Site Final | 4/6/2018 | 4/6/2018 | 4/6/2018 | P | PASS |
Andy J. Long
|
|
|
Sunny Ridge phase 2 complete. All temporary BMPS removed, included sediment filter bags. Concrete washout area has been cleaned and hauled away. ESC permit conditions satisfied.
|
General Inspection | 3/15/2018 | 3/15/2018 | 3/15/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/12/2018 | 2/12/2018 | 2/15/2018 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 1/11/2018 | 1/11/2018 | 1/11/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/11/2017 | 12/11/2017 | 12/11/2017 | | PEND |
Michael Zawacki
|
|
|
DI bags need to be removed. Once done permit will be finalled.
|
Site Final | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PEND |
Michael Zawacki
|
|
|
check for DI bags left behind... DI bags still installed.
|
General Inspection | 10/9/2017 | 10/9/2017 | 10/12/2017 | | PASS |
Michael Zawacki
|
|
|
no new activity.
|
General Inspection | 8/7/2017 | 8/7/2017 | 8/7/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/6/2017 | 7/6/2017 | 7/6/2017 | | PEND |
Melissa Jannusch
|
|
|
Concrete washout has been removed. No activity on site.
|
General Inspection | 6/2/2017 | 6/5/2017 | 6/6/2017 | A | PEND |
Melissa Jannusch
|
|
|
Phase complete. Some DI bags still in place. Concrete washout needs to be cleaned up before this permit can be finaled.
|
General Inspection | 6/1/2017 | 6/1/2017 | 6/2/2017 | | CANC |
Melissa Jannusch
|
|
|
Rescheduled
|
General Inspection | 5/1/2017 | 5/1/2017 | 5/1/2017 | | PEND |
Andy J. Long
|
|
|
Sunnyridge phase 3 is complete and all homes have been built. Permit open for clean up of old concrete washout waste and debris on Bear Ridge. Located in future are for phase 4. No trackout or discharges from site, subdivision retains all storm water
|
General Inspection | 3/30/2017 | 3/30/2017 | 3/30/2017 | | PASS |
Melissa Jannusch
|
|
|
Work has not resumed. Equipment on site. DI bags ok. No ESC issues observed.
|
General Inspection | 2/27/2017 | 2/27/2017 | 2/28/2017 | | PASS |
Melissa Jannusch
|
|
|
No issues
|
General Inspection | 1/26/2017 | 1/26/2017 | 1/27/2017 | | PASS |
Melissa Jannusch
|
|
|
No WIP snow covered conditions. DI bags still in on Deer Ridge Rd. Currently frozen check back once thawed for removal. Concrete washout materials appear to have been removed. Streets are clean and snow plowed.
|
General Inspection | 12/26/2016 | 12/26/2016 | 12/28/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/24/2016 | 11/24/2016 | 11/25/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/24/2016 | 10/24/2016 | 10/24/2016 | A | PEND |
Andy J. Long
|
|
|
All SFHs in Sunnyridge phase 3 are no complete, no current activity or open parcels. Storm drains on Deer Ridge still have DI bags installed and street needs sweeping. Dried concrete washout material has not been hauled away.
Knife River and Hayden Homes not active on site, will monitor and check in with developer on future phases. No immediate corrections.
|
General Inspection | 10/10/2016 | 10/10/2016 | 10/13/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/6/2016 | 9/7/2016 | 9/7/2016 | P | PASS |
Andy J. Long
|
|
|
Permit open to monitor temp BMP removal. SFHs in Sunnyridge in progress by Hayden Homes. No subdivsion work. No correction requests at this time.
|
General Inspection | 9/5/2016 | 9/5/2016 | 9/6/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 8/4/2016 | 8/4/2016 | 8/5/2016 | | PASS |
Andy J. Long
|
|
|
duplicate inspection
|
General Inspection | 8/5/2016 | 8/5/2016 | 8/5/2016 | P | PASS |
Andy J. Long
|
|
|
SFHs in progress. Streets and sidewalk are clean, storm drains have sediment protection. Lined washout located in southwest corner of Sunnyridge. No corrections requested at this time. Hayden Homes is main builder.
|
General Inspection | 7/4/2016 | 7/4/2016 | 7/4/2016 | | CANC |
Evan Jenkins
|
|
|
holiday
|
General Inspection | 6/2/2016 | 6/2/2016 | 6/3/2016 | | CANC |
Evan Jenkins
|
|
|
|
General Inspection | 5/2/2016 | 5/2/2016 | 5/2/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/1/2016 | 4/1/2016 | 4/1/2016 | | PART |
Andy J. Long
|
|
|
WIP on frames of homes by multiple contractors. Streets are relatively, common area lanscaping is now complete on Clear Ridge. DI bags into the stormwater pond are filtering sediment. Trash and materials are contained at each site.
