BLD-Final | 7/30/2020 | 7/30/2020 | 7/31/2020 | P | PART |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Blackburn//temp occ ok in all units except type A unit until grab bars are installed//fire tape area in fire riser room// all other signatures have been completed for temp occ//discussed handrails and code requirements, they will be fixed//
|
FIRE-Final Inspection | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PART |
Troy Cobbley
|
|
|
A temp for life safety is being given until the permanant address is installed and the heater is installed in the third roof access rooms.
F/L/S final. Smokes added Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Final | 7/28/2020 | 7/29/2020 | 7/29/2020 | P | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Blackburn//need all signatures, walked 1 and 2 floors, need to finish rooms, typa A room not complete, still need to walk 3rd floor//
|
FIRE-Final Inspection | 7/28/2020 | 7/29/2020 | 7/29/2020 | A | FAIL |
Troy Cobbley
|
|
|
Today turn into a conference. It appears that a smoke alarm was deleted in the three bedroom units which is actually required to be installed. Inspection was stopped and we conferenced about it.
Fire Life Safety inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
FIRE-Conference | 7/17/2020 | 7/20/2020 | 7/20/2020 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements to begin the building sign offs. The biggerst issue is the need to submit to Joe Bruce temp fire dept access plans for approval.
Phone #: ###-#### Inspection requested via web by Lee Scott
|
BLD-Wall Bracing | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Tell Riley
|
|
|
INspection for additional floor to floor straps and hold downs add afterwards Phone #: ###-#### Inspection requested via web by Travis Blackburn//added hold downs and floor to floor strapping--ok//
|
BLD-Wall cover | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | CANC |
Mike Jordan
|
|
|
Drop ceiling on 1st floor for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn. 1st and 2nd. floor drops ok.
|
BLD-Wall Bracing | 5/7/2020 | 5/8/2020 | 5/8/2020 | A | CANC |
Mike Jordan
|
|
|
Check interior gyp shear at all floors. Call Jeremy Smith ###-#### Phone #: ###-#### Inspection requested via web by Travis Blackburn. 1st, 2nd and 3rd floor interior shear ok.
|
BLD-Wall cover | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PART |
Tell Riley
|
|
|
Inspect 2nd floor drop ceilings Phone #: ###-#### Inspection requested via web by Travis Blackburn//2nd floor ok to cover when minor corrections, insulation added//
|
BLD-Wall cover | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | PART |
Tell Riley
|
|
|
If time allows, cover inspection for drop ceilings on 3rd floor. Phone #: ###-#### Inspection requested via web by Travis Blackburn//Plumbing rough in has passed, other rough ins ok//drops on 3rd floor ok when areas around mechanical on exterior walls have been insulated//
|
BLD-Wall cover | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | NR |
Tell Riley
|
|
|
Drop ceiling inspection for cover on 3rd floor and 2nd if time permits Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to have plumbing inspections passed prior to inspection///
|
BLD-Framing/Rough-in | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PEND |
Tell Riley
|
|
|
Corridor reinspect for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//corridor corrections made//Fire sprinkler inspection failed, need to have approval for fire sprinklers prior to any cover//
|
BLD-Framing/Rough-in | 4/28/2020 | 4/29/2020 | 4/29/2020 | A | NR |
Tell Riley
|
|
|
Corridor inspection to be able to hang lids Phone #: ###-#### Inspection requested via web by Travis Blackburn//walkthrough on corridor framing--minor framing corrections, nails hangers, fire caulking, add lags as discussed//address stair stringer attachment as it differs from plan details///
|
BLD-Wall cover | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | CANC |
Tell Riley
|
|
|
This is a cover inspection for drop ceilings in 3rd floor only! Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to have plumbing letter approved prior to any inspection on this permit//
|
BLD-Conference | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | DONE |
Tell Riley
|
|
|
