Information based on query as of Friday, May 10, 2024.
Permit Information
Permit NumberESC16-00242
StatusFinaled
Name BRIAN TERRY
Site Address 8000 S FEDERAL WAY
Project NameMicron Fab 51 - CUP
Customer NumberC24074
ePlanReviewNo
Description
Permit covers Fab 51, CUP facility construction activity. Includes staging and material storage areas, waste managment & lined washout. Site stormwater contained within Micron stormwater ponds. Trackout controls and inlet protection installed within site, fugitive dust control measures, and vegetative buffer controls along 5 mile creek along the southeast border of complex.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final9/16/20199/17/20199/17/2019APASS
DetailsAndy J. Long
Dillon Phone #: ###-####

Fab 51 scope of work complete per Stock Construction. Will continue to work with Micron Environmental Division on the remaining active project and construction staging/pollution prevention areas.
General Inspection7/24/20198/6/20198/7/2019ACANC
DetailsAndy J. Long
9 AM Micron Campus inspection

see site final
Site Final8/7/20198/7/20198/7/2019PPASS
DetailsAndy J. Long
9 AM Micron Campus inspection - seperate report compiled.

This project is complete, no ESC requests.
General Inspection6/28/20196/28/20196/28/2019 CANC
DetailsAndy J. Long
General Inspection5/13/20195/13/20195/14/2019 PEND
DetailsAndy J. Long
RP to schedule site final walk through
General Inspection3/26/20193/26/20193/28/2019 CANC
DetailsAndy J. Long
General Inspection2/8/20192/8/20192/8/2019 DEFR
DetailsMichael Zawacki
Will schedule spring walk through with Micron
General Inspection12/24/201812/24/201812/24/2018PDONE
DetailsAndy J. Long
change RP to Brian Terry
General Inspection11/19/201811/19/201811/20/2018 PASS
DetailsMichael Zawacki
Did quick site survey. All areas clean, BMPs in place. No noted ESC issues. WIll schedule inspection for campus in spring.
General Inspection10/2/201810/4/201810/4/2018APASS
DetailsAndy J. Long
9 AM wth Brian Terry and Susan Beesley, Micron environmental compliance division. Inspection conducted by ESC Inspectors Long and Zawacki

Micron SWPPP inspection of all construction projects with earth disturbance and use of staging and laydown areas. The CUP, Nitrogen plant, and B37 are under construction. B37 parking lots should be paved before end of month. Interior work is still occuring on Fab 51. Pathway is in progress around perimeter of site. Parking lot expansion at the MASK building on Columbia.

SWPPP inspections are conducted weekly by Micron stormwater team as well as contractors (Air Products, ESI, Stock, Warner) . SWPPP binders, site maps, and inspection reports were available for review and are well organized and complete.

Light rain and wind at time of inspection.

BMPs installed:
- construction trackout control with rock and rumble bars for both access points (B37 and laydown/employee parking)
- parking and laydown area access route has certain areas with rock and geotextile berms to prevent runoff from leaving the construction area into Micron employee parking.
- storm drain inlet protection on all receiving inlets. Stormwater is retained onsite at Micron.
- lined concrete washouts
- large covered dumpsters
- containers for material and equipment storage prevent exposure to rain
- spill kits located in various locations around site.
- water trucks onsite to keep down dust.

No violations observed. Site is clean, BMPs are installed correctly, site is inpsected regularly. No correction requests at this time, Micron projects are currently in compliance.
General Inspection10/1/201810/1/201810/1/2018 CANC
DetailsAndy J. Long
Walk through of all ESC permits at Micron to be conducted this month.
General Inspection8/10/20188/15/20188/15/2018ADEFR
DetailsMichael Zawacki
Will schedule walk through with Micron team.
General Inspection8/10/20188/10/20188/10/2018 CANC
DetailsAndy J. Long
General Inspection6/25/20186/25/20186/25/2018 PASS
DetailsAndy J. Long
Perimeter inspeciton.

No fugitive dust observed at time of inspection, construction access within Micron campus is clean and free of trackout. South storm water pond is filled, no offsite discharge.

