Permit Information
Permit NumberESC18-01636
StatusIssued
Name JASON JONES
Site Address 3901 E WARM SPRINGS AVE
Project NameDallas Harris Estates TH #9
Customer NumberGRD18-00089
ePlanReviewNo
Description
Stabilized construction entrance and ESC permit information to be located off Warm Springs by-pass, south of area of disturbance and inline with Trailwood Way. Gravel road access also to be extended west to Wise Way. Old stormwater features witin subdivsion are to be overexcavated and have structural fill placed. Entire area will be raised in elevation level. Perimeter vegetation outside of clearing limits in the pasture shall be preserved. Perimter sediment control wattles shall installed along south limit next to new ditch route and also along Wise and Trailwood. See ESC site plan. This project will require dewatering for the installation of sewer lines and potentially for drain old ponds. Dewatering plan and inspection required. Site pre-construction and ESC site preparation inspection are required. Note: ESC plan submitted meets City of Boise requirements only, not CGP 2017 SWPPP requirements (SWPPP currently being preparared)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/30/20207/30/20208/7/2020 CANC
DetailsAndy J. Long
General Inspection7/15/20207/15/20207/15/2020 PASS
DetailsMichael Zawacki
Knife River on south side of Warm Springs. They are removing culvert connecting ponds. They will also grade and get everything to elevation before fence installed. Will be back on north of road to continue grading soon.
General Inspection6/30/20206/30/20206/30/2020PPASS
DetailsMichael Zawacki
No development activity at time of inspection, site is contained, no issues.
General Inspection6/29/20206/29/20206/29/2020 PASS
DetailsMichael Zawacki
No workers on site.
General Inspection6/12/20206/12/20206/12/2020 PASS
DetailsAndy J. Long
General Inspection5/28/20205/28/20205/28/2020 PASS
DetailsMichael Zawacki
No activity on western half of project.
One truck hauled some material into eastern side. One worker on site.
General Inspection5/13/20205/13/20205/13/2020 PASS
DetailsMichael Zawacki
Grader and roller on far east of site. Water truck and water wagon on site. Two sweepers at site, no tracking on any paved road.
Homes are starting to be built on NW corner of new development.
General Inspection4/28/20204/28/20204/28/2020 PASS
DetailsMichael Zawacki
One grader working on east side of project. Black Rock has cleaned their mess that was going into the knife river project.
West area has one dozer moving fill material. Pile of contanimated soil still on far west of project.
Sewer work on south of project. Currently installing box on west of last pond. Dewatering straight into pond. Still some sewer work on far east, boxes not on site yet.
General Inspection4/13/20204/13/20204/13/2020PPASS
DetailsMichael Zawacki
No more pond dewatering. Finishing touches on ponds. Will get willows and hydroseeded, iron fence will be installed.
Safety fence on greenbelt has been wind damaged, Rex has a guy to repair it.
Contanimated water pond has been cleared to drain, pumping under road through hose and into middle pond.
Still have large stockpile of contanimated soil. Will get more plastic to move pile and expose. Contanimates are evaporative and need to be exposed.
Clean fill staged will be used to bring area around contanimate pond up to elevation.
In future there will be one more pond west of Barber, not in current phase.
General Inspection4/3/20204/3/20204/3/2020PPASS
DetailsMichael Zawacki
Stockpiles of material. Crew working on water lines.
General Inspection3/26/20203/26/20203/26/2020PPASS
DetailsMichael Zawacki
Running sewer line through site, dewatering water is going onto pasture. Hauling in of fill material from north side. No issues.
General Inspection3/16/20203/16/20203/16/2020 PASS
DetailsMichael Zawacki
No pond excavation. Ditch for dewatering water has been piped. No plans to do any work in area of contanimation for about a month.
No work on NE section of project. Placing fill already hauled from ponds.
Work on finishing storm pond overflow along greenbelt and under road.
General Inspection2/28/20202/28/20202/28/2020 PASS
DetailsMichael Zawacki
Connection through to wise way not completed, no crew on site. Haul trucks not running material from ponds at time of inspection.
General Inspection2/13/20202/13/20202/18/2020 PASS
DetailsMichael Zawacki
Crew is working on connecting east and west phases with water lines. Any trench dewatering is staying on site in existing retention. Roads will need to be swept from deliveries. Workers are parked on paved areas.
General Inspection1/29/20201/29/20201/29/2020 PASS
DetailsMichael Zawacki
Met with Rex at site. Starting to strip and stockpile on south of Warm Spring. They are getting the bench stripped and plan to grade a few feet above water table. Will not start well points or dewatering until next week.RP supposed to get site prep scheduled before excavation work.
North side concrete work has begun on east edge of area, will be the alley behind homes. Washout is being used, some tracking, getting cleaned as occurs, power broom at site.
Currently hauling away brush and fill from behind Shakesphere, want to get road done.
General Inspection1/29/20201/29/20201/29/2020PCANC
DetailsMichael Zawacki
General Inspection1/14/20201/14/20201/14/2020 PASS
DetailsMichael Zawacki
No activity on site
General Inspection12/30/201912/30/201912/30/2019 PASS
DetailsMichael Zawacki
Crews starting to install fence along greenbelt, no dirt activity.
RPC on main site doing wall along Shakesphere building. Sidewalks LLC doing some work, no concrete pours.
All issues are from site to east.
General Inspection12/13/201912/13/201912/13/2019PPASS
DetailsMichael Zawacki
Sidewalks LLC on site working on Ped ramps and sidewalks. Crews still doing irrigation work. Some piped staged on south side of project. No dirt work.
General Inspection11/29/201911/29/201912/4/2019 PASS
DetailsMichael Zawacki
Crew on site installing irrigation system. Alley ways havew been poured, have blankets on them. No dirt work at site.
General Inspection11/14/201911/14/201911/19/2019PPASS
DetailsMichael Zawacki
Met with Rex at site.
Area is paved and has curbing and sidewalks, washout on site.
Original dewatering water oked to drain. Pond about half full from water from finishing connection, still waiting for test results.
Most contanimated dirt gone, area still need some cleanup.
Still no for sure timeline on ponds.
General Inspection11/1/201911/1/201911/4/2019PPASS
DetailsMichael Zawacki
Met with Rex from Knife river while at site.
They are waiting for lab results for water in pond. If it comes back clean they will pump it out into the field to the east.
Contanimated dirt pile still on site, if test come back ok it will be used as fill.
They are planning to pave and do curb and gutter this fall, not sure if it will get done in time.
Three ponds are planned on getting built on south side of warm springs and all excavated material used for fill.
Will need to set up meeting with all parties to see what plan is, nothing has any dates set yet.
General Inspection10/25/201910/25/201910/25/2019APASS
DetailsMichael Zawacki
Got tap done on south now on north side of road. Pond is nearly full, no sign of overflowing or pumping out.
General Inspection10/22/201910/24/201910/23/2019APASS
DetailsMichael Zawacki
Engineer on site monitoring excavation and dewatering for contanimation. Pumps will go into lined pond, if needed decontanimation system will be broughjt to site to clean water before discharge from pond. Bad dirt is being seperated and will be hauled off site is past limits of contanimation set by DEQ.
General Inspection10/22/201910/22/201910/22/2019 PEND
DetailsAndy J. Long
Warm Springs bypass to be closed and excavated for sewer connections. Special dewatering system with lined basin has been set up to receive the potentially contaminated ground water from the work. There is no discharge allowed for this dewatering operation. Stockpile on site has been tested and is approved for re-use. Any new excavated soil will need to be stored and tested on site until approval.

