- inspection on Shear rock Phone #: ###-####. Insulation in electrical romm and fire riser room walls. Completion of 1hr. firewall behind freezer ok to cover.
BLD-Framing/Rough-in4/12/20194/12/20194/12/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. Interior steel stud framed walls area F and G, ok to double side.
BLD-Framing/Rough-in4/9/20194/9/20194/9/2019PPASS
DetailsMike Jordan
James Phone #: ###-####. OK to one side 1 hr. fire walls in food storage room for install of walk in freezer.
BLD-Framing/Rough-in4/5/20194/8/20194/8/2019APART
DetailsMike Jordan
Bobbie Phone #: ###-####. Interior steel stud framed walls and sofits in areas F and G. Work is in progress. Needs to complete puddy pads on corridor 1hr. smoke barrier wall.
BLD-Framing/Rough-in4/2/20194/3/20194/3/2019APASS
DetailsMike Jordan
Zack Phone #: ###-####. INterior steel stud frmed walls at area E to gridline 16 and lobby area. Remaing hardlids in Area D ok.
BLD-Energy code compliance4/2/20194/2/20194/2/2019PPASS
DetailsMike Jordan
Are E, North exterior wall.
BLD-Framing/Rough-in4/1/20194/2/20194/2/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Area D bathroom hardlids. Area E interior steel stud walls, and rockwool at top of walls ok.
BLD-Ceiling Grid Inspection3/21/20193/22/20193/22/2019PPASS
DetailsMike Jordan
above ceiling inspection // James Phone #: ###-####. Bathroom hardlids only, Areas B and C.
BLD-Framing/Rough-in3/20/20193/21/20193/21/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Interior steel stud franed walls for data room only. Ok to one side data room only for equipment install.
BLD-Framing/Rough-in3/18/20193/19/20193/19/2019ANR
DetailsMike Jordan
James Phone #: ###-####. hardlid areas not ready.
BLD-Conference3/13/20193/13/20193/13/2019PDONE
DetailsMike Jordan
BLD-Framing/Rough-in3/4/20193/5/20193/5/2019APASS
DetailsMike Jordan
Zach Phone #: ###-####. Interior steel stud framed wall in area C ok to cover. Area H electrical room ok to one side to hang electrical panels.
BLD-Energy code compliance3/5/20193/5/20193/5/2019APASS
DetailsMike Jordan
Zach Phone #: ###-####. Area C.
BLD-Framing/Rough-in2/28/20193/1/20193/1/2019APASS
DetailsMike Jordan
Base layer of 5/8 type x rock on 2hr. fire wall at area C and D seperation.
BLD-Framing/Rough-in2/27/20192/27/20192/27/2019PPASS
DetailsMike Jordan
Work in progress on areas b and C.
BLD-Energy code compliance2/27/20192/27/20192/27/2019PPASS
DetailsMike Jordan
Area B and area C exterior walls ok to cover.
BLD-Framing/Rough-in2/22/20192/27/20192/27/2019ACANC
DetailsMike Jordan
BLD-Framing/Rough-in2/22/20192/22/20192/22/2019PPASS
DetailsMike Jordan
Interior steel stud framed walls for areas B and C. All menbrane penetrations have been protected at rated walls. Still needs to insulate exterior walls .
BLD-Framing/Rough-in2/20/20192/21/20192/21/2019ANR
DetailsMike Jordan
BLD-Framing/Rough-in2/20/20192/21/20192/21/2019ANR
DetailsMike Jordan
James Phone #: ###-####
BLD-Framing/Rough-in2/13/20192/14/20192/14/2019PPASS
DetailsMike Jordan
Parapet construction at areas D and E.
BLD-Framing/Rough-in2/13/20192/13/20192/13/2019PPEND
DetailsMike Jordan
Weekly visit to check on work in progress. Sheetrocking remaing walls in area A, one side sheet rock in area B from roof deck to ceiling elevation. More work on @hr. fire wall seperating Area C and D. Will inspect parapet construction on 2-14-19.
BLD-Framing/Rough-in2/7/20192/13/20192/13/2019ACANC
DetailsMike Jordan
BLD-Energy code compliance2/8/20192/8/20192/8/2019PPASS
DetailsMike Jordan
Area A exterior walls.
BLD-Framing/Rough-in2/7/20192/8/20192/8/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Area C exterior walls ok to cover on exterior side only. Area A ok to sheet rock. Araa B Ok to start one sideing only.
