Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberESC16-01354
StatusFinaled
Name ROBERT L MITCHELL
Site Address 1101 W FRONT ST
Project NamePioneer Crossing grading
Customer Number 
ePlanReviewNo
Description
First phase of Pioneer Crossing parking garage and site improvements for future office and retail space.. No dewatering operations are currently anticipated. MS4 storm drain inlets are to be fitted with new sediment filter bags. Site will have designated construction access and track out controls. Fugitve dust supression from construction and disturbed areas is required. Site preparation inspection and pre-construction BMP installation is required, call 384-3802 or 794-8996 to schedule.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final3/11/20193/12/20193/12/2019PPASS
DetailsAndy J. Long
All remaining work and removal of temporary BMPs at Pioneer Crossing is covered by ESC18-00529 and ESC18-00565.

No further inspections on this permit, conditions satisfied.
General Inspection3/8/20193/8/20193/11/2019 CANC
DetailsAndy J. Long
General Inspection1/21/20191/21/20191/22/2019 PASS
DetailsAndy J. Long
General Inspection12/4/201812/4/201812/4/2018 PASS
DetailsMichael Zawacki
All projects complete with ground disturbances except for Okland's project. Site is half thawed and messy, only one mechanical contractor truck parked on site, all others in lot across 13th.
Site is well contained and nothing is leaving. Will need to watch for trackout.
General Inspection10/19/201810/19/201810/19/2018 PASS
DetailsAndy J. Long
General Inspection9/3/20189/3/20189/4/2018 PASS
DetailsAndy J. Long
General Inspection7/17/20187/17/20187/17/2018 PASS
DetailsAndy J. Long
No corrections requested. ESC permit open to make sure all DI bags installed around project perimeter are removed. Buildings permited seperately
General Inspection6/1/20186/1/20186/1/2018 PASS
DetailsMichael Zawacki
Completed all permits as one large site inspection. Controlled entrance and exit, no trackout onto roads. Site is free from fugitive dust, all trash contained. Materials on site are neatly stored. Landscaping along front of hotel not yet completed. Panera Bread has no stucco washout, is being dumped on ground.
General Inspection4/16/20184/16/20184/16/2018 PASS
DetailsMichael Zawacki
No new work. Area is currently stable and clean.
General Inspection2/27/20182/27/20182/27/2018 PASS
DetailsAndy J. Long
BLD has temp. occupancy for parking garage and Chamber of Commerce tenant space. Two active projects on block, will keep this permit open for continued monitoring.
Tracking Control11/27/201711/27/201711/28/2017PPASS
DetailsAndy J. Long
Trackout has been cleaned up. New rock installed at entrance to Myrtle.

Crews installing grass and trees between sidewalk and curbing along Myrtle. Will need to have gutters swept upon completion.

Pioneer Path entrance work that was included on this permit is now stabilized. WIP on parking garage exterior and interior finishes..
Tracking Control11/27/201711/27/201711/27/2017PCANC
DetailsAndy J. Long
Tracking Control11/24/201711/24/201711/27/2017ACANC
DetailsAndy J. Long
Tracking Control11/6/201711/7/201711/7/2017APASS
DetailsAndy J. Long
follow up

New rock construction entrance installed and Myrtle and 11th were street swept. Next sweeping the bike lane and gutter should be a focus.

Corrections complete
Tracking Control11/6/201711/6/201711/6/2017AFAIL
DetailsAndy J. Long
Trackout to Myrtle, construction entrance/exit muddy with in site.

Verbal correction requests to Okland RP:
- sweep north lane of Myrtle to 11th street
- repair construction entrance and clean up mud on apron.

Concrete washout has been removed, shell of parking structure is complete. WIP to prep site for further development @ Pioneer Crossing.

RP stated sweeper has been scheduled. Crew working on new construction entrance.
General Inspection10/3/201710/3/201710/4/2017 PASS
DetailsAndy J. Long
Washout pit being utilized, stabilized entrance and regular sweeping provided. MS4 around project has sediment filter bags installed.
General Inspection8/18/20178/18/20178/18/2017 PASS
DetailsAndy J. Long
No trackout. Permit signs posted. DI bags installed on surrounding MS4 drains. No fugitive dust or discharges offsite observed
General Inspection6/30/20177/3/20177/3/2017APASS
DetailsMelissa Jannusch
General Inspection6/28/20176/28/20176/30/2017ACANC
DetailsAndy J. Long
General Inspection5/23/20175/23/20175/23/2017PPASS
DetailsAndy J. Long
Vertictal construction in progress and on interior access road. Perimeter curb and gutter installation is near complete. No trackout or discharges observed on Myrtle or 11th street. No fugitive dust issues observed or reported. Approved.
General Inspection4/10/20174/10/20174/10/2017PPASS
DetailsAndy J. Long
WIP on first and second levels of parking garage. No trackout from either entrance. RP on duty. Large lined concrete washout pit onsite. No corrections at this time, need to check construcrtion entrance on 11th next inspection. Parcel shared with Hilton Garden Inn, different contractor, see ESC16-01446.
General Inspection3/10/20173/10/20173/10/2017PPASS
DetailsAndy J. Long
WIP on vertical construction for parking garage. Using Myrtle entrance and exit on 11th. No trackout. RP on site. No corrections requested.
Tracking Control2/6/20172/7/20172/8/2017APASS
DetailsAndy J. Long
Trackout cleaned, alternate construciton entrance provided. No new trackout. No corrections requested.
General Inspection12/7/201612/8/201612/8/2016APASS
DetailsAndy J. Long
check for concrete washout

Large capacity lined concrete washout pit has been installed and is being utilized. Rock tracking pad provided.
General Inspection12/6/201612/7/201612/7/2016APASS
DetailsAndy J. Long
ESC BMPs installed per ESC plan. SWPPP binder on site with regular inspections recorded.

RP Robert on site, informed that heavy concrete truck traffic will be occuring and has sweeper on call if necessary.

Concrete washout pit to be provided at west end of site.
General Inspection11/21/201611/21/201611/21/2016PPASS
DetailsAndy J. Long
Perimeter sediment controls and trackout prevention access are installed. No discharges, trackout, or fugitve dust observed. RP onsite. Approved.
General Inspection11/17/201611/18/201611/17/2016APASS
DetailsAndy J. Long
Site Preparation10/31/201611/1/201611/1/2016APASS
DetailsAndy J. Long
Robert Phone #: ###-####

Initial BMPs installed including new MS4 inlet protection and perimeter wattle. ESC permit sign posted on 11th Street entrance. Extra signage provided for 13th Street.

Employee parking and Alta staging area in process of being set up and will have gravel rock base to keep mud down.

RP Robert stated that working on building a stabilized access road through site for loading and concrete truck traffic. Exit on 13th will have rock trackout pad and/or rumble. Exit to be graded to not slope out to street as it currently is. Lined concrete washout pit will also be installed prior to any concrete work.

RP to call for follow inspection for stabilized construction entrance(s) and washout facility. Water from the pit will be sucked out and put into Eco-Pans for appropriate disposal.

Dewatering not scheduled to occur till Spring per Robert, will continue to monitor.

CGP tracking # IDR12AW61, active status
General Inspection1/12/20181/12/2018   
DetailsMichael Zawacki
General Inspection11/9/201711/9/2017 P 
DetailsMichael Zawacki