General Inspection | 11/27/2019 | 11/27/2019 | 11/27/2019 | | CANC |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 11/27/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Michael Zawacki
|
|
|
Landscaped and exterior completed.
|
General Inspection | 11/12/2019 | 11/12/2019 | 11/12/2019 | | PASS |
Michael Zawacki
|
|
|
Lot is now landscaped. OK to final when BLD closed.
|
General Inspection | 10/28/2019 | 10/28/2019 | 10/28/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/11/2019 | 10/11/2019 | 10/11/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/26/2019 | 9/26/2019 | 9/26/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/11/2019 | 9/11/2019 | 9/11/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 8/27/2019 | 8/27/2019 | 8/27/2019 | | CANC |
Andy J. Long
|
|
|
|
Site Final | 8/12/2019 | 8/12/2019 | 8/15/2019 | P | NR |
Andy J. Long
|
|
|
Work still in progress.
|
General Inspection | 8/12/2019 | 8/12/2019 | 8/12/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/26/2019 | 7/26/2019 | 7/26/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 7/11/2019 | 7/11/2019 | 7/11/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 6/26/2019 | 6/26/2019 | 6/26/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/11/2019 | 6/11/2019 | 6/11/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/27/2019 | 5/27/2019 | 5/28/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/10/2019 | 5/10/2019 | 5/10/2019 | | PASS |
Michael Zawacki
|
|
|
Backyard being landscaped, buffer by creek.
|
General Inspection | 4/25/2019 | 4/25/2019 | 4/25/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/10/2019 | 4/10/2019 | 4/10/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/26/2019 | 3/26/2019 | 3/26/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity. Large buffer in backyard between disturbed area and crane creek.
|
General Inspection | 3/11/2019 | 3/11/2019 | 3/11/2019 | | PASS |
Michael Zawacki
|
|
|
Front is landscaped. Access to rear and rear are both exposed, no activity and no dirt leaving site.
|
General Inspection | 2/22/2019 | 2/22/2019 | 2/26/2019 | | PASS |
Michael Zawacki
|
|
|
Side lot into back bare, no activity. No runoff going to creek.
|
General Inspection | 2/7/2019 | 2/7/2019 | 2/7/2019 | | PASS |
Michael Zawacki
|
|
|
Back will need landscaping, hasn't been disturbed since new owner took over.
|
General Inspection | 1/23/2019 | 1/23/2019 | 1/24/2019 | | PASS |
Michael Zawacki
|
|
|
Front is landscaped and stable. No work has begun in rear.
|
General Inspection | 1/8/2019 | 1/8/2019 | 1/8/2019 | | PASS |
Michael Zawacki
|
|
|
Front yard has been sodded, no new activity in rear.
|
General Inspection | 12/24/2018 | 12/24/2018 | 12/24/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/7/2018 | 12/7/2018 | 12/7/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/22/2018 | 11/22/2018 | 11/23/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/7/2018 | 11/7/2018 | 11/7/2018 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/23/2018 | 10/23/2018 | 10/23/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/8/2018 | 10/8/2018 | 10/8/2018 | | PASS |
Michael Zawacki
|
|
|
Homeowner expects to have grass out front in the next two weeks, backyard will not be disturbed.
|
General Inspection | 9/21/2018 | 9/21/2018 | 9/21/2018 | | PASS |
Andy J. Long
|
|
|
|
General Inspection | 9/6/2018 | 9/6/2018 | 9/6/2018 | | PASS |
Michael Zawacki
|
|
|
No new outside work. Yard is bare, vegetative buffer before creek.
|
General Inspection | 8/22/2018 | 8/22/2018 | 8/22/2018 | | CANC |
Michael Zawacki
|
|
|
|
Complaint Inspection | 8/7/2018 | 8/7/2018 | 8/7/2018 | P | PASS |
Michael Zawacki
|
|
|
Work on running new underground power. No runoff issues to creek. Some retaining wall work.