Corrections: - need new washout before next round of foundations is approved to start. - sweep roads and gutters on Dear Ridge
|
General Inspection | 2/24/2016 | 3/1/2016 | 3/4/2016 | P | PASS |
Andy J. Long
|
|
|
WIP on SFHs in Sunnyridge. No discharges, resident complaints, or other violations. Subdivision storm drains have sediment protection. Designated washout is being utilized.
|
General Inspection | 2/16/2016 | 2/24/2016 | 2/24/2016 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 2/15/2016 | 2/15/2016 | 2/16/2016 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 1/14/2016 | 1/14/2016 | 1/14/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 12/14/2015 | 12/14/2015 | 12/14/2015 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/10/2015 | 11/12/2015 | 11/12/2015 | A | PART |
Andy J. Long
|
|
|
Significant trackout occuring on Brundage Ave due to active landscaping. Muddy conditions are making it difficult. Hayden Homes and Eaglewood Homes will have developer order street sweeper.
No spills or areas of sediment runoff from open parcels observed.
Employees parking on paved surfaces, all storm drain inlets have sediment bags installed, and a designated lined washout is being utilized and has remaining capacity. Soon road/sidewalk medians will be landscaped stabilized so trackout will be less of problem. Trash and materials are contained at sites.
|
General Inspection | 11/9/2015 | 11/9/2015 | 11/10/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled for Thursday 11/12
|
Random Inspection | 10/9/2015 | 10/9/2015 | 10/9/2015 | P | PASS |
Andy J. Long
|
|
|
WIP on SFHs by Hayden Homes and Eagleridge in Sunnyridge phase 3. Streets appear to have been swept recently, new lined washout pit is installed and marked. DI bags installed. No windblown trash or fugitive dust issues occuring at time of inspection. Landscaping and irrigation line installation between roads and sidewalk is occuring, so some loose topsoil and dirt should be swept upon completion.
No corrections at this time..
|
General Inspection | 9/28/2015 | 9/28/2015 | 9/28/2015 | | PASS |
Eric Strole
|
|
|
|
General Inspection | 8/27/2015 | 8/28/2015 | 8/28/2015 | A | PART |
Andy J. Long
|
|
|
WIP on SFHs by Hayden Homes and Eaglewood Homes in new Sunnyridge phase. Approximately 15 homes being built simultaneously. Trash and materials are contained, some minor trackout and loose sediment on driveways and in front of homes. No discharges or spills observed around sites. Concrete washout pit was utilized for foundations.
Corrections:
1. Street sweeper should be scheduled every other week. 2. Install new washout for next round of homes. Remove old washout material and recycle/dispose properly.
|
General Inspection | 8/27/2015 | 8/27/2015 | 8/27/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled
|
General Inspection | 7/27/2015 | 7/27/2015 | 7/27/2015 | | PASS |
Andy J. Long
|
|
|
New washout for SFHs in phase was installed at west end of Bear Ridge as requested and utilized. Near 75% capacity and needs to be replaced this week.
No trackout or discharges. Old washout that was being used was cleaned/removed. Approved.
|
Random Inspection | 6/24/2015 | 6/24/2015 | 6/24/2015 | P | PASS |
Andy J. Long
|
|
|
ACHD onsite chip sealing and fence crews working. DI bags already installed on new stormdrains. Lots pre-graded for SFH construction which has not yet started. No fugitive dust issues.
|
General Inspection | 6/12/2015 | 6/12/2015 | 6/12/2015 | | PASS |
Evan Jenkins
|
|
|
|
Random Inspection | 5/12/2015 | 5/12/2015 | 5/12/2015 | P | PASS |
Andy J. Long
|
|
|
Streets, gutters and sidewalks are installed. DI sediment bags have been installed on all new storm drains.
