Permit Information
Permit NumberESC16-01189
StatusFinaled
Name KENNETH R SCAGGS
Site Address 7711 W PREECE DR
Project NameMARINA APARTMENTS
Customer Number 
ePlanReviewNo
Description
(MARINA APARTMENTS) - Grading permit to excavate, grade and compact site earth materials in preparation for a new shell building to be constructed under BLD . All work to be performed as approved by the Public Works Department and Planning & Zoning Department under PUD16-00007. Underground utilities only, no buildings or footings are allowed to be constructed under this permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final8/24/20189/7/20189/7/2018APASS
DetailsAndy J. Long
DI bag on Preece has been removed. ESC permit conditions satisfied. ESC permit finaled
Site Final8/24/20188/24/20188/24/2018PCANC
DetailsAndy J. Long
Site Final8/24/20188/24/20188/24/2018PNR
DetailsAndy J. Long
Still need to remove DI bag on Preece. RP dave said he will do it. Rescheduled for two weeks out....
General Inspection7/16/20187/16/20187/16/2018 PASS
DetailsMichael Zawacki
Witches hat still in on Preece, everything else on site complete.
Site Final5/29/20185/29/20185/30/2018PNR
DetailsAndy J. Long
Need to remove temporary DI protection on Preece on south side of site.
General Inspection5/28/20185/28/20185/29/2018 CANC
DetailsAndy J. Long
General Inspection4/10/20184/10/20184/10/2018 PASS
DetailsMichael Zawacki
Construction and landscaping complete. Most are leased out. Some of the drains still have inlet protection.
General Inspection2/23/20182/23/20182/23/2018 CANC
DetailsAndy J. Long
General Inspection1/5/20181/8/20181/8/2018APASS
DetailsAndy J. Long
No trackout or discharges leaving site.

All vertical construction of units in Marina Apartments are complete. Units along Emerald are finished and some occpied with paved access, stormwater retention, parking. Sod landscaping has been completed along the south side of site. WIP on interior and site work along Preece to the north.

Corrections/tasks remaining to final ESC permit for site:
- remove silt fence along Emerald, complete landscaping and sweep gutter and site access curbing.
- remove stockpile on south side of site, finish paving and sweep apron. As conditions warm this week the frozen dirt on apron should be swept
- check perimeter for any loose construction trash, put in dumpster, remove dumpster
- sweep Preece, remove DI bag from MS4 storm drain.

- Call for site final. All individual unit ESC permits for project have been closed, all remaining ESC inspections will be on this main site permit.
General Inspection1/3/20181/3/20181/5/2018ACANC
DetailsAndy J. Long
General Inspection11/27/201711/27/201711/27/2017APASS
DetailsAndy J. Long
Trash around site has been picked up, regular pick up and scrap collection is in progress. No trackout or discharges offsite. Interior is still not yet fully paved or landscaped.

Site is still on trash warning.

Need to pick up roof material wrappings along
General Inspection11/17/201711/21/201711/20/2017PCANC
DetailsAndy J. Long
BMP Violation11/17/201711/17/201711/17/2017APASS
DetailsAndy J. Long
trash deadline

- All perimeter trash has been picked up as requested.

- Both entrances on Preece and Emerald have been swept.

- RP/GC on duty directing washout locations. I requested that a daily perimeter trash pick up be completed until the duration. Wind and active roofing still has potential for wind blown trash.

No trackout to streets, no offsite stormwater discharges.

Will inspect weekly until project completion in December. Landscaping to begin next week.
BMP Violation11/15/201711/15/201711/15/2017AFAIL
DetailsAndy J. Long
Site walk through with developer and interim RP:

Large trash piles around perimeter have been picked up but still noticable amount of loose trash around site. Dumpster has been emptied, crews to continue pick up today and tomorrow AM, inspection Thursday PM must pass or fines d/or SWO shall be issued.