Lined berm around construction staging area and parking is installed. No disharges to Micron parking lots and lanes observed.

No corrections requested.
General Inspection5/10/20185/10/20185/11/2018PPASS
DetailsMichael Zawacki
Did site walk through with Micron storm water team. Looked at location of future nitrogen plant and state of site. SIte is well managed and maintained. Trash is contained, kept in covered dust, water trucks are in use and site is free of dust. Work on new pump system for water.
All construction traffic is required to take controlled construction entrance and exit.
Building 37 is self contained in parking lot.
Micron is doing weekly site inspections and has all records.
General Inspection3/27/20183/27/20183/27/2018PPASS
DetailsMichael Zawacki
Met with Casey from Steck. Weekly walkthroughs are done on Wednesday. Lots of standing water on site, no mud leaving area. Stormwater all stays on Micron campus.
General Inspection2/21/20182/21/20182/21/2018PPASS
DetailsMichael Zawacki
In house ESC monitors and manages project.
General Inspection1/9/20181/17/20181/17/2018APASS
DetailsAndy J. Long
10 AM Micron walk through for B37 & Fab 51/CUP

10 AM Micron walk through for Fab 51/CUP

On site SWPPP review and site walk through inspection conducted. City of Boise ESC Division, Micron Environmental Compliance team and Stack Construction SWPPP supervisor.

SWPPP book available and up to date. Inspections are conducted weekly and kept within SWPPP binder with BMP checklist, corrective actions, and site maps detailing where BMPs and corrections have been made.

Sediment control BMPs:
- designated construction entrance with rock tracking pad and sectioned off parking and material drop off route via Gate C. No access to Micron employee parking and other gates.
- sheet flow of work area generally flows to the west towards Federal Way and stormwater pond, the construction areas west boundary has rock and filter fabric berms across all discharge points to the parking lots. Additionally all storm drains in this area have sediment filters installed and checked weekly. Maintained as needed.
- Warner Construction sweeps and scraps mud off paved areas within the construction area and access road.

Staging area housekeeping & pollution prevention:
- two large dumpsters on site. Covered at end of each day and during wind events. - Construction waste stream is seperated to recycle wood, cardboard, and scrap metal.
- large capacity lined concrete washout pit located on north west side of staging area near the CUP. Second auxiliary washout is located at east side of staging in case first pit fills up.
- trash is picked up regularly around site. Designated smoking areas to control butt littering has been implemented.
- hazardous materials and waste are stored within a locked Conex container to prevent exposure to storm water and control access to prevent spills. No fuel tanks for equipment on site, Warner Construction has mobile fuel truck with spill kit and protocol.
Summary:
No violations of ESC permit observed. Onsite Responsible Persons, frequent inspections, and regular sweeping and maintenance of sediment control BMPs, and administrative measures are keeping the site in compliance
General Inspection10/30/201711/1/201711/2/2017PCANC
DetailsAndy J. Long
General Inspection10/27/201710/27/201710/30/2017 CANC
DetailsAndy J. Long
General Inspection9/11/20179/11/20179/19/2017 CANC
DetailsAndy J. Long
Conference7/25/20177/25/20177/25/2017PPEND
DetailsAndy J. Long
Fee added for additional disturbance and CUP project disturbance is not shown as paid. Investigation and follow up in progress.
Aging Inspection6/20/20176/20/20176/20/2017 CANC
DetailsMelissa Jannusch
General Inspection4/19/20175/24/20175/24/2017APEND
DetailsMelissa Jannusch
Fees have not been paid for ESC permit
General Inspection3/16/20174/19/20174/19/2017APASS
DetailsMelissa Jannusch
Inspected stormwater pond for sediment plumes. Stormwater pond is not discharging into five mile creek therefore no turbidity testing is required.
Inspected the rock check dams preventing flow into the adjacent parking lots. One needs maintenance which is logged in the SWPPP inspection report.
Inspected DI bags around site to check for clogging. The DI bags have been recently replaced.
A new rip rap drainage swale has been installed to collect and slow water entering the natural drainage area to the south of the site. This area has been tracked incorrectly and will need to be retracked/smoothed and potentially revegetated. Controls along the drainage area are in place to slow water and prevent sediment from entering the vegetation and potentially reaching five mile creek during an extreme event.
Continue preforming maintenance noted in the inspections notes from the weekly inspections.
ESC permit fee still need to be paid. E-mailed RP asking for update in payment status or reason for the delay.
No outstanding corrections.
General Inspection3/14/20173/16/20173/16/2017APASS
DetailsMelissa Jannusch
9:15AM-11:00AM
• Met onsite with erosion control team
• Reviewed SWPPP, weekly inspection reports, inspection maps. SWPPP is available and inspections are up to date. Weekly inspection take place around 9:00AM each Wednesday.
• Discussed site flow and measures that have been implemented to prevent trackout and dirty discharges.
• Discussed changing RP on permit to reflect current responsible person
• Requested changing area of disturbance to reflect current size of project to include the CUP building and staging areas used for active construction.
• The drainage pond’s headwall height has been increased and is no longer discharging into Five Mile Creek.
• Preformed site walk through
• Inspected roof drain, drop inlet protection, concrete washout, staging areas, construction entrance, rock filter berms
• Discussed other BMPs being implemented on site
Corrections requested:
• Preform maintenance noted during the weekly inspections. Reinstall main construction entrance, change plastic dams to filter fabric, preform maintenance on DI bags that require attention.
• Evaluate new area of disturbance to encompasses CUP building disturbance and active staging areas.