Notified engineer to have Knife River notify the SWPPP inspector to be aware of the operation and update the dewaterinfg plan in SWPPP.

Follow up inspection scheduled
General Inspection9/26/20199/26/20199/26/2019PPASS
DetailsMichael Zawacki
One excavator on site. Some open holes for joint trench. Pipe and material staged on site.
General Inspection7/3/20197/3/20197/3/2019PPASS
DetailsMichael Zawacki
3 man crew on site filling and compacting backfill. Road crew should be on site next week. Water truck on site, no blowing dust.
General Inspection6/13/20196/13/20196/13/2019PCANC
DetailsMichael Zawacki
General Inspection6/12/20196/12/20196/12/2019PPASS
DetailsMichael Zawacki
Only dewatering was staying on site, pump and well point into storm sewer turned off. New road access has been cut to site from behing shakespere building. No dust or ESC issues. Sweeper still at site.
General Inspection5/1/20195/1/20195/1/2019PPASS
DetailsMichael Zawacki
Dewatering still ongoing. Well point goes straight to ditch, discharge is clear. Trench work overland discharged. Large pond on sitye and flows east into filed with cows. Sewer, water, and drainage pipes stored on site. Some dust as trucks drive away, no other ESC issues.
General Inspection4/2/20194/2/20194/2/2019PPART
DetailsMichael Zawacki
Dewatering ongoing, discharge is clear. Still hauling in pit run, construction exit needs some repair, pretty compacted, pile of rocks is next to it. Drain inlet bags next to entrance nearly full. Not much trackout, talked to guys on site and said it is swept every few hours.
General Inspection3/14/20193/15/20193/15/2019PPEND
DetailsAndy J. Long
Water that was flowing through site has now been diverted for bypass around disturbed areas. Dewatering water in channels within site is being land applied to the adjacent pasture.

Follow up next week

Trucking operation upsetting neighbors, request to check that loads are not overfull and route is appropriate.
General Inspection3/8/20193/11/20193/14/2019ACANC
DetailsAndy J. Long
BMP Violation3/7/20193/7/20193/14/2019PCANC
DetailsAndy J. Long
General Inspection3/7/20193/7/20193/7/2019PFAIL
DetailsAndy J. Long
Dewatering with no record of turbidity or visual monitoring. Incomplete SWPPP paperwork.

Notice of discharge noted in SWPPP corrective action log was not reported to City of Boise ESC division. No ESC dewatering inspection or plan submitted.

Case pending.

Construction entrance are also not 50 ft length per ESC site plan.
General Inspection2/8/20192/8/20192/8/2019PPASS
DetailsMichael Zawacki
Currently bringing in fill to raise area out of floodplain. Old cattail wetland being filled, will need to be dewatered. Plenty of surface area for overland dewatering. Utilities may need dewatering during install, will know more when parcel is raised and elevations established.
Site currently has rock entrance that is working well, sweeper also on site. Stripped material being stored on Harris property for future park.
Site Preparation1/31/20191/31/20192/1/2019PPASS
DetailsAndy J. Long
Permit posted. Initial BMPs installed per first phase. Site will be built out in phases as stabilization is accomplished.

Approved for construction. Follow up next week for completion of construction entrances.