Site Final | 7/21/2020 | 7/21/2020 | 7/21/2020 | P | PASS |
Andy J. Long
|
|
|
Reseeded hillsides on south side of Joplin are stabilized/vegetated. Wattles and silt fence along north side have become incorporated into road shoulder, removal would cause significant disturbance. Agreed with PW Inspector Gary that if a problem arises, the treatment plant facility crews will take care of it. No further ESC inspections required. ESC permit finaled.
|
General Inspection | 7/15/2020 | 7/15/2020 | 7/21/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/30/2020 | 6/30/2020 | 7/2/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/15/2020 | 6/15/2020 | 6/19/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/29/2020 | 5/29/2020 | 6/5/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/13/2020 | 5/14/2020 | 5/21/2020 | P | PASS |
Andy J. Long
|
|
|
|
General Inspection | 5/6/2020 | 5/6/2020 | 5/13/2020 | P | CANC |
Andy J. Long
|
|
|
check on issues around the storage unit place (may not be related to this project)
|
General Inspection | 4/22/2020 | 4/22/2020 | 4/23/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/7/2020 | 4/7/2020 | 4/7/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/23/2020 | 3/23/2020 | 3/23/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 | | PASS |
Michael Zawacki
|
|
|
Will continue to monitor revegetation.
|
General Inspection | 2/20/2020 | 2/20/2020 | 2/20/2020 | | PEND |
Andy J. Long
|
|
|
revegetation monitoring
|
General Inspection | 2/5/2020 | 2/5/2020 | 2/6/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/21/2020 | 1/21/2020 | 1/22/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/6/2020 | 1/6/2020 | 1/6/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/20/2019 | 12/20/2019 | 12/20/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/5/2019 | 12/5/2019 | 12/5/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/20/2019 | 11/20/2019 | 11/20/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 11/5/2019 | 11/5/2019 | 11/6/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 10/21/2019 | 10/21/2019 | 10/21/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 10/4/2019 | 10/4/2019 | 10/4/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/19/2019 | 9/19/2019 | 9/20/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 9/4/2019 | 9/4/2019 | 9/4/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 8/20/2019 | 8/20/2019 | 8/20/2019 | | PEND |
Michael Zawacki
|
|
|
Talked to public works inspector 8-19. Pavement has failed and will be redone.
|
Site Final | 8/2/2019 | 8/5/2019 | 8/5/2019 | A | NR |
Andy J. Long
|
|
|
Will continue to monitor revegetation. No corrections. Wattle and silt fence are still installed between Joplin and Thurmna Drain.
|
General Inspection | 8/2/2019 | 8/2/2019 | 8/2/2019 | | CANC |
Andy J. Long
|
|
|
rescheduled for site final
|
General Inspection | 7/18/2019 | 7/18/2019 | 7/18/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 7/3/2019 | 7/3/2019 | 7/5/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/18/2019 | 6/18/2019 | 6/18/2019 | | PASS |
Michael Zawacki
|
|
|
BMPs still installed. Good regrowth on hillside, no issues at site.
|
General Inspection | 6/3/2019 | 6/3/2019 | 6/3/2019 | | PASS |
Michael Zawacki
|
|
|
Good new vegetation growth, everything is stable. Silt fence and no bio-degradable BMPs will need to be removed.
|
General Inspection | 5/13/2019 | 5/13/2019 | 5/13/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 4/26/2019 | 4/26/2019 | 4/26/2019 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 4/11/2019 | 4/11/2019 | 4/11/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/22/2019 | 3/27/2019 | 3/27/2019 | A | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/22/2019 | 3/22/2019 | 3/22/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/7/2019 | 3/7/2019 | 3/7/2019 | | PASS |
Michael Zawacki
|
|
|
Silt fence and wattle still around replaced culvert. Wattles still around area of old construction entrance. Grass starting to grow on hillside protected wth blanket. BMPs will need to be removed eventually.
|
General Inspection | 2/15/2019 | 2/15/2019 | 2/15/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/30/2019 | 1/30/2019 | 1/30/2019 | | PASS |
Michael Zawacki
|
|
|
BMPs still in place, stabalization under way.
|
General Inspection | 12/27/2018 | 12/27/2018 | 12/27/2018 | | CANC |
Michael Zawacki
|
|
|
|
General Inspection | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Michael Zawacki
|
|
|
All work complete, BMPs still installed.
|
General Inspection | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | PASS |
Andy J. Long
|
|
|
Construction complete. Some temporary wattles are still installed around creek/canal crossings. Will continue to monitor the disturbed section of hillside next to Joplin road that has ECBs installed. ECBs are installed in correct direction and are stapled and staked to slope.
|
General Inspection | 9/28/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Michael Zawacki
|
|
|
Sewer line work complete. IMC on site prepping road for paving, new wattles installed where needed. Old sewer hasn't been filled yet.
|
General Inspection | 9/19/2018 | 9/19/2018 | 9/19/2018 | P | PASS |
Michael Zawacki
|
|
|
Last section of trunk being placed. Bypass is on. Paving is planned to begin next week, so is filling of old trunk. Stockpile will be used by sewer plant to build new road.
