Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberESC16-00561
StatusFinaled
Name STEVE BRUNEEL
Site Address 2659 E MESA VERDE CT
Project NameDavis Residence
Customer Number 
ePlanReviewNo
Description
Single family hillside residence; BMPs include preservation of existing vegetation outside of clearing limits, perimter wattles along frontage, down gradient sediment controls. Site preparation inspection required prior to earthwork.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final9/28/20179/28/20179/28/2017PPASS
DetailsAndy J. Long
HOme complete, landscaped, temporary BMPs (silt fence & wattles) have been removed. Perimeter of lot has had a fiber mulch/tacifier applied for stabilization. Home is occupied. ESC permit conditions satisfied.
General Inspection9/26/20179/26/20179/28/2017 CANC
DetailsAndy J. Long
General Inspection9/11/20179/11/20179/19/2017 CANC
DetailsAndy J. Long
General Inspection8/24/20178/25/20178/25/2017APASS
DetailsAndy J. Long
WIP on driveway and prep for landscaping. No trackout or discharges. Trash contained. RP-GC onsite.
General Inspection8/22/20178/22/20178/24/2017 CANC
DetailsAndy J. Long
General Inspection8/7/20178/7/20178/14/2017 CANC
DetailsAndy J. Long
General Inspection7/21/20177/21/20177/21/2017 CANC
DetailsAndy J. Long
Tracking Control6/30/20177/6/20177/5/2017APASS
DetailsMelissa Jannusch
Trackout has been swept up to minimum compliance.
Tracking Control6/21/20176/28/20176/30/2017AFAIL
DetailsMelissa Jannusch
Trackout has not been cleaned up. Talked with site owner on site and told him the trackout needs to be swept up and informed him that enforcement will be escalated for repeat violations that are not addressed.

Called RP that is listed on permit and left a message with him asking for an update on the progress and plan for cleanup and when he thinks the correction will be completed. Informed him about the escalation procedure and warned him that continued noncompliance may lead to fines or stop work orders for the site.
Complaint Inspection6/26/20176/26/20176/26/2017PPART
DetailsAndy J. Long
Two tracks of track-out from driveway entrance to Travertine need to be swept including a sweep of the gutter.

All sub-contractors should be made aware of the trackout regulations and proper disposal of trash within the trash containement on site.

Written correction notice posted on ESC permit sign.

No discharges, permit posted, trash containment and some perimeter BMPs installed.
Complaint Inspection6/20/20176/21/20176/21/2017AFAIL
DetailsMelissa Jannusch
Significant trackout. No sign posted. Posted sign on site. Called RP and requested sweep up of trackout. Follow up next week.
General Inspection6/19/20176/19/20176/19/2017 CANC
DetailsMelissa Jannusch
General Inspection6/2/20176/2/20176/2/2017 PASS
DetailsAndy J. Long
WIP on exterior. Project scheduled to be complete end of July. No trackout discharges to Mesa Verde . Rear hillside vegetation has established and perimeter silt fence and wattles are still installed till final landscaping/stabilization.
General Inspection5/18/20175/18/20175/19/2017 PASS
DetailsMelissa Jannusch
WIP. No ESC violations observed.
General Inspection5/3/20175/3/20175/3/2017 PASS
DetailsMelissa Jannusch
WIP. Vegetation/weeds stabilizing soil in the back yard. Silt fence is trenched but needs repair in several places.
General Inspection4/18/20174/18/20174/18/2017 CANC
DetailsAndy J. Long
General Inspection4/3/20174/3/20174/3/2017 CANC
DetailsAndy J. Long
General Inspection3/17/20173/17/20173/17/2017 CANC
DetailsAndy J. Long
General Inspection3/2/20173/2/20173/6/2017 PASS
DetailsAndy J. Long
No trackout or loose materials leaving site. Trash contained Discussed rear silt fence installation with RP-GC. Grass starting to row. Will check on conditions next inspection. No corrections at this time.
BMP Violation2/8/20172/15/20172/15/2017PFAIL
DetailsMelissa Jannusch
Corrections addressed: Trash
Corrections not addressed. Track out, silt fence, sign
Left a message for RP Steve Bruneel. 2nd request to remove or reinstall silt fence, address trackout, and post sign. Follow up 2/23.
General Inspection2/8/20172/8/20172/8/2017 FAIL
DetailsAndy J. Long
Corrections needed at site as sites dries up

