Permit Information
Permit NumberESC15-01175
StatusFinaled
Name MIKE KOCI
Site Address 500 S CAPITOL BLVD
Project NameNew Hotel Downtown
Customer Number 
ePlanReviewNo
Description
The scope of work for this permit includes demolition of existing site amenities, including but not limited to the demolition and removal of existing asphalt parking lot, associated parking signs, existing site lighting and associated electrical work. Proposed new construction to include site rough grading and underground seepage beds for drainage with utility stub ups for future Hotel and parking structure.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/29/20176/29/20176/30/2017 PASS
DetailsAndy J. Long
ESC permit finaled. DI bags associated with project have been removed. DI bag in parking lot near Flicks is for the Idaho History Museum project.

No further inspections or requests.
DOC - Permit Finaled6/30/20176/30/20176/30/2017PPASS
DetailsAndy J. Long
General Inspection6/14/20176/14/20176/14/2017 CANC
DetailsAndy J. Long
General Inspection5/30/20175/30/20175/30/2017 PEND
DetailsAndy J. Long
General Inspection5/15/20175/15/20175/15/2017 CANC
DetailsMelissa Jannusch
Site Final4/28/20174/28/20175/2/2017PPEND
DetailsMelissa Jannusch
Perimeter DIs have been removed. There are still several DIs in the back parking lot and driveway that needs to be removed before site final.
General Inspection4/28/20174/28/20174/28/2017 PASS
DetailsAndy J. Long
General Inspection4/13/20174/13/20174/13/2017 PASS
DetailsMelissa Jannusch
Interior and exterior WIP. No sediment is leaving job site. Project ok.
General Inspection3/29/20173/29/20173/30/2017 CANC
DetailsAndy J. Long
General Inspection3/14/20173/14/20173/14/2017 PASS
DetailsAndy J. Long
General Inspection2/27/20172/27/20172/27/2017 PASS
DetailsAndy J. Long
WIP on interior and at 6th street parking entrance. Site access and street /sidewalk improvements & stabilization complete. No discharges observed.
General Inspection2/10/20172/10/20172/10/2017 PASS
DetailsMelissa Jannusch
General Inspection1/26/20171/26/20172/1/2017 PASS
DetailsMelissa Jannusch
General Inspection1/11/20171/11/20171/19/2017 CANC
DetailsAndy J. Long
General Inspection12/27/201612/27/201612/29/2016 PASS
DetailsAndy J. Long
General Inspection12/12/201612/12/201612/14/2016 PART
DetailsAndy J. Long
WIP on interior and concrete work on entry way plaza. Storm drains have sediment protection. No discharges or spills observed.

correction:
- sweep closed lane and staging area on Capitol once concrete work is complete.
General Inspection11/25/201611/25/201611/25/2016 PASS
DetailsAndy J. Long
General Inspection11/10/201611/10/201611/15/2016 PASS
DetailsAndy J. Long
WIP. No discharges, DIs have sediment filter bags installed, no trackout from construction areas. No corrections requested
General Inspection10/26/201610/26/201610/27/2016 PASS
DetailsAndy J. Long
No trackout to Myrtle or Capitol. Vertical construction in progress. No discharges or spills observed in staging areas.
General Inspection10/11/201610/11/201610/14/2016 CANC
DetailsAndy J. Long
General Inspection9/26/20169/26/20169/26/2016 PASS
DetailsAndy J. Long
Vertical construction in progress. No trackout or discharges around perimeter. No corrections issued at this time.
General Inspection9/9/20169/9/20169/9/2016 PASS
DetailsAndy J. Long
General Inspection8/25/20168/25/20168/25/2016 PASS
DetailsEvan Jenkins
work is in full progress. no discharges leaving site
General Inspection8/10/20168/10/20168/10/2016 PASS
DetailsEvan Jenkins
Vertical Construction in progress
General Inspection7/25/20167/26/20167/26/2016APASS
DetailsAndy J. Long
BMPs installed. Street gutters around site are clean. Vertical construction in progress.
General Inspection7/25/20167/25/20167/25/2016 CANC
DetailsAndy J. Long
General Inspection7/8/20167/8/20167/8/2016 PASS
DetailsAndy J. Long
Site perimeter is clean, no loose dirt or construction debris. Concrete washout contained, waste materials managed well. No trackout or discharges. Approved.
General Inspection6/23/20166/23/20166/23/2016 PASS
DetailsEvan Jenkins
General Inspection6/8/20166/8/20166/8/2016 PASS
DetailsAndy J. Long
General Inspection5/24/20165/24/20165/24/2016 PASS
DetailsEvan Jenkins
General Inspection5/5/20165/5/20165/5/2016 PASS
DetailsEvan Jenkins
WIP: no ESC issues observed at this time.
Site Preparation10/29/201510/29/201510/29/2015PPEND
DetailsAndy J. Long
RP for project will be Carl Benjamin - ###-####

Correction request:

-Need to post yellow ESC sign and install 2x DI bags by end of day.

Construction entrance will be rumble bar once the existing asphalp is removed. Requested to clean up any trackout or mud in the gutter.
Random Inspection10/20/201510/20/201510/20/2015PPASS
DetailsAndy J. Long
Initial site set up and security fencing is in progress. No earthwork yet. Will monitor to ensure a site preparation inspection is conducted.