Information based on query as of Friday, May 10, 2024.
Permit Information
Permit NumberESC17-01157
StatusFinaled
Name ALVARO R GONZALEZ
Site Address 11818 W JOPLIN RD
Project NamePamela Baker Park
Customer Number 
ePlanReviewNo
Description
Park & Pathway space. Flat area located between treatment plant pasture area and subdivsion in Eagle. DEWATERing is anticipated for construction on new ponds in the park area. Dewatering plan and onsite dewatering inspection shall be required prior to begining dewatering operation. Existing Thurman Mill irrigation ditch runs through center of site and shall be preserved. Protect existing storm drains at site access on Colchester. Staging area must have trash and leakproof concrete washout containment. Site preparation inspection is required. CGP eNOI filed by owner and operator see IDR10008Y & IDR1000CG
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final4/16/20194/19/20194/18/2019APASS
DetailsMichael Zawacki
DOC - Permit Finaled4/18/20194/18/20194/18/2019PPASS
DetailsMichael Zawacki
General Inspection4/16/20194/16/20194/16/2019 CANC
DetailsAndy J. Long
General Inspection4/1/20194/1/20194/1/2019 CANC
DetailsMichael Zawacki
General Inspection3/15/20193/15/20193/18/2019 CANC
DetailsMichael Zawacki
General Inspection2/28/20192/28/20192/28/2019 CANC
DetailsMichael Zawacki
General Inspection2/13/20192/13/20192/14/2019 CANC
DetailsAndy J. Long
General Inspection1/29/20191/29/20191/30/2019 PASS
DetailsMichael Zawacki
General Inspection1/11/20191/14/20191/14/2019PPASS
DetailsMichael Zawacki
No disturbances to creek channel. Walked perimeter, no wind blown trash from homes inEagle blowing onto Boise parcel. Landscapers on Eagle side.
General Inspection1/14/20191/14/20191/14/2019PPASS
DetailsMichael Zawacki
check on ECBs and other BMPs along Joplin
Wttle and silt fence still installed along canal where new culvert installed. Wattle and ECB on hillside where there was disturbance. Some tenting, no rills occurring.
General Inspection1/11/20191/11/20191/11/2019 CANC
DetailsAndy J. Long
rescheduled
General Inspection12/27/201812/27/201812/27/2018 CANC
DetailsMichael Zawacki
General Inspection12/12/201812/12/201812/12/2018 PASS
DetailsMichael Zawacki
Greenbelt and parking lot paved. No landscaping around ponds.
General Inspection11/23/201811/27/201811/27/2018PCANC
DetailsAndy J. Long
General Inspection11/22/201811/22/201811/23/2018 CANC
DetailsAndy J. Long
General Inspection11/7/201811/7/201811/7/2018 CANC
DetailsAndy J. Long
General Inspection10/23/201810/23/201810/24/2018 PASS
DetailsAndy J. Long
WIP on park development. NO wind blown dust, trackout or discharges observed.
General Inspection10/4/201810/8/201810/8/2018APASS
DetailsMichael Zawacki
General Inspection10/4/201810/4/201810/4/2018 CANC
DetailsAndy J. Long
rescheduled
General Inspection9/19/20189/19/20189/19/2018 PASS
DetailsMichael Zawacki
No new activity.
General Inspection9/4/20189/4/20189/4/2018 PASS
DetailsMichael Zawacki
No new activity.
General Inspection8/17/20188/17/20188/17/2018 CANC
DetailsMichael Zawacki
General Inspection8/2/20188/2/20188/3/2018 PASS
DetailsMichael Zawacki
Work on leveling stockpiles. No dust or other issues.
General Inspection7/18/20187/18/20187/19/2018 PASS
DetailsMichael Zawacki
General Inspection6/12/20186/12/20186/13/2018PPASS
DetailsMichael Zawacki
Pathway bordering WWTP completed. Sidewalks and curbing for park parking lot in place. Landscapers working in area. Lots of work for future homesites that arein the Eagle. Neighborhood BMPs in place. Lots of material being hauled away.
General Inspection5/16/20185/16/20185/16/2018PPASS
DetailsMichael Zawacki
General Inspection5/1/20185/1/20185/1/2018PPASS
DetailsMichael Zawacki
Area still exposed and roads under construction. Not much for BMPs but no issues. Majority of area is stockpiles of river rock.
General Inspection3/16/20183/20/20183/20/2018APEND
DetailsAndy J. Long
CGP tracking # IDR1000CG

pete.wilson@idahomaterials.com
Conference3/15/20183/16/20183/16/2018APEND
DetailsAndy J. Long
Project is in Boise and Eagle, working out if Boise has jurisdiction over all disturbed areas.

Need to improve sediment protection along Walling Creek and check for 404 permit.
General Inspection3/12/20183/12/20183/12/2018PPEND
DetailsAndy J. Long
WIP park.

Need to check scope of work, adjacent subdivision development has improperly installed wattle along Thurman Mill creek. Needs proper trenching and/or more stakes.
General Inspection1/3/20181/3/20181/3/2018PCANC
DetailsMichael Zawacki
No access.
General Inspection10/20/201710/20/201710/24/2017PCANC
DetailsMichael Zawacki