|
General Inspection | 8/2/2018 | 8/2/2018 | 8/2/2018 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/18/2018 | 7/18/2018 | 7/18/2018 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 7/3/2018 | 7/3/2018 | 7/3/2018 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 6/18/2018 | 6/18/2018 | 6/18/2018 | | PASS |
Michael Zawacki
|
|
|
No new outside work.
|
General Inspection | 6/1/2018 | 6/1/2018 | 6/1/2018 | | PASS |
Michael Zawacki
|
|
|
Working on home. No new disturbances.
|
General Inspection | 5/17/2018 | 5/17/2018 | 5/17/2018 | | PASS |
Michael Zawacki
|
|
|
No new exterior work.
|
General Inspection | 5/2/2018 | 5/2/2018 | 5/2/2018 | | PASS |
Michael Zawacki
|
|
|
New owners focusing on interior and making house livable before dealing with yard. No changes and no issues.
|
General Inspection | 4/17/2018 | 4/17/2018 | 4/17/2018 | | PASS |
Michael Zawacki
|
|
|
No new work has begun.
|
General Inspection | 4/2/2018 | 4/2/2018 | 4/2/2018 | | PASS |
Michael Zawacki
|
|
|
Met with new owners. Will begin rehab soon.
|
General Inspection | 3/16/2018 | 3/16/2018 | 3/16/2018 | | PASS |
Michael Zawacki
|
|
|
Site is idle. For sale sign has come down. Will need to monitor so that new owners know requirements.
|
General Inspection | 3/1/2018 | 3/1/2018 | 3/1/2018 | | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 2/14/2018 | 2/14/2018 | 2/15/2018 | | PASS |
Michael Zawacki
|
|
|
Perimeter controls in place and trash cleaned up. House is for sale.
|
General Inspection | 1/30/2018 | 1/30/2018 | 1/30/2018 | | PASS |
Michael Zawacki
|
|
|
Trash has been removed. Wattle fixed around perimeter. Wash out container has been removed.
|
General Inspection | 1/15/2018 | 1/15/2018 | 1/16/2018 | | PASS |
Michael Zawacki
|
|
|
Wattle along front needs to be reinstalled.
|
General Inspection | 12/29/2017 | 12/29/2017 | 12/29/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/14/2017 | 12/14/2017 | 12/14/2017 | | PEND |
Michael Zawacki
|
|
|
WIP. Dirt has been pushed over wattle and into the road. Old washout container still on site.
|
General Inspection | 11/29/2017 | 11/29/2017 | 11/29/2017 | | PASS |
Michael Zawacki
|
|
|
No erosion or dirt issues. Workers will be hauling of trash and cleaning site.
|
General Inspection | 11/14/2017 | 11/14/2017 | 11/15/2017 | | CANC |
Andy J. Long
|
|
|
|
Random Inspection | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PASS |
Michael Zawacki
|
|
|
Talked to new GC who may take over.
|
General Inspection | 10/23/2017 | 10/23/2017 | 10/23/2017 | | FAIL |
Michael Zawacki
|
|
|
Permit not displayed. Concrete washout full and over flowing. Looks like no work occured since last inspection.
|
General Inspection | 10/6/2017 | 10/6/2017 | 10/10/2017 | | PEND |
Michael Zawacki
|
|
|
Washout is full and has overflowed, needs to be emptied or replaced. Perimeter controls intact. Building waste is piled on side of house, large dumpster and cleanup recommended.
|
General Inspection | 9/19/2017 | 9/21/2017 | 9/22/2017 | P | PASS |
Andy J. Long
|
|
|
WIP. Perimeter wattles installed and concrete washout has been utilized. No discharges or trackout. Permit posted in window.
Correction: - washout is full, need new washout for project completion.
|
General Inspection | 9/15/2017 | 9/15/2017 | 9/19/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/25/2017 | 8/31/2017 | 8/31/2017 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/25/2017 | 8/25/2017 | 8/25/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/10/2017 | 8/10/2017 | 8/14/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/26/2017 | 7/26/2017 | 7/26/2017 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 7/5/2017 | 7/5/2017 | 7/5/2017 | | PASS |
Andy J. Long
|
|
|
WIP, no trackout or discharges. Perimeter wattle installed to contain stockpiles in front yard.
|