Information based on query as of Thursday, May 9, 2024.
Permit Information
Permit NumberESC17-01360
StatusFinaled
Name JILL JENKINS
Site Address 7000 E COLUMBIA RD
Project Name 
Customer Number 
ePlanReviewNo
Description
(BONNEVILLE POINTE SUB #2) SWPPP with narrative and site map submitted meet City of Boise requirements.. Project has filed Construction General Permit NOI, tracking # IDR1000PF. Flat site, limited cut and fill so no GRD permit was required. Erosion and sediment controls include stabilized construction entrance (angular rock), SWPPP & permit sign posting, provide leakproof concrete washout and trash containments, and stay within clearing limits to preserve vegetation surrounding site. Install perimeter wattles along west and south sides of project. ESC site preparation inspection is required.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled11/15/201911/15/201911/15/2019PPASS
DetailsMichael Zawacki
One DI has truck parked on it. Owner travels alot and not around. HOA is supposed to notify RP when they get the truck moved.
Perimeter had trash cleaned. Any new garbage is from phase on north east perimeter.
General Inspection11/7/201911/7/201911/7/2019 PASS
DetailsMichael Zawacki
All exterior work on phase completed. DI protections still installed.
WIll final permit when RP has inlet protection removed, makes sure all trash cleaned, and does perimeter check outside area for wind blown trash.
General Inspection10/7/201910/7/201910/8/2019PPASS
DetailsAndy J. Long
All streets in sub have all homes complete except on Wagon's West. Storm drain sediment bags and concrete washout pan are still on site. Some windblown trash at dead end streets off Wagon's West
General Inspection9/16/20199/16/20199/16/2019 PASS
DetailsMichael Zawacki
Most homes completed. No major issues at site. Some trash is blown against fence by concrete washout.
General Inspection8/16/20198/16/20198/16/2019PFAIL
DetailsMichael Zawacki
check that area around washout is cleaned up (trash, spilled washout)
Poorly cleaned, sent pictures to rp.
She was told it was cleaned and will make some calls and be out here next week to follow up.
General Inspection8/12/20198/12/20198/12/2019 FAIL
DetailsAndy J. Long
Correction needed:

Maintenance and loose material clean up is needed around the concrete washout pan.

RP notified.
General Inspection7/10/20197/10/20197/10/2019PPART
DetailsMichael Zawacki
Landscapers tracking down wagons west pretty bad, picture sent to RP.
Today is scheduled inspection day and Jill will be out in a few hours.
General Inspection6/21/20196/21/20196/21/2019 CANC
DetailsAndy J. Long
General Inspection5/17/20195/21/20195/21/2019PPART
DetailsMichael Zawacki
Concrete washout has been relocated to dead end road.
Some gravel stored on Prosperity, few foundations that no framing has begun.
Only on site ESC issue caused by River Wood builders on Wagons West Ave.
Area to muddy to walk fence perimeter looking for trash.
General Inspection5/16/20195/16/20195/17/2019 CANC
DetailsAndy J. Long
General Inspection4/15/20194/15/20194/15/2019PFAIL
DetailsMichael Zawacki
RP is aware and already ordered sweeper and new washout.
Lot's of tracking on road, few trailers on site with muddy tires. Lot's of blown trash along northern perimeter and into open lands.
Eaglewood homes on prosperity has mini excevator on site dumping straight onto sidewalk, other homes with stored backfill without builder sign out front.
Large pile of landscape rock stored on Wagon Wheel.
Conference3/19/20193/20/20193/21/2019APEND
DetailsAndy J. Long
NOV to be sent to developer, ESC RP, and all homebuilders for

trash control
sweeping
limits of disturbance violations
Conference3/15/20193/18/20193/19/2019APEND
DetailsAndy J. Long
General Inspection3/13/20193/14/20193/15/2019PPEND
DetailsAndy J. Long
Follow up inspection
BMP Violation3/8/20193/11/20193/13/2019PPEND
DetailsAndy J. Long
corrections in progress. Follow up inspection scheduled
General Inspection3/7/20193/8/20193/8/2019AFAIL
DetailsAndy J. Long
Loose trash leaving subdivision limits in to surrounding areas. Backfill and equipment access occuring within the mutual easement shared between subdivision and Ada County. Developer must connect with Ada County to discuss use of the area. No backfill or extra material should be placed on the subdivision perimeter.

Corrections:
- trash pick around entire permeter within 50 meters of the fence line.
- sweep streets
- provide new construction entrance material for the designated washout.

