Site Final | 4/13/2017 | 4/13/2017 | 4/13/2017 | P | PASS |
Melissa Jannusch
|
|
|
|
General Inspection | 4/13/2017 | 4/13/2017 | 4/13/2017 | | PASS |
Melissa Jannusch
|
|
|
Dirt pile and trash in parking lot have been cleaned okay to final
|
General Inspection | 3/29/2017 | 3/29/2017 | 3/29/2017 | | PASS |
Melissa Jannusch
|
|
|
Library nearing completion. Sidewalk and curb work complete. Soil not yet stabilized. No corrections requested.
|
General Inspection | 3/14/2017 | 3/14/2017 | 3/14/2017 | | PASS |
Melissa Jannusch
|
|
|
To obtain ESC site final need to remove small dirt pile in corner of parking lot and trash.
|
General Inspection | 2/27/2017 | 2/27/2017 | 2/27/2017 | | PASS |
Andy J. Long
|
|
|
Project near completion. Building exterior complete and site landscaping and permanent stormwater swale are installed. No offsite discharges, no trackout or loose trash around site perimeter. WIP on installing carports in parking lot with some disturbed area that need stabilization and final sweep up before ESC site final.
|
General Inspection | 2/10/2017 | 2/10/2017 | 2/10/2017 | | PASS |
Melissa Jannusch
|
|
|
Small amount of work in parking lot. Small amount of trackout. Make sure this is cleaned before final. Surrounding vegetation is mature.
|
General Inspection | 1/26/2017 | 1/26/2017 | 1/27/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/11/2017 | 1/11/2017 | 1/12/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/27/2016 | 12/27/2016 | 12/28/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/12/2016 | 12/12/2016 | 12/13/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/25/2016 | 11/25/2016 | 11/25/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/26/2016 | 10/26/2016 | 10/27/2016 | | PASS |
Andy J. Long
|
|
|
WIP on exterior finish and interior. Loose dirt in guttter on Bown has been removed/cleaned. No new trackout or issues.
|
General Inspection | 10/11/2016 | 10/11/2016 | 10/11/2016 | | PASS |
Phil Shearer
|
|
|
No trackout, discharges, or uncontained trash observed
|
General Inspection | 9/26/2016 | 9/26/2016 | 9/26/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/9/2016 | 9/9/2016 | 9/9/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Structure is framed. Exterior and interior finishes occuring. Vegetation around site has been preserved, site storm water retention system is already installed. No trackout, discharges, or uncontained trash observed.
|
General Inspection | 8/25/2016 | 8/25/2016 | 8/25/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 8/10/2016 | 8/10/2016 | 8/10/2016 | | PASS |
Andy J. Long
|
|
|
WIP. Vertical construction, no earthwork or utility installation remaining except final landscaping. No trackout or loose dirt/sediment leaving site.
|
General Inspection | 7/26/2016 | 7/26/2016 | 7/26/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 7/11/2016 | 7/11/2016 | 7/12/2016 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 6/24/2016 | 6/24/2016 | 6/24/2016 | | PASS |
Andy J. Long
|
|
|
Vertical construction in progress. No earthwork. No violations observed.
|
General Inspection | 6/9/2016 | 6/9/2016 | 6/10/2016 | | PASS |
Andy J. Long
|
|
|
No trackout. Vegetated perimeter is undisturbed. Working on the interior. Site infrastructure already installed.
|
General Inspection | 5/25/2016 | 5/25/2016 | 5/25/2016 | | PASS |
Andy J. Long
|
|
|
WIP. No trackout or discharges. Vegetated swale at corner of Bown and Parkcenter is undisturbed and berm keeps out sediment during rain. Construction fencing defines site limits. No corrections issued.
|
General Inspection | 5/10/2016 | 5/10/2016 | 5/10/2016 | | PART |
Evan Jenkins
|
|
|
WIP: sweep minor trackout off road
|
General Inspection | 4/25/2016 | 4/25/2016 | 4/25/2016 | | PASS |
Evan Jenkins
|
|
|
WIP: no ESC issues at this time
|
General Inspection | 4/8/2016 | 4/8/2016 | 4/8/2016 | | PASS |
Andy J. Long
|
|
|
No trackout or sediment/debris leaving site. No activity at time of inspection. No violations.
|
General Inspection | 3/24/2016 | 3/24/2016 | 3/24/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/9/2016 | 3/9/2016 | 3/10/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/23/2016 | 2/23/2016 | 2/24/2016 | | PART |
Andy J. Long
|
|
|
No activity at site. No discharges or trackout.
Corrections needed at site:
- remove damaged and inoperable silt fence - clean loose trash around site - sweeping parking lot/staging area
Correction issue to Travis with Pinnacle Builders.
|
General Inspection | 2/8/2016 | 2/8/2016 | 2/8/2016 | | PART |
Andy J. Long
|
|
|
Corrections needed:
- post ESC permit sign - sweep up parking lot/staging area
|
General Inspection | 1/21/2016 | 1/22/2016 | 1/22/2016 | P | PART |
Andy J. Long
|
|
|
Vertical construction in progress. No earthwork occuring. Need to repair silt fence barrier or install alternative perimeter control. No trackout or discharges observed.
|
General Inspection | 1/21/2016 | 1/22/2016 | 1/21/2016 | A | CANC |
Andy J. Long
|
|
|
data entry error
|
General Inspection | 1/21/2016 | 1/21/2016 | 1/21/2016 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/6/2016 | 1/6/2016 | 1/6/2016 | | PASS |
Andy J. Long
|
|
|
WIP on first floor columns and site work. No earth work. Site perimeter is stabile, no muddy runoff discharges observed.
|
General Inspection | 12/22/2015 | 12/22/2015 | 12/22/2015 | | PASS |
Andy J. Long
|
|
|
No activity at site. Seems to be inactive for over 1 month. Site security fence has been knocked down.
No trackout or discharges occuring, water retained within foundation footprint.
|
General Inspection | 12/3/2015 | 12/4/2015 | 12/7/2015 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/3/2015 | 12/3/2015 | 12/3/2015 | | CANC |
Andy J. Long
|
|
|
rescheduled for 12/4
|
General Inspection | 11/18/2015 | 11/18/2015 | 11/18/2015 | | PASS |
Andy J. Long
|
|
|
No construction activity at time of inpsection. Foundation was recently poured and a lined concrete washout box (Outpack) was utilized. No spills or leaks.
Site staging/parking area is utilizing existing paved area so no trackout issues. Silt fence installed along Bown Street is keeping west side of project contained. No activity in the swale overflow channel area next to Greenbelt with no loose sediment or disturbed area in channel. Site utilities are now installed so dewatering phase is complete and frack tank has been removed.
Permit sign posted, no corrections at this time.
|
General Inspection | 10/15/2015 | 10/15/2015 | 10/15/2015 | | FAIL |
Andy J. Long
|
|
|
###-#### Rob...
No activity at time of inspection. Warning issued to Hard Rock in regards to not scheduling site prep. Perimeter sediment BMPs and sign are posted. Rain4rent tank on site.
Notified that PW sewer inspector shut the operation down due to dewatering failure.
Dewatering permit pulled with ACHD to discharge "visibly clean and clear water" into MS4 swales.
|