BLD-Final | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
Charles Phone #: ###-####
|
FIRE-Final Inspection | 7/20/2018 | 7/23/2018 | 7/23/2018 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the project related fire alarm permit is finaled.
Barry Phone #: ###-####
|
BLD-Final | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | PEND |
Mike Jordan
|
|
|
Phase 3 will be ok as soon as fire/life/safety has signed off.
|
BLD-Final | 7/20/2018 | 7/23/2018 | 7/20/2018 | A | CANC |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
FIRE-Final Inspection | 7/19/2018 | 7/20/2018 | 7/20/2018 | A | FAIL |
Troy Cobbley
|
|
|
Need project related fire alarm permit finaled and an exit sign added in new corridor.
Barry Phone #: ###-####
|
BLD-Conference | 7/20/2018 | 7/20/2018 | 7/20/2018 | P | CANC |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/13/2018 | 7/13/2018 | 7/13/2018 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. phase 3 above ceiling and ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 7/10/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####. Break room, equipment room and sub sterile passage coridor ok.
|
BLD-Ceiling Grid Inspection | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ceiling grid and fire stopping above grid at mens and womens loker rooms, new phamacy rooms and two closets next to pharmacy.
|
BLD-Framing/Rough-in | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####. fire proofing has been patched on tube steel columns. !hr. assembly above grid complete. Aslo inspected shaft board liner on interior side of 1hr. wall in anesthesia work room.
|
BLD-Framing/Rough-in | 6/13/2018 | 6/14/2018 | 6/14/2018 | A | PART |
Mike Jordan
|
|
|
Berry Phone #: ###-####. Interior steel stud framed walls for new pre op bed aditions. Needs to hand patch fire proofing back on tube stell columns and complete 1hr. fire wall envelope aboce grid.
|
BLD-Framing/Rough-in | 5/24/2018 | 5/24/2018 | 5/24/2018 | P | PASS |
Mike Jordan
|
|
|
Max Phone #: ###-####. Prerock on 1hr. wall at anesthesia work room behind bump out wall on patient side.
|
BLD-Framing/Rough-in | 5/18/2018 | 5/21/2018 | 5/21/2018 | A | PART |
Mike Jordan
|
|
|
Barry Phone #: ###-####. Inteior steel stud framed walls for anesthesia work room.
|
BLD-Framing/Rough-in | 5/9/2018 | 5/9/2018 | 5/10/2018 | P | CANC |
Mike Jordan
|
|
|
Barry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/9/2018 | 5/10/2018 | 5/10/2018 | A | PASS |
Mike Jordan
|
|
|
Barry Phone #: ###-####. INterior steel stud framed walls for pharmacy, breakroom, New O.R. and substerilr rooms ok.
|
BLD-Final | 4/17/2018 | 4/18/2018 | 4/18/2018 | P | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Vending room 118 only ok to occupy..
|
FIRE-Final Inspection | 4/17/2018 | 4/18/2018 | 4/18/2018 | A | PART |
Troy Cobbley
|
|
|
Vending Room 118 life safety is passed. Will need an additional notification device before project final due to the office being utilized by more than one person.
Charles Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/13/2018 | 4/16/2018 | 4/16/2018 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Room #119.
|
BLD-Final | 4/2/2018 | 4/2/2018 | 4/3/2018 | P | PART |
Mike Jordan
|
|
|
Barry Phone #: ###-####. Purchasing room 119 only ok to occupy.
|
BLD-Ceiling Grid Inspection | 3/27/2018 | 3/28/2018 | 3/28/2018 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|
BLD-Final | 3/13/2018 | 3/14/2018 | 3/14/2018 | A | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ok to occupy new addition. Verified all trades.
|
FIRE-Final Inspection | 3/13/2018 | 3/14/2018 | 3/14/2018 | A | PART |
Troy Cobbley
|
|
|
Life safety for Passage 115 will be passed when ceiling tile has been installed.
Charles Phone #: ###-####
|
FIRE-Final Inspection | 3/12/2018 | 3/13/2018 | 3/13/2018 | A | PART |
Troy Cobbley
|
|
|
Life safety in new addition passed. Passage 115 was not complete yet.
Charles Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 2/13/2018 | 2/14/2018 | 2/14/2018 | P | PART |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Addition portion.
|
BLD-Framing/Rough-in | 2/1/2018 | 2/1/2018 | 2/1/2018 | P | PASS |
Mike Jordan
|
|
|
Blow patches on existing exterior wall at passage #115 behind furred wall.
|
BLD-Framing/Rough-in | 1/31/2018 | 2/1/2018 | 2/1/2018 | A | NR |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Moved to pm. inspection.
|
BLD-Framing/Rough-in | 1/30/2018 | 1/31/2018 | 1/31/2018 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. interior steel stud framed walls at rooms 117,118,119, 146 and 147. Furred walls on passage 115.
|
BLD-Energy code compliance | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/21/2017 | 12/21/2017 | 12/21/2017 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-#### Remainder of framing in addition ok.
|
BLD-Final | 12/13/2017 | 12/13/2017 | 12/13/2017 | P | CANC |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|
BLD-Final | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | PART |
Mike Jordan
|
|
|
Ok to occupy M.O.B building south of gridline N6.5 and corridor149 and 156 ( link from existing hospital to M.O.B.) only.
|
FIRE-Final Inspection | 12/12/2017 | 12/13/2017 | 12/13/2017 | A | PART |
Troy Cobbley
|
|
|
Life safety for the MOB portion of the project is passed. The connecting corridor from the new MOB to the existing hospital is ok on life safety as well.