conference with Matt, plumbing inspector, and Travis, discussed the need for the architect/engineer to sign off on plumbing as is prior to any other inspections//discussed the need for revised plumbing drawings for other buildings prior to plumbing inspection approval and or any cover//
|
BLD-Wall cover | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | NR |
Tell Riley
|
|
|
Inspection for cover at 2 hr ceilings in stairwells Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to fix a couple areas on shaft liner//
|
BLD-Wall cover | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PART |
Tell Riley
|
|
|
1st floor cover inspection on units only. Phone #: ###-#### Inspection requested via web by Travis Blackburn//1st floor ok to cover--energy ok//
|
BLD-Framing/Rough-in | 3/6/2020 | 3/9/2020 | 3/9/2020 | A | PART |
Tell Riley
|
|
|
Second reinspection for 1st floor of bldg B Phone #: ###-#### Inspection requested via web by Travis Blackburn//1st floor framing corrections made//call for energy//
|
BLD-Framing/Rough-in | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PART |
Tell Riley
|
|
|
Reinspection on first floor around 10 am would be preferred Phone #: ###-#### Inspection requested via web by Travis Blackburn//211 and 311 ok//others not ready corrections not made//rock wool at floor needs to be full depth//
|
BLD-Framing/Rough-in | 3/4/2020 | 3/5/2020 | 3/5/2020 | P | PART |
Tell Riley
|
|
|
Inspection for insulation on 1st floor needed. Nobody will be able to walk from 12-2. After 2 would be preferred. I would also like to inspect shaftliner assembly at top of stairways for cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//1st floor only//some framig corrections, fire caulking, and anchors bolts needed//still need fire blocking on separation walls//will call in for inspection of above//
|
BLD-Wall cover | 3/2/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Dave Hannah
|
|
|
2nd floor cover only except for the corridor and unit 211 Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 2/24/2020 | 2/26/2020 | 2/26/2020 | A | PART |
Tell Riley
|
|
|
INspection for 2nd floor approval to insulate walls and joists Phone #: ###-#### Inspection requested via web by Travis Blackburn//a couple joists need addressed//wrong hangers used for wide flange joists//will need to change and verify at insualtion inspection//ok to insulate only//
|
BLD-Framing/Rough-in | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PART |
Tell Riley
|
|
|
2nd floor inspection to allow insulation Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok// need to provide fix for the cut joists for plumbing//
|
BLD-Energy code compliance | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PART |
Tell Riley
|
|
|
3rd floor cover inspection again for units only after visqueen on the ceiling was installed except for unit 312 Phone #: ###-#### Inspection requested via web by Travis Blackburn//VB isntalled and secure to underside of ceiling//
|
BLD-Energy code compliance | 2/10/2020 | 2/11/2020 | 2/12/2020 | A | PART |
Tell Riley
|
|
|
Insulation approval for cover on 3rd floor only at units Phone #: ###-#### Inspection requested via web by Travis Blackburn//framing corrections made on third floor//insulation for unit fire separation ok per architect//third floor ok//
|
BLD-Framing/Rough-in | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | PART |
Tell Riley
|
|
|
Looking for a framing inspection to insulate walls on 3rd floor only Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate 3rd floor only if plumbing is approved// finsish fire caulk penetrations// fix fire collars//add headers as noted//
|
BLD-Framing/Rough-in | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | NR |
Tell Riley
|
|
|
Verify truss fixes and other misc. pre cover inspection items Phone #: ###-#### Inspection requested via web by Travis Blackburn//see truss engineering for fixes//
|
BLD-Other | 1/30/2020 | 1/30/2020 | 1/30/2020 | P | NR |
Jim Storey
|
|
|
Exteror 2hr sheetrock on stair walls first layer inspection and conference on assemblies for ga file wp 4136 and UL des U344 Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | PART |
Tell Riley
|
|
|
3rd floor inspection of trusses/hardware to start the process of inspections for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add nails to hangers, fix hangers where noted are wrong, add studs at girder and uplift brackets//bracing ok//trusses only//
|
BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/23/2020 | P | CANC |
Tell Riley
|
|
|
