Permit Information
Permit NumberESC19-00584
StatusIssued
Name JASON JONES
Site Address 4560 E WARM SPRINGS AVE
Project NameDallas Harris Estates TH#11
Customer Number 
ePlanReviewNo
Description
Initial permit for rough grading and fill for DHE townhomes for phase 10-11. Infrastructure or utilities and stormwater ponds added December 2019. BMPs include staying within clearing limits, controlling trackout and fugtive dust, protect existing storm drains at access points. Developer/general contractor must ensure ESC requirements are met by all subcontractors, including joint-trench. Heavy duty 50 ft+ construction entrance required. Site preparation inspeciton is REQUIRED; dewatering inspection is REQUIRED
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/30/20207/30/20208/7/2020 CANC
DetailsAndy J. Long
General Inspection7/15/20207/15/20207/15/2020 PASS
DetailsMichael Zawacki
Crew on site paving roads. Sidewalk and curb work completed. No esc issues at site.
General Inspection6/30/20206/30/20206/30/2020PPASS
DetailsMichael Zawacki
WIP on multiple phases on different units, some completed.
Site is clean, no issues.
General Inspection6/23/20206/23/20206/23/2020 PASS
DetailsMichael Zawacki
No issues with townhomes. Some dirt on alleyway from new sub prep on roadbeds.
General Inspection6/8/20206/8/20206/9/2020 PASS
DetailsAndy J. Long
WIP. No trackout, no fugitive dust observed. No discharges occuring at time of inspection.

Approved
General Inspection5/22/20205/22/20205/22/2020 PASS
DetailsAndy J. Long
DI bags installed. Active projects by Black Rock have lined concrete washout.
General Inspection5/6/20205/6/20205/7/2020 PASS
DetailsMichael Zawacki
No dumped washout from town homes.
Graders on site, no blowing dust.
Some material for waterlined staged on site. No tracking, no issues.
BMP Violation4/20/20204/21/20204/21/2020ADONE
DetailsAndy J. Long
investigate dumped washout.

Unable to determine who washed out at end of Hope's Well. Will continue to work with Knife River and Black Rock to enforce use of concrete washout and decrease the amount of dumping/trash storage in Parkcenter townhome allies.

General Inspection4/13/20204/13/20204/13/2020PPASS
DetailsMichael Zawacki
No more pond dewatering. Finishing touches on ponds. Will get willows and hydroseeded, iron fence will be installed.
Safety fence on greenbelt has been wind damaged, Rex has a guy to repair it.
Contanimated water pond has been cleared to drain, pumping under road through hose and into middle pond.
Still have large stockpile of contanimated soil. Will get more plastic to move pile and expose. Contanimates are evaporative and need to be exposed.
Clean fill staged will be used to bring area around contanimate pond up to elevation.
In future there will be one more pond west of Barber, not in current phase.
General Inspection4/3/20204/3/20204/3/2020PPASS
DetailsMichael Zawacki
Work has begun on new western pond. Contanimated soil is stored seperately on visqueen. Spoke with geo engineer while on site. DEQ gave ok to pump new pond water into middle pond, contanimated soil was above water table.
Met with Rex, finishing up and cleaning around middle pond. Overflow still needs to be ran to eastern pond. Pump will be relocated to furthest west to pump in middle.
Warm Springs has been patched, will get swept and opened to traffic tonight.
Still hauling material to noth side.
General Inspection3/31/20203/31/20203/31/2020PPASS
DetailsMichael Zawacki
Warm Springs is closed.
No dewatering water is leaving site.
West pond being dewaterewd into east and fill brought to north side. Very large stockpile starting to accumulate on site.
Sewer work on nw side of project.
General Inspection3/26/20203/26/20203/26/2020PPASS
DetailsMichael Zawacki
Dewatering west pond into east pond. No water is leaving site on north side of road. Warm Springs is closed. Sewer lines across Warm Springs completed, no more excavation of contanimated dirt or dewatering water.
Still hauling fill material across to south side.
General Inspection3/23/20203/23/20203/23/2020PPASS
DetailsMichael Zawacki
No pond dewatering. East pond has been excavated to elevation, excavator still on site working sides for grade.
West pond will be getting dewatered into east pond.
Sewer line work going across warm springs. Easte end water is being pumped into cow pasture on north side of road.
West side is hitting contanimated water and soil. Soil is being seperated into own pile. Dirty water is being pumped into lined pond for holding.
General Inspection3/19/20203/19/20203/19/2020PFAIL
DetailsMichael Zawacki
Discharge was greater than 1000 NTU, would not read on meter, exceeded capacity.
Talked to both RP Jason and Foreman Rex.
Crews were supposed to turn off pumps before work, only shut one down. Rex immediately turned off second pump and flow slowed, no new water.
All dewatering is supposed to be pumped to west pond, still has pump running, there is no outlet.
Lots of discharge to Wahling Creek, no turbid water reached Barber bridge, hoping that all the vegetation has filtered it out.
Told Jason to log an illicit discharge in SWPPP and self report.
Rex will get all sediment out of settling area and not restrt the well point pumps.
Bypass line dewatering is beng pumped under road and into lined pond on north side of road.
General Inspection3/13/20203/13/20203/13/2020PPASS
DetailsMichael Zawacki
More contanimated soil and water found on west of site. Currently on hold for new excavation. They will need to bore under warm springs to get water into lined pond. DEQ has been notified.
General Inspection3/11/20203/11/20203/11/2020PPASS
DetailsAndy J. Long
WIP excavating stormwater ponds. Currently no offsite disharge because crew is working on stormwater vault at east end where water was discharging.