- clean up trackout from entrance on sidewalk apron and gutter
- re-post ESC permit sign
- remove or re-install silt fence BMP that is not trenched in
- trash container filled above brim needs service to prevent more windblown trash

Will address hillside BMPs and slope repair once conditions dry
General Inspection1/24/20171/24/20172/1/2017 CANC
DetailsAndy J. Long
General Inspection1/6/20171/6/20171/10/2017 PASS
DetailsAndy J. Long
WIP on frame. No trackout. Snowy/frozen conditions. No muddy or polluted snowmelt . Inspected 1/9
General Inspection12/22/201612/22/201612/29/2016 CANC
DetailsAndy J. Long
General Inspection12/7/201612/7/201612/15/2016 CANC
DetailsAndy J. Long
General Inspection11/22/201611/22/201611/23/2016 PASS
DetailsAndy J. Long
WIP on frame and roof. No earth work occuring at this time. Permit sign posted on porta-pot.

No trackout, sidewalk and gutter have been swept. No erosion issues on slopes observed, slopes have been tracked. Silt fence section installed along SW slope below future rain gutter outlet pipe. No wind blown trash issues observed or reported by neighbors.
Site is currently in compliance.
General Inspection11/4/201611/4/201611/8/2016 PASS
DetailsAndy J. Long
General Inspection10/18/201610/18/201610/18/2016APASS
DetailsAndy J. Long
No activity at time of inspeciton. No muddy runoff coming from site. Perimeter sediment control wattles are installed properly and no trackout.

RP/GC installed silt along back side of home below a disturbed slope area as requested. No violations, corrections requested in previous inspections have been addressed. N
General Inspection10/14/201610/14/201610/14/2016APASS
DetailsDaryl DeGrange
Silt fence installed at lower edges of site.
General Inspection10/4/201610/6/201610/6/2016PPEND
DetailsAndy J. Long
No fugitive dust occuring at time of inspection. Street , sidewalk and gutter are free of loose sediment or trackout.

Silt fence installation at around the lower edges of site has not yet been accomplished.
Complaint Inspection10/3/201610/3/201610/4/2016PPART
DetailsAndy J. Long
Dust Complaints.

Removal of excess stockpile from foundation excavation and boulder removal is still in progress. Water is now available at site and garden hose was being used to spray down stockpile prior to loading dumptruck at time of inspection. During boulder excavation a water truck was onsite.

Some localized dust occuring due to this loading activity but no continuous plumes. Water suppression appeared to be working.

Significant dust at time of inspection from concrete saw cutting foundation for utility installations. Request that either same hose or new hose be used for wet cutting of the concrete. Noted that this is also an occupational hazard. Employee said all saw cutting was now complete. Informed RP and GC to provide this subcontractor water for saw cutting as much as practicable.

Yellow permit sign is posted, no trackout. Street and gutter have been cleaned/swept regularly. Dust control needs improvement. Warning issued.

RP/GC stated that all excess dirt will be gone by Thursday. ESC crew to install silt fence perimeter below slopes areas where dirt has been spread/graded and hydroseed. Follow up inspection scheduled for Thursday PM
General Inspection7/28/20167/28/20167/28/2016PPASS
DetailsAndy J. Long
Excavation crew still onsite removing excess boulders. Boulders being transported up to new SFH site prep work Windsong.

No trackout or discharges. BMPs installed.
General Inspection6/24/20166/24/20166/24/2016PPASS
DetailsAndy J. Long
Perimeter wattles now installed. GC has permission to temporarily use adjacent lot for rock stockpile, will re-vegetate/restore as needed.

Permit sign posted, GC responded to corrections promptly.
Site Preparation6/21/20166/22/20166/22/2016APART
DetailsAndy J. Long
Rock removal excavation crew active on site prior to site prep inspection. Warning issued.

Water truck brought to site to control dust as digging up large boulers. RP/GC stated that sediment control wattle will be installed today and ESC sign posted. Back side of lot BMP will be to maintain existing vegetation. Builder to re-survey parcel to establish clear lot lines.
Site Preparation6/21/20166/21/20166/21/2016PFAIL
DetailsAndy J. Long
No site prep inspection requested, no permit sign posted. No BMPs installed or discussed with ESC division. Appears clearing and rock stockpiling has already crossed over to the unoccupied vacant lot.

RP listed not on site and unknown to onsite excavator. Excavator was using water truck for dust control.

CN issued to Bruno Built. No trackout or discharges, but need to seet up site per ESC plan asap.