BLD-Framing/Rough-in2/6/20192/7/20192/7/2019APART
DetailsMike Jordan
exterior framing /// James Phone #: ###-####. Exterior steel stud framed walls at areas D and E, work is still in progess. Still needs to repair headers fro areas C .
BLD-Framing/Rough-in1/31/20192/1/20192/1/2019PFAIL
DetailsMike Jordan
James Phone #: ###-####. Area B interior steel stud framed walls. Needs to complete top of wall and mebrane penetration protection at 1hr. smoke barriers and 1hr. fire barries and recall framing inspection when completed.
BLD-Framing/Rough-in1/17/20191/18/20191/18/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Interior steel stud framed walls (sound walls and smoke partitions) at area A only ok to one side.
BLD-Framing/Rough-in1/10/20191/11/20191/11/2019APASS
DetailsMike Jordan
James Phone #: ###-####. Exterior wall framing at area 2, ok to cover exterior side only.
BLD-Framing/Rough-in1/2/20191/2/20191/2/2019PPART
DetailsMike Jordan
MJ Phone #: ###-####. Exterior walls for area A ok to dens glass exterior side only.
BLD-Wall Bracing12/13/201812/14/201812/14/2018ACANC
DetailsMike Jordan
James Phone #: ###-####
BLD-Framing/Rough-in12/14/201812/14/201812/14/2018APASS
DetailsMike Jordan
James Phone #: ###-####. Area E chevron bracing ok.
BLD-Framing/Rough-in12/7/201812/7/201812/7/2018PPART
DetailsMike Jordan
Work in progress on exterior steel stud walls at area a on grids 1 thru 8 on grids A,d and G. Still needs to install bridging, clips on lower sills and reshoot bottom track with correct shot pins. ok to sheet exterior in this area only.
BLD-Framing/Rough-in12/6/201812/7/201812/7/2018ANR
DetailsMike Jordan
James Phone #: ###-####. Needs to provide exterior wall details for welding, stud type ,spacong and connections.
BLD-Concrete11/19/201811/20/201811/20/2018PCANC
DetailsMike Jordan
rebar-James Phone #: ###-####
BLD-Foundation11/19/201811/20/201811/20/2018APART
DetailsMike Jordan
stem wall // James Phone #: ###-####. Stemwalls for area 3, Needs to clean dirt and debrie from bottom. Will have special inspection. Special inspector to verify bottom of stemwall has been cleaned.
BLD-Concrete11/5/201811/5/201811/5/2018PPART
DetailsMike Jordan
rebar- James Phone #: ###-####. Welded wire mesh and turn downs for interior slb on grade at area 2. Footings in area 4 on grids K and 7.
BLD-Framing/Rough-in10/31/201811/1/201811/1/2018ADEFR
DetailsMike Jordan
steel -James Phone #: ###-####. Will have special inspection.
BLD-Foundation10/23/201810/24/201810/24/2018APART
DetailsMike Jordan
rebar-James Phone #: ###-####. Interior column pad footings for area C.
BLD-Foundation10/3/201810/5/201810/5/2018APASS
DetailsMike Jordan
rebar // James Phone #: ###-####. Rmainder of area 2 and interior column pad footings in area 2. Prevoios exterior column pad footings on area 2 that were missing the top mat have been repaired. Exterior footings for area 3.
BLD-Foundation9/19/20189/20/20189/20/2018APART
DetailsMike Jordan
James Phone #: ###-####. Exterior perimeter footings for Area 2. Noted 4 F4B type column pad footings that require top and bottom mats of #4 rebar. Only one mat has been installed at this time. Special inspector to verify repair of these 4 F4B column pad footings prior to concrete placement.
BLD-Concrete9/18/20189/19/20189/19/2018APASS
DetailsMike Jordan
rebar- James Phone #: ###-####. Exterior footings for area A and interior column pad footings for area A on grid e and D.1 (first 4 only from south end).
BLD-Conference9/17/20189/17/20189/17/2018PCANC
DetailsMike Jordan
James-rebar Phone #: ###-####. Cancelled per contractor via phone call.
BLD-Foundation9/14/20189/17/20189/17/2018ANR
DetailsMike Jordan
James-rebar Phone #: ###-####. No city approved plans on jobsite. rescheduled for pm inspection.