Well pumped water being held in the east pond currently. No outlet. No overflow, plenty of capacity.

Knife River RP Rex monitoring. Street sweeper unit circulating site. No fugitive dust plumes observed.

No corrections requested at this time.
General Inspection3/3/20203/3/20203/3/2020PPASS
DetailsMichael Zawacki
Discharge is 0.62 NTU.
Two well points in east pond on east side.
Will begin excavating this afternoon, waiting on flaggers for Warm Springs. West pond down to starting grade. WIP on installing storm water bypass line along greenbelt, want to gewt it installed before any water needs to be pumped into pond. Some dewatering for install, going into pond, not being discharged, very little flow.
Currently doing some work on north of warm springs. Grubbing on west and hauling to east for fill. Plan on using west for fill brought from pond. Some dust on one section of haul road.
Talked with Rex while on site.
General Inspection2/26/20202/26/20202/26/2020PPASS
DetailsMichael Zawacki
Water being discharged is .84 NTU. Still only one well point ready, plans on getting second pumping tomorrow. Will pump into pond retention until clear and add to water leaving site. Some ponding along pipeline fromm leaking seals. Will get repaired, county is concerned about water backing up into storm drain along Warm Springs, will add berm around sewer cap.
Hauling material out of west pond to north side of road, has sweeper runnuing and makes sure everything clean end of day.
Keeping NTU log on site.
General Inspection2/19/20202/21/20202/21/2020APASS
DetailsMichael Zawacki
Water leaving site is 3.16 NTU.
First well point done and pumping.
Met with Rex at site. Pump ran all night into pond, was switched to go to outflow this morning. Currently digging some holed so surface water goes into ground and can be pumped. Will see how well pump is working at drawing down level and adjust as needed.
Plan is to start at east and work west, will leapfrog well points as work progresses.
Jason Jones is delivering water monitoring equipoment for site.
Site Preparation2/18/20202/19/20202/19/2020PPASS
DetailsMichael Zawacki
Follow up scheduled for 2/21.
Excavation for well point has begun. Pumping water into west of pond. No water flowing off site.
General Inspection2/18/20202/18/20202/18/2020PPASS
DetailsMichael Zawacki
Met with Rex at site, plan is to begin well point tommorow.
East pond is down to starting grade. Plan is to bring it down another 15'. Well point is to be 18' below current grade. To begin east pond is split with earthen dam, will dewater into other side until depth reached and water is clear. Bypass pump is being hardlined in and will go through some chip for energy dissiapation and cleaning and then to ditch leading to wahling creek.
Current Boise River turbidity is at 1.85 NTU at launch steps at Barber Park upstream of site.
Follow up scheduled to see progress.
Currently doing some stripping on west pond to get it to starting grade. Plan is to dewater west pond into east pond once work begins on west pond and east pond is finished.
General Inspection2/11/20202/11/20202/11/2020PPASS
DetailsMichael Zawacki
Stormwater pond being shaped and excavated from west to east. No pumping of ground water. Any water that falls in pond area is now contained. Some rock check dams in ditch leading to creek, no water flowing. Crossing of Warm Springs is bad, sweeper parked but not being used. SIte is on verge of thaw and will get very muddy.
General Inspection1/27/20201/27/20201/27/2020PFAIL
DetailsAndy J. Long
Trackout at Hope's Well. Dumping dirt in very muddy area, construction entrance is compacted.

