Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection8/7/20208/7/20208/11/2020 PASS
DetailsMichael Zawacki
No new construction activity on foxgrove. Landscapers are tracking some dirt onto roads and sidewalks.
General Inspection7/23/20207/23/20207/24/2020 PASS
DetailsAndy J. Long
Foxgrove is clean. Storm drains protected, designated concrete washout facility with construction entrance. No corrections requested.
General Inspection7/8/20207/8/20207/8/2020 PASS
DetailsMichael Zawacki
No new homes or foundations started on Foxgrove. Site is overall clean, some dirt on road from landscape/sprinkler crew who is currently on site.
General Inspection6/23/20206/23/20206/23/2020 PART
DetailsMichael Zawacki
Sections of Foxgrove need sidewalk and gutter swept. Overall site was cleane dafter rain.
General Inspection6/8/20206/8/20206/8/2020 PASS
DetailsMichael Zawacki
Foxgrove is clean. Trash crew on site cleaning up. Laqndscapers were active, equipment sitting idle. No issues on phase.
General Inspection5/22/20205/22/20205/27/2020 PASS
DetailsAndy J. Long
Homes on Foxgrove in progress. BMPs installed., regular street sweeping scheduled. No corrections requested
General Inspection5/7/20205/7/20205/7/2020 PASS
DetailsMichael Zawacki
No new foundation work in phase. Some homes near top completed, all homes under construction are framed.
Some runoff on bottom of foxgrove, no large areas or major issues.
General Inspection4/22/20204/22/20204/23/2020 PASS
DetailsMichael Zawacki
Site is clean and stable. One home on Barber is excavating and has material close to road.
Most homes are completed or lots vacant, not much current activity in phase.
General Inspection4/3/20204/7/20204/15/2020PPASS
DetailsAndy J. Long
BMPs installed including washout facility and storm drain protection. Streets are swept once per week. Some trackout occuring at active sites, dry conditions.

No corrections requested.
General Inspection3/27/20203/31/20204/3/2020PCANC
DetailsAndy J. Long
General Inspection3/25/20203/25/20203/27/2020 CANC
DetailsAndy J. Long
rescheduled
General Inspection3/10/20203/10/20203/10/2020PPASS
DetailsAndy J. Long
No debris or material in road on Foxgrove. Road appears to be recently swept. Trash contained. Concrete washout pans being utilized, good construction entrance. Storm drains have sediment protection installed. RP on duty. No corrections at this time for Foxgrove (phase 3)
General Inspection3/3/20203/3/20203/3/2020 PART
DetailsMichael Zawacki
Foxgrove has been cleaned up. Still some dirty areas of street and sidewalk, no backfill or materials stored on roads or sidewalk.
Crew with trash trailer at site, they are cleaning trash that has blown off of work sites.
Some tracking up Trapper, no large chunks, more staining from red dirt. A few landscape crews on site.
Overall site isn't to bad, just needs a cleaning.
General Inspection2/17/20202/17/20202/18/2020 PART
DetailsMichael Zawacki
Foxgrove has issues. Few dirty lots in site. Having individuals at site clean their lots, notified Kyle.
Tracking Control1/29/20201/31/20202/3/2020AFAIL
DetailsMichael Zawacki
Foxgrove is still a mess.
General Inspection1/29/20201/29/20201/29/2020PFAIL
DetailsMichael Zawacki
Met with Kyle while at site. Had streets swept this morning. Crew doing backfill has already trashed road(6073 Foxgrove). Drove front end loader a few hundred yard down road to lad, tracking whole way. Backfill in front of home all over road and sidewalk.
Tracking Control1/22/20201/23/20201/23/2020APART
DetailsMichael Zawacki
Area was swept. Concrete crew decided to back trailer into mud. Let RP know.
Tracking Control1/16/20201/22/20201/22/2020AFAIL
DetailsMichael Zawacki
Met with Kyle at site. Area was never swept, supposed to be on way now. Scheduled follow up for 1-23. Will issue fine if not swept.
General Inspection1/16/20201/16/20201/16/2020 FAIL
DetailsMichael Zawacki
Excavator back on lots. Foxgrove and sidewalk need to be swept again.
Message sent to rp.
Follow up scheduled.
General Inspection1/1/20201/1/20201/2/2020 PART
DetailsMichael Zawacki
Some lots need to be cleaned. Sent lot and block numbers to Kyle.
General Inspection12/17/201912/17/201912/17/2019PFAIL
DetailsMichael Zawacki
Upper fox grove needs to be swept. Hillside needs repair where excavator was driven up.
Message sent to Rp.
General Inspection12/6/201912/6/201912/10/2019PPART
DetailsMichael Zawacki
Some dirt on road and sidewalk going down fox grove. Message sent to RP.
Conference11/27/201912/2/201912/6/2019PCANC
DetailsAndy J. Long
General Inspection11/27/201911/27/201912/4/2019 CANC
DetailsAndy J. Long
Conference11/5/201911/12/201911/12/2019APASS
DetailsAndy J. Long
11 AM site walk through with Syman and Hunter Homes

Phase 3 corrections complete. Conscrete washout area is in good condition. Hunter Homes onsite RPs (Kyle and Les) check capacity and conditions daily.

