General Inspection | 3/9/2020 | 3/9/2020 | 3/9/2020 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 3/9/2020 | 3/9/2020 | 3/9/2020 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 2/7/2020 | 2/7/2020 | 2/7/2020 | | PASS |
Michael Zawacki
|
|
|
Everything completed. Sent message to have someone with CBH come and remove inlet protection.
|
Site Final | 1/6/2020 | 1/7/2020 | 1/7/2020 | P | NR |
Michael Zawacki
|
|
|
DI protection not removed.
|
General Inspection | 1/6/2020 | 1/6/2020 | 1/6/2020 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 12/5/2019 | 12/5/2019 | 12/6/2019 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 11/4/2019 | 11/4/2019 | 11/6/2019 | | PASS |
Michael Zawacki
|
|
|
Neighborhood looks completed. All homes landscaped. Inlet protection still installed.
|
General Inspection | 10/3/2019 | 10/3/2019 | 10/4/2019 | | PASS |
Michael Zawacki
|
|
|
All homes completed, some still need landscaping. DI protection still installed.
|
General Inspection | 9/2/2019 | 9/2/2019 | 9/3/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/1/2019 | 8/1/2019 | 8/2/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 7/1/2019 | 7/1/2019 | 7/1/2019 | | PART |
Michael Zawacki
|
|
|
Message sent to RP to clean old and make new washout before any more concrete work. No major issues at site.
|
General Inspection | 5/31/2019 | 5/31/2019 | 5/31/2019 | P | PART |
Michael Zawacki
|
|
|
Concrete washout full and needs to be cleaned or replaced. Dirt from rain has run onto sidewalk. No major concerns, needs some housekeeping.
|
General Inspection | 5/23/2019 | 5/23/2019 | 5/23/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/22/2019 | 4/22/2019 | 4/22/2019 | | PASS |
Michael Zawacki
|
|
|
Work has started on 3 new SFH. Large lined washout on site and used. Sites are clean. Some wind blown trash starting to accumulate in rear of site along fence.
|
General Inspection | 3/21/2019 | 3/21/2019 | 3/21/2019 | | PASS |
Michael Zawacki
|
|
|
Homes on east of Linda Vista all completed and landscaped. One lot on north of Burnett still needs to be landscaped. Few homes framed and under construction. No current excavation or foundation work. No dust or trackout.
|
General Inspection | 1/17/2019 | 1/17/2019 | 1/17/2019 | | PASS |
Michael Zawacki
|
|
|
No current construction activity. Large lined washout on site.
|
General Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | | PASS |
Andy J. Long
|
|
|
WIP. Lined washout installed for Diamante SFHs. Storm drains have sediment protection. No significant trackout, no loose trash around sites. No corrections at this time.
|
General Inspection | 11/15/2018 | 11/15/2018 | 11/16/2018 | | PASS |
Andy J. Long
|
|
|
2 homes in progress by CBH in Diamante. Storm drains have sediment protection. Lined concrete washout pit provided for subdivision, currently in operable condition.
|
General Inspection | 10/15/2018 | 10/15/2018 | 10/15/2018 | | PART |
Michael Zawacki
|
|
|
Witches hat at mitchell on south needs to be cleaned. Some bins were dumped on street, some random trash thrown around. Washout is in good shape. Sparse vegetation on empty lots.
|
General Inspection | 9/14/2018 | 9/14/2018 | 9/17/2018 | | PART |
Michael Zawacki
|
|
|
Witches hats and gutter need to be cleaned at Roan Meadows & Mitchell. New lined wahout pit on site, old washout was on ground, needs to be cleaned up. Some windblown trash on site. Homesites under construction are clean.
|
General Inspection | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | PASS |
Andy J. Long
|
|
|
WIP on SFHs by CBH. Concete washout installed. DIs have sediment protection. No fugitive dust or other violations observed. Approved.
|
General Inspection | 8/10/2018 | 8/10/2018 | 8/13/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/2/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Andy J. Long
|
|
|
WIP on SFHs by CBH. Subdivision storm drains have sediment protection installed. New lined concrete washout now installed by CBH as requested.
No corrections requested.
|
General Inspection | 7/2/2018 | 7/2/2018 | 7/2/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/31/2018 | 5/31/2018 | 5/31/2018 | | PASS |
Michael Zawacki
|
|
|
Not much activity on site. Talked with project manager and he will replace the witches hats.
|
General Inspection | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | FAIL |
Andy J. Long
|
|
|
Inspection reports not being read by contractor and not being conveyed to CBH by 3rd party inspectors.
Developer intends to close initial permit and have CBH take over.
Corrections needed: - clean up dumped washout to prevent further dumping - install lined concrete washout pit or leak proof container. - check all DI bags for maintenace. DI at Roan Meadow & Mitchell is full.
Verbal correction issued to developer Scott and Brett with CBH (Colby is out of town)
|
Complaint Inspection | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | PART |
Michael Zawacki
|
|
|
Washout has been dumped in vacant lot, no washout area for site. Withches hats on Roan Meadows Dr full and need to be cleaned.
|
General Inspection | 4/4/2018 | 4/4/2018 | 4/4/2018 | P | PART |
Michael Zawacki
|
|
|
DI protection near Mitchell needs to be cleaned. Dirt and sand is ending up on roads and sidewalks throughout site.
|
General Inspection | 3/5/2018 | 3/5/2018 | 3/6/2018 | | FAIL |
Michael Zawacki
|
|
|
Dirt and trackout throughout site. Washout has been dumped onto the ground.
|
General Inspection | 2/2/2018 | 2/2/2018 | 2/2/2018 | | FAIL |
Michael Zawacki
|
|
|
Trackout throughout sight. Will need a washout for lots or require each builder to have their own.