Request to extend rock to dumping zone or block off.
General Inspection1/9/20201/14/20201/14/2020PPASS
DetailsMichael Zawacki
1 excavator working on site. No tracking.
General Inspection12/13/20191/10/20201/9/2020ACANC
DetailsAndy J. Long
Conference1/8/20201/8/20201/8/2020PPEND
DetailsAndy J. Long
Discussion with Rex over trackout prevention and clean up

- no non-essential access to site or onsite employee parking
- getting PSI to have a sweeper on site or regular sweeping to better remove sediment that has built up in the gutters.
- will have two full length construction entrances and block off access to site where there is no entrance.

- request/reminder to notiify ESC divsion when dewatering for the stormwater ponds begins.
Tracking Control1/7/20201/8/20201/8/2020PFAIL
DetailsMichael Zawacki
Only good entrance off Hopes Well, still tracking to parkcenter. Dirt tracked into alleyways.
Dewatering for sewer into trench leading to ditch in field to south, all water being absorbed.
Tracking Control12/30/20191/2/20201/2/2020APEND
DetailsMichael Zawacki
More entrance rock being delivered and spread, sweeper running.
General Inspection12/13/201912/27/201912/30/2019AFAIL
DetailsMichael Zawacki
Sweeper is running.
Lots of trackout from hauling. Exit is compacted, needs to be improved.
Message and pictures sent to RP. Follow up scheduled.
Tracking Control12/19/201912/23/201912/24/2019PPART
DetailsMichael Zawacki
No trackout, no workers at site.
Eastern entrance has no rock. Middle and western entrance compacted and need new rock.
Do not know if they have made traffic plan.
Tracking Control12/19/201912/19/201912/19/2019PFAIL
DetailsAndy J. Long
Trackpads exiting north to Parkcenter Blvd from the area of fill placement need maintenance and additional rock, as well as traffic controls to make sure trucks are using the entrances and staying off muddy areas of site.

Notified RP Jason to coordinate with Rex at Knife River.

Follow up scheduled.

Conference12/18/201912/19/201912/19/2019APASS
DetailsAndy J. Long
2:30 PM

DHETH #11 site development and stormwater ponds meeting

Meeting complete. Will begin installing perimeter fencing and sediment controls in certain areas along Greenbelt. RP and site foreman to provide updated dewatering plan with well point info, discharge locations, turbidity monitoring log, and protocol for discharging clean water around the sediment treatment areas.

Any dewatering from the contaminated areas will be sent to the lined holding pond and then discharged into the sanitary sewer at low flow sewer times.
General Inspection12/13/201912/13/201912/13/2019PFAIL
DetailsMichael Zawacki
Equipment is being staged on site. Construction entrances installed. Lots of stockpiled soil on south edge. No current grading activity.
Lots of trackout headed east bound from equipment deliveries and fill being brought on site.
Started running sweeper whil I was still on site.
General Inspection9/26/20199/26/20199/26/2019PPASS
DetailsMichael Zawacki
No activity on phase. Large exposed area, no blowing dust.
Tracking Control8/8/20198/8/20198/8/2019PPASS
DetailsMichael Zawacki
No trackjout at site.
Dewatering on far east of site, is being overland discharged into some trees and a field, no offsite discharge.
No dust issues.
DI bags will soon need to be cleaned.
Tracking Control7/18/20197/19/20197/22/2019APASS
DetailsMichael Zawacki
No workers at site. No dust at time of inspection. If there was any trackout it has all been cleaned.
General Inspection7/3/20197/3/20197/3/2019PPASS
DetailsMichael Zawacki
Grding looks completed. No workers or equipment at site. Piles of backfill stored along southern edge of site. No blowing dust or trackout.
Site Preparation6/13/20196/14/20196/14/2019APASS
DetailsAndy J. Long
Jason Phone #: ###-####
General Inspection6/12/20196/12/20196/12/2019PPASS
DetailsMichael Zawacki
Met with Rex the foreman on site. Currently stripping top layer of soil. Site is dry, plan is to bring in fill and raise elevation while dry. Plan on bringing fill in next few days. Area is being watched for dust, using water truck on site as well as site next door. Site backs in to agricultural land, about halfway to warm springs bypass. No current excavations or dewatering.