Charles Phone #: ###-####
|
BLD-Final | 12/7/2017 | 12/12/2017 | 12/12/2017 | P | CANC |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|
FIRE-Final Inspection | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | FAIL |
Troy Cobbley
|
|
|
Life safety in the MOB tenant improvement will be ok to pass when the sprinkler system in the connecting corridor between the MOB and the existing hospitol has been activated..
|
BLD-Ceiling Grid Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 | P | PART |
Mike Jordan
|
|
|
Charles-above ceiling Phone #: ###-####. Corridor only between existing hospital and new cafeteria. Needs to complete fire stopping at #hr. wall and 1hr. wall above grid.
|
BLD-Ceiling Grid Inspection | 12/5/2017 | 12/6/2017 | 12/6/2017 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ceiling grid at main corridor between b occupancy and 3hr. fire wall ok. Also did courtesey walk through on B occupancy portion of building.
|
BLD-Final | 11/22/2017 | 11/27/2017 | 11/27/2017 | A | PART |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Ok to occupy rooms 111 and 112 only next to pharmacy. Verified all other trades sign offs.
|
FIRE-Final Inspection | 11/22/2017 | 11/27/2017 | 11/27/2017 | A | PART |
Troy Cobbley
|
|
|
Life safety is passed in the two new Pharmacy Rooms in the existing hospital area. Fire alarm and fire sprinkler work is complete.
Charles Phone #: ###-####
|
FIRE-Final Inspection | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | FAIL |
Troy Cobbley
|
|
|
Todays inspection was for the Pharmacy Room. Life safety will be ok in this room when the fier alarm devices have been tested.
Charles Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/14/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. All grid south of corridor 198 in the B occupancy portion of building.
|
BLD-Framing/Rough-in | 11/14/2017 | 11/15/2017 | 11/15/2017 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior steel stud framed walls at rooms 151/150/152/148 and corridors 149 and 156.
|
BLD-Energy code compliance | 11/8/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Mike Jordan
|
|
|
East and south walls of new building ok.
|
BLD-Energy code compliance | 11/7/2017 | 11/8/2017 | 11/8/2017 | A | NR |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Inspection moved to today in the pm.
|
BLD-Framing/Rough-in | 11/6/2017 | 11/7/2017 | 11/7/2017 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Soffit framing in new dinning room. Interior steel stud framed walls fro new cooridor from ramp at new dinning room to existing dinning room.
|
BLD-Framing/Rough-in | 11/1/2017 | 11/2/2017 | 11/2/2017 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior steel stud framed wals in east/west corridor, 3hr. fire wall and soffit in new cafetria. Noted will need engineering showing that bottom chord of roof trusses will support new soffit.
|
BLD-Framing/Rough-in | 10/19/2017 | 10/19/2017 | 10/19/2017 | P | CANC |
Mike Jordan
|
|
|
Completed inspection in the a.m.
|
BLD-Framing/Rough-in | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Exterkior curtain walls ok
|
BLD-Final | 10/5/2017 | 10/6/2017 | 10/6/2017 | P | PART |
Mike Jordan
|
|
|
late as possible // Charles Miller Phone #: ###-####. Ok to occupy O.R. #141 only. Noted all other trades signed off.
|
FIRE-Final Inspection | 10/5/2017 | 10/6/2017 | 10/5/2017 | P | PART |
Troy Cobbley
|
|
|
O.R. 141 life safety is passed. Sprinkler and alarm work is complete
Charles Miller Phone #: ###-####
|
BLD-Final | 10/4/2017 | 10/5/2017 | 10/5/2017 | P | CANC |
Mike Jordan
|
|
|
Charlies Phone #: ###-#### cancel per Cindy with The Robins & Morton Group
|
FIRE-Final Inspection | 10/4/2017 | 10/5/2017 | 10/5/2017 | A | CANC |
Troy Cobbley
|
|
|
Charlies Phone #: ###-#### cancel per Cindy with The Robins & Morton Group
|
BLD-Framing/Rough-in | 9/22/2017 | 9/25/2017 | 9/25/2017 | A | PASS |
Jim Storey
|
|
|
Charlies Phone #: ###-#### noted on plan set sheer wall/ hard ceilling/ two locations
|
BLD-Framing/Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 | P | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior steel stud framed walls , remainderof framing west of engineering room and south of corridor.
|
BLD-Framing/Rough-in | 9/8/2017 | 9/11/2017 | 9/12/2017 | A | PART |
Dave Hannah
|
|
|
Charles Phone #: ###-#### fire caulking inter shaft wall ok to cover ext
|
BLD-Ceiling Grid Inspection | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Hardlid ok in OR 141.
|
BLD-Framing/Rough-in | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PASS |
Mike Jordan
|
|
|
Charles Phone #: ###-####. Interior stel stud framed walls for hood room and anti room. OR #141 and corridor at sterile passage#126. Corridor wallsat corridor 199, and all walls to the east of corridor 199.Also purchaseing office 215 and office 214. All areas marked on approved plans.
|