|
General Inspection | 9/4/2018 | 9/4/2018 | 9/4/2018 | P | PASS |
Michael Zawacki
|
|
|
Still dewatering trenches, no turbid discharge. Staging area has water applied, no dust. Stockpiles still on site. BMPs along road, only water is from dust control. Expected time to paving is four weeks.
|
General Inspection | 8/15/2018 | 8/16/2018 | 8/15/2018 | A | PASS |
Michael Zawacki
|
|
|
Creeks and ditch clean. BMPs are along road where dust control runoff may enter watereays. Creek culvert is completed. Still minor dewatering. Pumps are in place to soon bypass section of sewer.
|
General Inspection | 7/23/2018 | 8/3/2018 | 8/2/2018 | A | PASS |
Michael Zawacki
|
|
|
Wattle has been installed in requested areas. Currentli installing new culvert for canal. Water is being pumped around jobsite, very clean.
|
Conference | 7/19/2018 | 7/23/2018 | 7/23/2018 | A | PASS |
Michael Zawacki
|
|
|
Site walkthrough with foreman. Water leaving site was 6.5 NTU, water entering was 4.5 NTU. No plumes or turbidity observed while on site. Few area where new BMPs were requested, ditch crossing and roadside where there was some signs of rilling and previous runoff. Scheduled follow up inspection for 8-3.
|
General Inspection | 7/19/2018 | 7/19/2018 | 7/19/2018 | P | PASS |
Michael Zawacki
|
|
|
Trunk line is moving east down Joplin. Dewatering still active and discharge clear. Water truck on site keeping staging and work area dust free. Excavated fill is being brought to original work area for storage.
|
General Inspection | 6/21/2018 | 6/25/2018 | 6/25/2018 | A | PASS |
Michael Zawacki
|
|
|
Trunk line is nearly to Joplin. Well points installed along Joplin, not yet pumping. Materials and storage now on road. Water truck on site. No runoff or turbid discharge.
|
General Inspection | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Michael Zawacki
|
|
|
Currently dewatering back into neighbors pond, level has fallen about 3 feet. Saw a plume in canal that only lasted a few minutes, unable to determine orgin. Well points are installed going down road, no pumping yet. Old silt fence was left behind and is still working. No ESC issues.
|
General Inspection | 5/30/2018 | 5/30/2018 | 5/30/2018 | P | PART |
Michael Zawacki
|
|
|
Water at outlet was reading 50-150 NTU depending which side of outlet was tested, visible plume. Water below last hose was 10.5 NTU. Hoses were directed for overland flow while I was on site, no way to know for sure how long there was a high turbidity dfischarge. Corrective actions were taken and discharge was clearing up while on site.
|
General Inspection | 5/16/2018 | 5/16/2018 | 5/16/2018 | P | PASS |
Michael Zawacki
|
|
|
Site inspection and dewatering check. Checked water coming in at property boundry,13.7 ntu, water leaving site measured 18.2 NTU. Dewatering operation working well. Canal is currently diverted as trunk goes through main channel, upon completion it will be redirected back into main channel. No ESC issues at site.
|
General Inspection | 4/27/2018 | 4/30/2018 | 5/1/2018 | A | PASS |
Michael Zawacki
|
|
|
No turbid discharges fromn any of the well points. Excavation is down to main trunk line on north side of project. Site is free from issues.
|
General Inspection | 4/3/2018 | 4/12/2018 | 4/12/2018 | A | PASS |
Michael Zawacki
|
|
|
Checked on dewatering operation. Many operating well points throughout project. Water entering site measured at 9.82 and exits at 8.91 ntu. Dishcharge points are 7.79 and 0 .70 ntu.
|
Site Preparation | 4/2/2018 | 4/3/2018 | 4/3/2018 | A | PASS |
Andy J. Long
|
|
|
Site preparation inspection and walk through conducted at 11 AM. Meeting with Kevin w/ Whitaker Construction, Public Works Inspector Gary Cooper, and the ESC Division (Long & Zawacki)
City of Boise ESC Permit sign posted at entrance on Joplin. Heavy duty construction rock entrance has been ordered and will be installed before end of week. A silt fence perimeter was installed on the east side of the site entrance to protect Thurman MIll from any stormwater sheet flow from site. Fence is properly trenched in.
Thurman Mill ditch & drain channel was rerouted prior to irrigation water release. The bank topsoil of old ditch was preserved and spread along the banks of the new channel and should regrow. Water is now passing through the ditch as of today.
2 well points have been installed and are now dewatering. The high flow pump is deep (25ft) and was discharging clear water, an energy dissipator fabric was put on end of hose and hose is in grassy drainage ditch. 2nd pump was low flow and land applying turbid water to infiltrate. An additional berm to prevent sheet flow to the ditch leading to Thurman Mill was requested and installed during the inspection.
Turbidity samples were taken upstream from discharge point and ditch connection in Thurman Mill reading 31 NTU. Sample in ditch where high flow pump hose was discharging was 7 NTU, and the water downstream in Thurman Canal after the discharges joining was 26 NTU.
Approved for construction. Initial BMPs installed. Will check back after more dewatering wells are installed and construction entrance. Notified RP about fugitive dust control requirements.
|