|
General Inspection | 1/2/2018 | 1/2/2018 | 1/2/2018 | P | PASS |
Andy J. Long
|
|
|
Subdivision complete and awaiting new SFH construction by CBH in 2018. No ESC issues observed.
|
General Inspection | 12/28/2017 | 12/28/2017 | 12/29/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/27/2017 | 11/27/2017 | 11/27/2017 | P | PASS |
Michael Zawacki
|
|
|
No WIP, roads, sidewalk, curb and gutter completed. DIs are clean, Syman is doing inspections. Site has no EPA NOI. Was done under 2012 permit and there is no record of changing to 2017.
|
General Inspection | 11/2/2017 | 11/2/2017 | 11/2/2017 | | CANC |
Andy J. Long
|
|
|
|
Random Inspection | 10/2/2017 | 10/2/2017 | 10/2/2017 | A | PASS |
Andy J. Long
|
|
|
No new activity or SFH work. Area is free of loose trash or debris and no windblown dust observed.
|
General Inspection | 9/11/2017 | 9/11/2017 | 9/13/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/10/2017 | 8/10/2017 | 8/14/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/10/2017 | 7/10/2017 | 7/10/2017 | P | PASS |
Andy J. Long
|
|
|
No activity. Perimeter landscaping installed. MS4 on Mitchell and Victory have sediment protection.
|
General Inspection | 7/7/2017 | 7/7/2017 | 7/10/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/6/2017 | 6/6/2017 | 6/6/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/3/2017 | 5/3/2017 | 5/3/2017 | A | PASS |
Andy J. Long
|
|
|
Subdivsion work complete. No SFH construction yet. All new inlets have sediment filter bags. MS4 on Victory has protection and bank and perimeter control wattle with some natural revegetation occuring. SWPPP info onsite. Approved.
|
General Inspection | 4/12/2017 | 4/12/2017 | 4/12/2017 | P | PASS |
Andy J. Long
|
|
|
Subdivision development work complete at Diamante. Will be a CBH subdivision. NO homes started yet. New storm drain inlets within sub, Mitchell and Victory have sediment protection.
Open lots are graded flat with some volunteer grass establishinng. No loose stockpile. No fugitive dust issues.
CBH will need to provide concrete washout facility. Will request an above ground portable containment.
No corrections requested..
|
General Inspection | 4/5/2017 | 4/5/2017 | 4/5/2017 | | PASS |
Melissa Jannusch
|
|
|
Subdivision inactive. No ESC issues.
|
General Inspection | 3/2/2017 | 3/2/2017 | 3/2/2017 | P | PASS |
Melissa Jannusch
|
|
|
SWPPP binder up to date. No corrections requested.
|
General Inspection | 2/8/2017 | 2/9/2017 | 2/9/2017 | P | CANC |
Melissa Jannusch
|
|
|
|
General Inspection | 10/21/2016 | 10/21/2016 | 10/21/2016 | A | PART |
Andy J. Long
|
|
|
Permit sign posted, road widening of Mitchell in progress as well as prep for concrete curbing and connection to storm water facilities.. MS4 on Victory has sediment filter bag installed a. No trackout to Victory or sediment runoff to sidewalk. No fugitive dust observed, water truck onsite.
Due to activity, construction entrance is not in good condition and there is trackout to Mitchell on the south entrance.
Verbal Correction Request to RP-developer Scott to ensure that crews sweep up all trackout to Mitchell to prevent muddy water on road and as courtesy to neighbors south of project. RP agreed to request and stated he will make sure it is swept.
|
General Inspection | 9/19/2016 | 9/20/2016 | 9/20/2016 | P | PASS |
Andy J. Long
|
|
|
Follow up inspection to dust complaint. Water truck is on site to spray down stockpiles as they are used for backfill and compaction activities. 1 water truck on site with designated driver. No trackout, no complaints regarding dust this week. warning issued to RP, RP notified subcontractor to manage dust control as a priority.
No dust plumes leaving site boundaries at time of inspection
|
Complaint Inspection | 9/19/2016 | 9/19/2016 | 9/19/2016 | P | PEND |
Andy J. Long
|
|
|
dust complaint.
Called RP Scott to request better fugitive dust control. Heavy activity last week disturbed neighbors. Water tank and water truck on site but need to improve frequency and coverage during all active grading.
|
General Inspection | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | PASS |
Evan Jenkins
|
|
|
Mass Grading is occuring at this time. Water truck is being utilized to reduce dust. no discharges leaving the site at this time
|
General Inspection | 8/15/2016 | 8/15/2016 | 8/15/2016 | P | PASS |
Andy J. Long
|
|
|
No activity at time of inspection. Only small portion of area has been excavated. Rough grading and grubbing has not occured yet.
Will need to install rock construction entrance once equipment arrives on site. No trackout, dust, or other issues at time of inspection.
|
General Inspection | 7/21/2016 | 8/4/2016 | 8/4/2016 | A | PASS |
Evan Jenkins
|
|
|
work continues on grading for SFH lots. No issues observed at this time.
|
Site Preparation | 7/21/2016 | 7/21/2016 | 7/21/2016 | A | PASS |
Andy J. Long
|
|
|
11:30 AM Scott ###-####
Site walk through with RP Scott. Permit sign posted, initial BMPs (perimeter wattle along Victory, DI protection on Victory @ Mitchell. No violations.
Flat lot with good infiltration, limited runoff potential. No surface waters. RP familiar with fugitive dust control and requirements and will have water truck(s) on site.
Approved for construction. Construction entrance to be installed after initial grubbing on S. Mitchell.
|
General Inspection | 2/18/2019 | 2/18/2019 | | | |
Andy J. Long
|
|
|
|