Permit and NOI information is posted. Approved. Parcels have been graded and preped for SFH. Currently no dust or issued, but may need tacifier on lots that will not be built this season.
|
General Inspection | 4/13/2015 | 4/13/2015 | 4/13/2015 | | PART |
Andy J. Long
|
|
|
WIP on parcel grading for new Sunnyridge phase. Curbing has been installed and roads will be this week or next. Permit is posted, no trackout to Snowbird or Columbia. No fugitive dust at time of inspection or complaints received by ESC division. Ground FX is now conducting SWPPP inspections for Knife River
Need to sweep up loose sediment at entrances and gutter on Snow Bird this week.
|
General Inspection | 3/12/2015 | 3/12/2015 | 3/12/2015 | | PASS |
Andy J. Long
|
|
|
Work has resumed on new phase of Sunnyridge after winter shutdown. No fugitive dust issues, working on widening Columbia and installing curb & sidewalk so there is some loose dirt on parts of roadway. No stormwater features or surface water receive runoff from this area. Inlets along Bogus Ridge have sediment protection.
No corrections at this time
|
General Inspection | 2/9/2015 | 2/9/2015 | 2/9/2015 | | PASS |
Andy J. Long
|
|
|
Sunnyridge phase is currently shut down for winter. No offsite discharges, sediment runoff, or trackout observed.
No immediate corrective actions needed at this time, but once site dries out and work resumes perimeter BMPs, construction entrance(s), and DI bags along Snowbird should be maintained.
|
Random Inspection | 1/8/2015 | 1/8/2015 | 1/8/2015 | P | PASS |
Andy J. Long
|
|
|
New SunnyRidge phase is currently shut down for winter. No runoff from site, water is ponding and infiltrating in various areas. Entrances are blocked to prevent trespassing/track out. No corrections at this time.
|
General Inspection | 12/25/2014 | 12/25/2014 | 12/26/2014 | | CANC |
Andy J. Long
|
|
|
|
Tracking Control | 11/24/2014 | 11/24/2014 | 11/24/2014 | P | PEND |
Andy J. Long
|
|
|
Called RP and left VM to restrict access to work area at one designated entrance to cut down on trackout. Will continue to monitor
|
General Inspection | 11/13/2014 | 11/13/2014 | 11/14/2014 | | CANC |
Evan Jenkins
|
|
|
due to dangerious snow conditions/road ways, unable to make it to the inspection
|
General Inspection | 10/10/2014 | 10/13/2014 | 10/13/2014 | A | PASS |
Andy J. Long
|
|
|
In process of installing sewer and utilities at new phase of Sunnyridge. No trackout to Snow Bird or Columbia. No dust observed. Permit posted. Approved.
|
General Inspection | 10/10/2014 | 10/10/2014 | 10/10/2014 | | CANC |
Andy J. Long
|
|
|
rescheduled for Monday 10/13
|
General Inspection | 9/9/2014 | 9/9/2014 | 9/9/2014 | | PART |
Andy J. Long
|
|
|
No trackout or sediment runoff. Using large trench machine to dig into lava bedrock.
Need to provide water truck to keep down dust during the trenching/rock grinding operation.
|
General Inspection | 8/7/2014 | 8/7/2014 | 8/7/2014 | | PASS |
Evan Jenkins
|
|
|
no issues
|
Random Inspection | 7/7/2014 | 7/7/2014 | 7/7/2014 | P | PASS |
Andy J. Long
|
|
|
New Sunnyridge phase is in progress. No trackout or dust issues at time of inspection and minimal activity. Permit and SWPPP are on site and BMPs are installed. No corrections at this time.
Note: Eaglewood Homes RP informed me that a street sweeper will be coming this week for the existing Sunnyridge phases (per developer Brad M.)
|
Random Inspection | 6/17/2014 | 6/17/2014 | 6/17/2014 | A | PASS |
Andy J. Long
|
|
|
Permit posted and BMPs installed for Sunny Ridge #3. No trackout to Snow Bird or Columbia Rd. No dust issues observed at time of inspection and no citizen complaints at this time.
|
Site Preparation | 6/3/2014 | 6/3/2014 | 6/3/2014 | P | PASS |
Andy J. Long
|
|
|
Permit was retrieved by Knife River after initial miscommunication between contractors/developers/City. The BMPs were installed, no violation, the permit paid for but was not physically picked up. RP Randy and project manager Jeff Corsen got the permit as I requested last week upon discovery of the work occuring.
Permit is now issued and posted at site. Wattles protect the stormwater retention pond area. Water truck actively doing rounds all over site to keep down dust. SWPPP on site. Approved.
|
General Inspection | 9/7/2017 | 9/7/2017 | | | |
Andy J. Long
|
|
|
|