General Inspection3/13/20173/13/20173/14/2017 CANC
DetailsAndy J. Long
rescheduled for Thursday 9:30
General Inspection12/20/201612/20/201612/21/2016PCANC
DetailsAndy J. Long
General Inspection11/25/201611/25/201611/25/2016APASS
DetailsAndy J. Long
WIP at Micron. SWPPP infor and Boise ESC permit posted at entrance C.

Onsite retention pond outlet to Fivemile creek has had erosion control blankets installed on slope areas. Silt fene removed from outlet pipe. Wattles installed in creek bed. No corrections requested. Onsite stormwater contols and construction area monitored by BLD inspector
General Inspection11/8/201611/8/201611/10/2016 CANC
DetailsAndy J. Long
General Inspection9/20/20169/23/20169/26/2016PCANC
DetailsAndy J. Long
General Inspection9/20/20169/20/20169/20/2016 CANC
DetailsAndy J. Long
rescheduled for 9/23
General Inspection8/4/20168/4/20168/5/2016PPASS
DetailsAndy J. Long
Heavy duty rock construction entrance installed, permit sign and SWPPP sign posted. Perimeter silt fence in good condtion. No trackout, no fugitive. WIP on foundation work. No corrections requested.
General Inspection7/6/20167/6/20167/6/2016APASS
DetailsAndy J. Long
WIP on large "Fab" building with in Micron. No issues at site perimeter. Permit and SWPPP info posted at Gate C. No fugitive dust observed. No disharges or water in Fivemile Creek. Wattles still installed in outlet area. Approved.
General Inspection4/18/20164/18/20164/18/2016PPASS
DetailsAndy J. Long
WIP at Micron. No discharges off site, no trackout, no issues or changes to SWPPP reported. Permit posted at Gate C. No fugitive dust observed in the area.

No corrections requested.
General Inspection2/24/20162/29/20163/2/2016APASS
DetailsAndy J. Long
10 AM walk through inspection. Meet at Micron Gate C at the stop light on Federal Way.