- sweep and clean Preece and aprons to both Preece and Emerald.
BMP Violation11/14/201711/14/201711/15/2017APEND
DetailsAndy J. Long
pick up in progress. Some corrections completed. Status pending walk through inspection 11/15
Complaint Inspection11/13/201711/13/201711/13/2017AFAIL
DetailsAndy J. Long
Uncontained trash arond entire site. Dumpster at south end of site was emptied today.

24 hour correction request to complete trash pick up around site. Piles along Preece and silt fence on Emerald should be picked up today.

Gutter and apron on Preece should be swept.

Developer said crews will be completing trash pick up today. If trash around site is not picked up tomorrow Stop Work Orders will be issued until complete.
General Inspection10/11/201710/11/201710/11/2017PFAIL
DetailsMichael Zawacki
Silt fence along Emerald damaged. Sidewalk along Preece covered in dirt. Lots of dirt in parking area, none yet tracked out. Dumpster on sitr but lots of loose garbage blowing around. DI is clean.
General Inspection9/19/20179/19/20179/19/2017 CANC
DetailsAndy J. Long
General Inspection8/2/20178/2/20178/4/2017APEND
DetailsAndy J. Long
No trackout off site to Preece or Emerald. Interior still needs additional sweeping. Trash has been serviced.

Notified Summit Development that operator does not appear to have an "active" NOI for the CGP 2017 coverage.
General Inspection7/28/20177/31/20178/2/2017ACANC
DetailsAndy J. Long
General Inspection7/24/20177/25/20177/28/2017ACANC
DetailsAndy J. Long
Conference7/19/20177/19/20177/24/2017PCANC
DetailsAndy J. Long
General Inspection7/18/20177/18/20177/19/2017PPART
DetailsAndy J. Long
WIP at Marina Apartments. Vertical construction at south entrance along Emerald. Grading and foundation work along Preece in the north half.

No excess trash or overfull dumpsters. MS4 on Preece has sediment bag protection, no discharges or trackout offsite. Silt fence on Emerald is trenched in, though some areas are sagging and should be reattached. Area is soon to be replaced by a landscaped berm. No sediment leaving site along this border.

Corrections needed:
- sweep up loose dirt and gravel in the paved areas. Some areas are still unpaved.
- pick up any loose trash laying around site.
- continue weekly sweeping of
- check on CGP status, no up to date inspections in SWPPP found. Search for 2017 CGP eNOI was not found. Will notify owner/ and operator.
General Inspection6/20/20176/21/20176/21/2017APASS
DetailsAndy J. Long
No trackout to Emerald or Preece. Permit sign posted on Preece. Exits have had asphalt installed. No corrections issued at this time.
General Inspection6/9/20176/13/20176/20/2017PCANC
DetailsAndy J. Long
rescheduled 6/21
General Inspection6/8/20176/9/20176/9/2017PCANC
DetailsAndy J. Long
General Inspection6/7/20176/7/20176/8/2017 CANC
DetailsAndy J. Long
General Inspection4/19/20174/19/20174/19/2017 CANC
DetailsMelissa Jannusch
Conference11/23/201611/28/201611/30/2016PPEND
DetailsAndy J. Long
working with Dusty @ Granite to get valid RP contact on permit.

Dusty cell ###-####
General Inspection11/17/201611/22/201611/23/2016APEND
DetailsAndy J. Long
should hear from Granite Excavation to get certified RP on permit....

Emailed Summit Development to get Granite Excavation RP on permit.
BMP Violation11/17/201611/17/201611/17/2016AFAIL
DetailsAndy J. Long
No trackout or discharges, but improper permit and project start-up procedures:

- no site preparation inspection requested as required
- RP Ken Scaggs is listed but is not directly associated or in control of project
- SWPPP & eNOI filed by Granite Excavation, they should have RP
- No inspection reports filled out in SWPPP binder
- No permit or contact information on yellow permit sign (I provided permint # and Granite contact Dusty Hibbard)