Permit Information
Permit NumberESC19-00076
StatusIssued
Name CHRIS FUHRMAN
Site Address 5015 N PIERCE PARK LN
Project NamePierce Park E.S. Replacement
Customer Number 
ePlanReviewNo
Description
CONSTRUCT A NEW ELEMENTARY SCHOOL TO REPLACE THE EXISTING ELEMENTARY SCHOOL. REMOVE EXISTING ELEMENTARY SCHOOL AND EXISTING RELOCATABLE BUILDING(S) FROM SITE.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/12/20208/12/20208/12/2020 PASS
DetailsMichael Zawacki
Paving crew on site.
General Inspection7/28/20207/28/20207/28/2020 PASS
DetailsMichael Zawacki
Currently dewatering. Trench with well point on north east corner. Pumps are running to excavated hole on lot. No water on surface or leaving site.
Lots of prep work for parking lot, roads, and landscaping in front of school. Looks like the are drilling holes for lights. Water truck being used for dust control. No issues at site.
General Inspection7/13/20207/13/20207/13/2020 PASS
DetailsMichael Zawacki
School exterior work looks completed. WIP ut front on grading for parking lot. No esc issues.
General Inspection6/26/20206/26/20207/1/2020 PASS
DetailsMichael Zawacki
New school exterior completed, old school demoed. WIP on seepage beds and grading out front. Workers working on sidewalks and curbs, washout pan at site.
Water truck for compaction and dust control at site.
No issues.
General Inspection6/11/20206/11/20206/12/2020 PART
DetailsAndy J. Long
No major trackout, no discharges or fugitive dust observed. Storm drains have sediment protection installed.

Corrections needed:
- sweep Pierce Park in front of project
- maintain outbound (north) construction entrance, is compacted and not long enough

Left VM with RP Chris
General Inspection5/27/20205/27/20206/4/2020 CANC
DetailsAndy J. Long
General Inspection5/12/20205/12/20205/12/2020 CANC
DetailsAndy J. Long
General Inspection4/27/20204/27/20204/27/2020 PASS
DetailsMichael Zawacki
ALL work is interior. Ring around new school has been paved, area has not been landscaped. Clean, no issues.
General Inspection4/10/20204/10/20204/10/2020 CANC
DetailsAndy J. Long
General Inspection3/26/20203/26/20203/27/2020 CANC
DetailsAndy J. Long
General Inspection3/11/20203/11/20203/11/2020 PASS
DetailsMichael Zawacki
Site is contained, nothing leaving, no issues.
General Inspection2/25/20202/25/20202/27/2020 PASS
DetailsMichael Zawacki
Everything contained on site. Washout next to mortar mixer in rear of site. Lots of dirt on pavement within site, none being tracked out. No loose trash.
General Inspection2/7/20202/7/20202/10/2020 PASS
DetailsAndy J. Long
General Inspection1/22/20201/23/20201/27/2020PPASS
DetailsMichael Zawacki
South entrance is locked, everyone forced to go out pitrun to rock. Area around school paved. Work at site is interior or siding. SOme mud in site from genie lifts, none leaving site.
DIs on Pierce still have plenty of room.
General Inspection1/20/20201/20/20201/22/2020 CANC
DetailsAndy J. Long
General Inspection1/3/20201/3/20201/3/2020 PASS
DetailsMichael Zawacki
Northern entrance off of Pierce is closed. arking lot around school paved, lots of trackon fromn lifts, no leaving site. Trash is cleaned up, dumpsters in muddy area.
General Inspection12/19/201912/19/201912/19/2019 PASS
DetailsMichael Zawacki
Site is contained. Section of entrance between gate and rock now paved. No tracking to pierce park.
General Inspection12/4/201912/4/201912/4/2019 PASS
DetailsMichael Zawacki
Entrance has been paved near pierce park. No trackout, multiple washouts. Site is all contained.
No issues.
General Inspection11/12/201911/12/201911/12/2019 PASS
DetailsMichael Zawacki
Lots of concrete work, slabs, sidewalks, and curbing. Washout on site and being used, no dumped anywhere. No trackout or loose trash. No ESC issues at site.
General Inspection10/28/201910/28/201910/28/2019PPASS
DetailsMichael Zawacki
Site is clean andcontained, washouts in use. All trash and storage on rear of site.
Some new rock added to entrance, mix of crush and round rock, kind of small.
General Inspection9/27/20199/27/20199/27/2019PPASS
DetailsMichael Zawacki
Met with ESI on site. Only issue is to repair and turn entrance so it is not so compacted.
Masons and concrete crews using washouts. All material, trash, and recycling is on rear of lot.
General Inspection8/2/20198/2/20198/2/2019PPASS
DetailsAndy J. Long
WIP on pouring slabs and vertical CMU work. Concrete washout pans are staged around the site and in use. RP on duty at time of inspection. Permit signs posted, no trackout, discharges, or blowing fugitve dust.

Correction request to make a mortar mixing station containment area and to refresh south construction entrance next week.
General Inspection7/11/20197/11/20197/11/2019PPASS
DetailsMichael Zawacki
Masons getting ready to do block walls. Most workers parking in school lot in front of building. Two stabalized entrances, no trackout. Will need to watch for blowing styrofoam insulation during construction.
General Inspection6/26/20196/26/20196/26/2019PPASS
DetailsMichael Zawacki
Both entrances are stabalized, no entrances. Currently working on foundation, 3 washouts on site, some concrete spills on site. Perimeter controls in place, no blowing dust, no loose trash.
General Inspection5/28/20195/28/20195/28/2019PFAIL
DetailsAndy J. Long
Correction request:
- clean up trackout on sidewalk and street at end of the day
- add additional rock to construction entrance to increase entrance length to a minimum of 50 ft.
General Inspection5/7/20195/8/20195/8/2019APASS
DetailsMichael Zawacki
Stabalized entances scheduled to be installed today. Buffers have been left on perimeter. Sunroc doing earthwork, bringing water trucks and sweepers everyday.
Site Preparation4/19/20194/19/20194/19/2019PPASS
DetailsAndy J. Long
ESC plan and SWPPP book onsite for review. BMPs installed include:
- storm drain sediment protection installed on Pierce Park street
- perimeter wattles installed west of clearing limits
- dewatering for sewer connection infiltration basin has been excavated
- existing grass has been vegetated.

BMPs not yet installed:
- construction entrance (next week)
- concrete washout (Ecopan listed on ESC site map.

Approved for construction.