Site Final | 4/20/2020 | 4/21/2020 | 4/21/2020 | P | PASS |
Andy J. Long
|
|
|
Homes now in progress and permitted seperately. Blackrock will remove DI bags at end of construction of townhomes
No ESC corrections. Adjacent subdivision phases have their own permits, see ESC19-00584.
This permit finaled.
|
General Inspection | 4/20/2020 | 4/20/2020 | 4/20/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Michael Zawacki
|
|
|
All foundations, roads, sidewalks and curbing completed. No framing in site, all work is on perimeter homes and 4-plexes. No trash blown into creek, site is clean.
|
General Inspection | 1/28/2020 | 1/28/2020 | 1/29/2020 | | PASS |
Michael Zawacki
|
|
|
WIP on multiple 4-plexes. Site is being kept clean, no wind blown trash or tracking.
|
General Inspection | 12/13/2019 | 12/13/2019 | 12/13/2019 | P | PASS |
Michael Zawacki
|
|
|
All foundations poured. Site is clean. Building work is going from west to east.
|
General Inspection | 11/1/2019 | 11/1/2019 | 11/4/2019 | | PASS |
Michael Zawacki
|
|
|
WIP on both framing and foundations. Lined concrete washout on site and in use. Trash contractor on site clearing trash boxes. Site is clean in regards to trash. Lots of dirt tracked inside site, none leaving. Silt fence/ trash fence protecting creek.
|
General Inspection | 9/16/2019 | 9/16/2019 | 9/17/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/30/2019 | 7/30/2019 | 7/31/2019 | | PASS |
Michael Zawacki
|
|
|
Inlet protection has been installed on hopewell. Lumber has been deliverd and trash boxes built, no framing activity. Grader is working on pad for new foundation, site still has washout.
|
General Inspection | 6/14/2019 | 6/14/2019 | 6/17/2019 | | PASS |
Michael Zawacki
|
|
|
Foundations installed washout on site. Split rail fence installed, wind/trash fence not installed, no framing yet. Pile of backfill along creek on southside is being removed.
|
General Inspection | 4/29/2019 | 4/29/2019 | 4/30/2019 | | PART |
Michael Zawacki
|
|
|
Inlet protection needed inside Hopes Way alleys. Currently large buffer between work area and creek, creek is vegatated and has wattle along top. Workers are placing backfill in first batch of foundations. Sent message to RP to install drain inlet protection.
|
General Inspection | 3/12/2019 | 3/12/2019 | 3/19/2019 | | PEND |
Andy J. Long
|
|
|
Perimeter controls at east end of development are installed. Grass is begninning to grow on slope near Warm Springs Creek.
Lots of wind blown trash. Need to work with Blackrock and Harris Ranch HOAs to get regular trash pick up in Warm Springs Creek.
|
General Inspection | 1/25/2019 | 1/25/2019 | 1/25/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity. All site prep is done.
|
General Inspection | 12/5/2018 | 12/5/2018 | 12/7/2018 | | PASS |
Michael Zawacki
|
|
|
Site prep work complete, no new home activity.
|
General Inspection | 10/9/2018 | 10/11/2018 | 10/12/2018 | P | PEND |
Andy J. Long
|
|
|
follow up on wattles and trash in DHETH #8 / Parkcenter Blvd
|
General Inspection | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | PART |
Andy J. Long
|
|
|
Wattles installed at east of DHETH No 8 at Warm Springs, but are not staked or overlapping. Lots of trash in creek where project occured.
Correction to RP & Knife River to pick up trash and re-install wattle properly.
|
General Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on foundations and some framing. Trash contained. Storm drains fitted with DI bags, lined concrete washout is onsite.
|
General Inspection | 8/14/2018 | 8/14/2018 | 8/14/2018 | P | PASS |
Michael Zawacki
|
|
|
Grading is complete, water and sewer lines installed. Park Center now has sidewalks and curbing, being prepped for paving. Landscapers on site installing sprinklers for right of way landscaping.
|
General Inspection | 6/14/2018 | 6/14/2018 | 6/14/2018 | P | PASS |
Michael Zawacki
|
|
|
Bringing in fill material and grading. Old creek channel has been filled. Water truck on site, no dust.
|
General Inspection | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PASS |
Michael Zawacki
|
|
|
Starting to remove vegetation and prep area to fill old creek channel. Water truck on site, no dust leaving site.
|
General Inspection | 5/21/2018 | 5/21/2018 | 5/21/2018 | P | PASS |
Andy J. Long
|
|
|
check on dewatering and creek opening..
WIP. Channel work occuring at south connection point @ Warm Springs bypass. Old channel has not yet been filled.
No discharges, trackout, or fugitive dust from site. Permits posted, construciton entrances installed.
|
General Inspection | 5/8/2018 | 5/22/2018 | 5/21/2018 | A | PASS |
Andy J. Long
|
|
|
Channel realignment is in process of being opened up. Knife River working on project. Lining connection areas with geotextile and rip rap. Groundwater in channel is being pumped to the adjacent pasture to the west. No turbid discharges in construction areas. Knife River active on grading & fill for DHETH 6-7 and DHE #17 and 404 permits to fill in old channel have been approved and will occur this week and next.
When channel by Warm Springs bybass is opened, plan is to capture sediment laden water from first flush in basin south of road and north of Greenbelt and discharge w/ 2 " pump to the vegetated area west of the creek. Will follow up.
|
Random Inspection | 5/18/2018 | 5/18/2018 | 5/18/2018 | P | PASS |
Michael Zawacki
|
|
|
WIP on grading. Old warm springs creek is protected by siltfence. Channel has been cut diverting creek into new creek bed, no work on filling old creek has begun.
|
Site Preparation | 5/8/2018 | 5/8/2018 | 5/8/2018 | P | PASS |
Andy J. Long
|
|
|
pre-con meeting DHE townhomes # 7
Knife River is contractor (Rex ###-####), Riverridge engineering project design.
construction entrance on east end of project. Will protect Warm Springs creek channel with silt fence until 404 permit approval to fill the channel as planned.
Standard BMPs required: dust control, trackout prevention and sweeping, concrete washout facility, staging area with safe storage or materials and chemicals on site.
Requested that silt fence crew also pick up loose trash encountered in the area.
|