Perimeter control put on lot 9 block 2 as requested.

No new corrections requested. Approved.
General Inspection11/5/201911/5/201911/5/2019 CANC
DetailsAndy J. Long
General Inspection10/21/201910/21/201910/21/2019 PART
DetailsMichael Zawacki
Construction on 3 homes in phase. 2 rollpan washouts on site with nice gravel entrance.
Some dirt tracked onto road and sidewalk near top of phase., someone has been driving on vacant lot.
General Inspection10/4/201910/4/201910/9/2019 PART
DetailsAndy J. Long
Corrections needed:

- clean up dumped washout. Post notice about dumping on ground and service.
- sweep up trackout from retaining wall installation crew
- install perimeter sediment control on lot 9 block 2 in Harris north 3 (corner of Foxgrove and Hootowl)
General Inspection9/18/20199/18/20199/18/2019 FAIL
DetailsMichael Zawacki
Work on one home. Lots of trackout on road. RP notified.
General Inspection8/30/20198/30/20198/30/2019 PART
DetailsMichael Zawacki
No major issues.
Sections of development need streets and sidewalks swept at end of work day.
General Inspection8/15/20198/15/20198/15/2019 PART
DetailsMichael Zawacki
No home construction. Some stockpiling on lower lots. Some trackout where stockpiles are and equipment is parked.
General Inspection7/31/20197/31/20197/31/2019 PASS
DetailsMichael Zawacki
No work has begun on any lots, form trailer has been staged on road. Road and side walk have been swept.
Some large stockpiles on lower lots.
General Inspection7/16/20197/16/20197/17/2019PPART
DetailsAndy J. Long
Road is complete, storm drains have sediment protection. Lots in progress of terracing.

Correction request to install perimeter controls at the junction of Hootowl and Foxgrove.
General Inspection7/8/20197/9/20197/9/2019PPASS
DetailsMichael Zawacki
Material being hauled from area of next phase off of Barber. Site can use sweeping. No major issues.
General Inspection7/4/20197/4/20197/8/2019 CANC
DetailsAndy J. Long
General Inspection6/19/20196/19/20196/19/2019 PASS
DetailsMichael Zawacki
Sidewalks completed and road paved. No dirt leaving down hillside on back.
Sidewalks can be swept. Perimeter controls should be installed on lower sections of Fox Grove.
General Inspection5/29/20195/29/20196/3/2019PCANC
DetailsAndy J. Long
General Inspection5/21/20195/21/20195/21/2019PPASS
DetailsMichael Zawacki
Still needs paving. Runoff is following road, very little sediment on road.
General Inspection4/23/20194/23/20194/23/2019PPASS
DetailsMichael Zawacki
Crew on site guiding guide wires set up for curbs. Lots are terraced and cut below hill grade, water can't run off them. Some walls installed, may be taller than 4' in area, notified hillside engineer.
General Inspection4/9/20194/9/20194/10/2019PFAIL
DetailsMichael Zawacki
post rainfall
Trackout and mud coming from both upper and lower entrances. Site walk through already scheduled.
General Inspection1/22/20191/22/20191/22/2019PPART
DetailsAndy J. Long
post rainfall inspection

No trackout or sediment runoff to Hootowl. Need to repair the upper entrance or provided stabilized access or road mix to get equipment in and out
General Inspection1/8/20191/8/20191/9/2019PPART
DetailsMichael Zawacki
RP on site doing maintenance to rock entrance, trackout is coming from area.
Did walkthrough with Kyle and went over improvement and what needs cleaning.
General Inspection12/6/201812/6/201812/7/2018PPASS
DetailsMichael Zawacki
Work is above first steep grade. Road is rough and does not provide runoff a clear channel. Berms installed at bottom blocking access and acting as dam for any runoff. Site is mostly frozen, some freeze thaw happening.
Site Preparation11/26/201811/27/201811/27/2018APASS
DetailsAndy J. Long
9:15 AM pre-construction conference

Approved for construction. Utility and sewer trenching has now started by Schmidt Construction. Construction entrance to be installed at upper end of Foxgrove Street to prevent trackout. Material staged within work area so should not be too much in and out traffic. Trench will capture runoff during rain events, but will need to install check dams and other BMPs as they work their way through sub. Will follow next week to check on progress and temp. stabilization steps. Road and gutters will not be installed until Spring 2019