3rd floor inspection of trusses/hardware to start the process of inspections for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 1/10/2020 | 1/10/2020 | 1/10/2020 | P | PART |
Tell Riley
|
|
|
pre rock areas on 1st and 2nd floors//ok to rock areas to install shower/tubs//
|
BLD-Framing/Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | NR |
Tell Riley
|
|
|
Framing inspection at prerock areas behind tubs on 1st and 2nd floors and for cover at top of stairways and exterior balconies Phone #: ###-#### Inspection requested via web by Travis Blackburn//inspection request was used as a conference to discuss ceiling, wall rating for 2 HR corridor areas and fireblocking at pre-rock areas for tubs and showers//
|
BLD-Wall Bracing | 1/3/2020 | 1/6/2020 | 1/6/2020 | A | PART |
Tell Riley
|
|
|
Verify hardware at 1st floor sufficient per RFI Phone #: ###-#### Inspection requested via web by Travis Blackburn//hold downs ok other than those marked-one missing nut-one missing completely//
|
BLD-Wall Bracing | 12/18/2019 | 12/19/2019 | 12/19/2019 | A | FAIL |
Tell Riley
|
|
|
Holddown hardware inspection is the last of the shear inspection. Look for Matt to guide the inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//not all hold downs are correct//address incorrect hold downs and call for re-inspection//
|
BLD-Wall Bracing | 12/10/2019 | 12/11/2019 | 12/11/2019 | P | PART |
Tell Riley
|
|
|
This is for the hardware portion of shear. All wall panels were previously inspected. Phone #: ###-#### Inspection requested via web by Travis Blackburn//exterior nailing and straping ok per plans//still need to check interior hold downs//
|
BLD-Other | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PART |
Tell Riley
|
|
|
This is for a reinspect for cover at portions of party walls that are behind plumbing walls. Phone #: ###-#### Inspection requested via web by Travis Blackburn//3rd floor ok//1st and 2nd floor not ready//
|
BLD-Concrete | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PART |
Tell Riley
|
|
|
We are pouring the patios on building B tomorrow at 10am... Also included will be the last garbage enclosure, pier pads for building J, and piers for building H. Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//
|
BLD-Wall Bracing | 12/4/2019 | 12/5/2019 | 12/5/2019 | A | PART |
Tell Riley
|
|
|
This is for a partial shear inspection, as much as time will allow. Phone #: ###-#### Inspection requested via web by Travis Blackburn//verify and use approved fasteners in pressure treated plates//add nails in areas marked during walk thorugh//nailing inspection no hardware inspected//
|
BLD-Other | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | FAIL |
Tell Riley
|
|
|
This inspection is for prerock areas behind tubs at party walls and exterior walls prior to setting tub/shower enclosures. Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to remove insulation at exterior wall fur outs to drywall per details //call for re - inspection//
|
BLD-Wall Bracing | 10/15/2019 | 10/15/2019 | 10/15/2019 | P | PART |
Tell Riley
|
|
|
This is for 1st floor shear nailing only. Hardware excluded (hold downs). Phone #: ###-#### Inspection requested via web by Travis Blackburn//1st floor shear nailing ok//
|
BLD-Concrete | 9/25/2019 | 9/26/2019 | 9/26/2019 | P | PASS |
Tell Riley
|
|
|
Pouring slab at 4am on Friday. We need the latest possible inspection in the afternoon as we will be working late prepping for the pour. Phone #: ###-#### Inspection requested via web by Travis Blackburn//vapor barirer ok//rebar ok//ok pending specials//
|
BLD-Foundation | 9/5/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Tell Riley
|
|
|
This is the second portion of bldg B foundation walls. This will pour directly after the clubhouse footings (also scheduled) Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to pour pending special inspetions//
|
BLD-Foundation | 9/3/2019 | 9/4/2019 | 9/4/2019 | A | PART |
Tell Riley
|
|
|
This will be for the first of two pours on the foundation walls. Geotek will be doing our special inspection as well. Pour time is 1:00pm. Phone #: ###-#### Inspection requested via web by Travis Blackburn//first portion of building B// ok to pour pendings specials//
|
BLD-Footing | 8/26/2019 | 8/27/2019 | 8/27/2019 | A | PASS |
Tell Riley
|
|
|
Concrete pour is scheduled for 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//footing and rebar per plans//ok pending specials//
|