Case pending. NOV to developer and all builders in sub regarding trash, accessing the easement, backfill placement, and concrete and other materal washouts.
General Inspection2/14/20192/14/20192/14/2019 CANC
DetailsAndy J. Long
Tracking Control1/11/20191/14/20191/15/2019PPASS
DetailsMichael Zawacki
Snowing at time of inspection.
Very large rock pad installed leading to concrete washout. Some areas where backfill is on sidewalk. Did not see any large piled of building waster laying around.
Some homes are sold and have residents.
General Inspection1/8/20191/8/20191/8/2019PFAIL
DetailsAndy J. Long
Corrections needed:

- concrete washout area needs new construction rock entrance and/or maintenance of existing entrance to prevent further trackout. Some minor trackout already occuring.
- one container is full to brim, spilling over. A new containment is needed. The other bin does not have a ramp(?)
- need to work with SFH homebuilders to do a trash pick up in the open areas. Lots of wind blown trash and debris in all open spaces between homes.



No trackout or discharges offsite. Stormdrains have sediment protection.
General Inspection12/24/201812/27/201812/28/2018PCANC
DetailsAndy J. Long
General Inspection12/24/201812/24/201812/24/2018 CANC
DetailsAndy J. Long
rescheduled
General Inspection11/22/201811/22/201811/23/2018 CANC
DetailsAndy J. Long
General Inspection10/22/201810/22/201810/22/2018 FAIL
DetailsMichael Zawacki
Lots of trackout and dirt on sidewalks throughout site. Washout has rock pad but still has lots of trackout. Site is windy and trash is being blown around.
General Inspection9/21/20189/21/20189/21/2018PPART
DetailsMichael Zawacki
Multiple homes under construction. Community BMPs installed, two washouts on site. Some wind blown trash around site. Some trackout and dirt accumulation in gutters.
General Inspection9/5/20189/5/20189/5/2018PPASS
DetailsMichael Zawacki
Multiple homes under construction. Community BMPs in place, central concrete washout in area. Some landscaping is complete. Homes have their own trash boxes, no garbage blowing around site.
BMP Violation8/9/20188/10/20188/10/2018APASS
DetailsAndy J. Long
Spilled concrete washout has been cleaned up as requested. Oils spill have had some asorbent material applied and swept up. Washout pans have been relocated to a parcel and have construction rock installed to keep down trackout.
BMP Violation8/7/20188/8/20188/9/2018PPEND
DetailsAndy J. Long
follow up to correction request

Compliance extended due to ongoing issues with concrete delivery crews improperly washing out.
BMP Violation8/6/20188/6/20188/6/2018PFAIL
DetailsAndy J. Long
concrete washout maintenance and clean up needed

Concrete washout pan is overfull and slurry spilled all over road in addition to oil leaks and spills around the washout.

48 hr correction notice:
- provide new washout pan. Re-locate to an open lot if possible and 50 ft or more distance from storm drain.
- clean up street and replace damaged sediment bags and gravel bag check dams.
General Inspection7/16/20187/16/20187/16/2018PPASS
DetailsAndy J. Long
Subdivision utilities, roads, curb/gutter, and sidewalks complete. Storm drains have sediment protection installed. Concrete washout pan provided for builders at west end of Prosperity. No wind blown dust observed at time of inspection. Irrigation lines being installed on common areas. Subdivision has multiple builders. First set of SFHs is now beginning, project permitted seperately.

No corrections requested.
General Inspection5/2/20185/2/20185/2/2018PPASS
DetailsAndy J. Long
WIP prepping road for paving. No fugitive dust, discharges, or other issues observed.
General Inspection4/6/20184/6/20184/6/2018PPASS
DetailsAndy J. Long
General Inspection12/21/201712/21/201712/21/2017PPASS
DetailsMichael Zawacki
Curtis clean sweep on site. Grading in process. No dust, roads are being cleaned.
General Inspection12/8/201712/8/201712/8/2017PFAIL
DetailsMichael Zawacki
Significant trackout on Wagons View Ave. Some also caused by neighboring development. Also lots of trackout onto Wagons West Ave.
Site Preparation12/8/201712/8/201712/8/2017PCANC
DetailsMichael Zawacki
Complaint Inspection11/8/201711/8/201711/8/2017APASS
DetailsMichael Zawacki
Grading. Survey has marked where streets will be layed out.
Random Inspection10/31/201710/31/201710/31/2017PPASS
DetailsMichael Zawacki
WIP. RP was on site installing wattles. Water truck being used to control dust. Construction entrance used and road is clean.
Site Preparation10/24/201710/24/201710/24/2017PPASS
DetailsMichael Zawacki
Clearing and grubbing in process. Water truck on site, contractor is hauling away trash dumped on site. Entrance constructed. Asked GC to make sure traffic flows correct way to avoid using exit without a rock pad.
Site Preparation10/12/201710/12/201710/12/2017PPEND
DetailsMichael Zawacki
This is on East side of road. Please note it has same address as project across the street. Hasn't begun.
Site Preparation10/12/201710/12/201710/12/2017PDONE
DetailsMichael Zawacki
Under progress.