Jerry ###-####


Meeting and inspection performed Monday 2/29/2016. The inspection started with a meeting with the project’s storm water pollution prevention team. The team consists of M+W Construction and Micron representatives. City of Boise ESC Permit conditions and prospective inspection frequency for the project was reviewed and discussed. The items mentioned included:
• A City of Boise ESC Inspector will inspect the project at a minimum of once a month. Inspections may consist of a site walk through and observation of construction site pollution prevention BMPs and a meeting. Inspections of track-out to Federal Way, checking for significant fugitive dust plumes, and the discharge point into Fivemile Creek will also occur without a full walk through.
• City of Boise ESC Division responds to all complaints received regarding an active construction sites, which results in an inspection.
• The project storm water team shall be notified when inspections are conducted and the inspection results can be reviewed at http://pdsonline.cityofboise.org/pdsonline/details.aspx?id=ESC16-00242
• Micron may request an inspection by the ESC division by ###-#### or ###-####
• If an inspection results in the need for a corrective action, a Correction Request will be issued with set time of compliance depending on the urgency – for example, if a turbid/polluted storm water discharge is occurring, corrections would need to be made immediately. Street sweeping and BMP maintenance typically have 2-3 day compliance times.
There were no points of contention with the above topics that were brought to attention. The stamped and approved SWPPP notebook prepared for the project was presented and reviewed. All required forms including a site map with BMPs indicated, NOI form for CGP permit, signed Certification Statements, narrative of BMPs installation and maintenance procedure, inspection form templates, and corrective action forms. The SWPPP is very comprehensive and easy to follow.
• SWPPP inspection frequency is once per week by members of the storm water team using the inspection template that has all BMPs on site listed.
• Corrections and maintenance procedures are noted on the form as well as a site map that is included as part of the template. Changes are then added to the master SWPPP site map.
• BMPs include perimeter sediment control around the active building footprint, sediment control silt filter bags on all on-site storm drains, wattles used to intercept/trap larger sediment in gutters before entering bags, rock construction entrances for the haul roads, plan for fugitive dust control as needed, and designated material storage and spill prevention practices.
• There were no corrections needed on the SWPPP and record keeping.
General Inspection3/2/20163/2/20163/2/2016APASS
DetailsAndy J. Long
Inspection notes continued from 2/29:

After reviewing the SWPPP, we performed a site walk through and review of BMPs.
• All runoff from the construction site flows into Micron’s permanent storm water treatment and retention facilities. There were no non-point sources or direct outlets offsite. These include catch basins, sand and oil interceptors, a large retention pond, and a flow control device at the outlet to the creek. Micron is monitors storm water discharges for their industrial operations (MSGP) including testing for pollutants. Flow out of the pond may also be stopped altogether if necessary.
• Temporary BMPs have been installed to protect the permanent storm water infrastructure and treat construction site storm water runoff. The installation of sediment filter bags on all receiving catch basins was done properly. These are checked during each inspection and maintained regularly per the Storm water Team. No full bags were observed.
• Around the site it appeared that any loose sediment on roads and parking lots were swept up regularly. A heavy duty rock construction entrance is installed for construction traffic. The areas around the site were very clean.
• All waste materials are contained and hazardous materials collected for proper disposal per RCRA requirements for Micron’s operations. A designated staging and stockpiling area has been provided to the northeast of the construction area. A leak-proof concrete washout facility and silt fence perimeter are noted in the SWPPP.
• A perimeter sediment control is installed around the building footprint. It consists of filter fabric buffer strip covered with rock. Sheet flow off the paved surfaces passes through this filter and traps sediment before flowing towards the gutters and catch basins.
• No fugitive dust issues observed at time of inspection.
• City of Boise ESC permit sign and CGP permit signage posted clearly at Gate C on Federal Way.
• We did discuss use of the straw wattles and filter fabric installed at the outlet to Fivemile Creek that had been observed prior to this inspection. After review of the onsite treatment and BMPs and that these installations are not intended to be the primary filtering BMPs, they are not causing any apparent damage and may be used at the discretion of the project’s Stormwater team.
The inspection passed the review. No violations were observed and no corrective actions issued.
Site Preparation2/24/20162/24/20162/24/2016PCANC
DetailsAndy J. Long
Jerry-call to meet Phone #: ###-####

rescheduled with Jerry for Monday 2/29 @ 10 AM
General Inspection12/18/201712/18/2017   
DetailsMichael Zawacki