Permit Information
Permit NumberFIR18-00633
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2419 W FAIRVIEW AVE
Project NameAdare Manor Apartment
Customer Number 
ePlanReviewYes
Description
***INSPECTOR SEE NOTE ON PLAN MOD DRAWING FP-9 AND FP-10***MAS**Shilo will attach onto a 6" UG and run a 6" feed to a floor control valve standpipe. Shilo will install 4 wet systems in a 148,045 FT² 4 story combustible apartment complex. There are 4 stair towers, each with a standpipe. There is a building separation requiring an addition hose valve on each floor at the separation. Plan Mod #2 Approved: Additional 90's used to pipe around mechanical equipment. **MAS**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/13/20199/13/20199/13/2019PPASS
DetailsJim Page
Final fire sprinkler inspection complete.

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/10/20199/12/20199/12/2019APART
DetailsJim Page
Fire alarm associated devices have been tested, still need to perform walk through.

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/10/20199/11/20199/10/2019ACANC
DetailsJim Page
Kenny Caldwell is the contact for this final inspection. Thank you for your help. We appreciate it. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection9/6/20199/9/20199/9/2019AFAIL
DetailsJim Page
Could not test fire alarm associated items with risers due to floor adhesive in stairwell tower, could not access risers.

Kenny Caldwell is the contact for this final inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection9/5/20199/6/20199/6/2019PCANC
DetailsJim Page
Fire alarm system was not ready to test devices, inspection will need to be rescheduled, this request is cancelled.

Kenny Caldwell is the contact for this final inspection. We appreciate your help. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection8/29/20198/30/20198/30/2019ACANC
DetailsJim Page
Could not test fire alarm associated devices, fire alarms not ready, this requst is cancelled per conversation with point of contact.

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection8/28/20198/29/20198/29/2019PCANC
DetailsJim Page
Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in8/28/20198/28/20198/28/2019PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping on level 1 complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro8/27/20198/28/20198/28/2019PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping on level 1 witnessed, no pressure loss was observed.

Kenny Caldwell is the contact. He would like this inspection to be a TCO as well as a hydro for the 1st floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Conference8/22/20198/22/20198/22/2019PDONE
DetailsJim Page
Fire sprinkler conference complete, discussed possible issue before TCO, items noted are already on the job site foreman list, no major issues noted.
INSP-Final Inspection8/20/20198/22/20198/22/2019PCANC
DetailsJim Page
Request was for a conference to discuss final inspection items, this request is cancelled.

Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in7/22/20197/23/20197/23/2019APART
DetailsJim Page
Rough to cover inspection for trash shute/shute acces sprinkler piping complete, approved for cover.

Kenny Caldwell is the contact. This is only to be a partial rough-in. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/26/20196/28/20196/28/2019APART
DetailsJim Page
Hydrostatic test for levels 2, 3, 4 and standpipe witnessed, no pressure loss observed, level 1 is the last hydro requirement.

Kenny Caldwell is the contact for this full building hydro. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/26/20196/28/20196/28/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in remaining apartments on level 1 complete, approved for cover.

Kenny Caldwell is the contact for this partial rough-in for the 1st floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in6/7/20196/10/20196/10/2019PPART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 1 compete, notated city approved drawings with yellow highlighter/red ink areas approved for cover.

Kenny Caldwell is the contact for this RTC inspection. He is needing it on the 1st Floor. We appreciate your help. Thank you! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/14/20195/15/20195/15/2019PPART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 1 compete, notated city approved drawings with yellow highlighter/red ink areas approved for cover.

Kenny Caldwell is the contact. This rough-in is for the 1st floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/24/20194/25/20194/25/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler pipng partially complete, notated city approved drawings with pink and yellow highlighters areas approved for cover.

Kenny Caldwell is the contact. This rough-in is only for the 3rd and 4th floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/10/20194/11/20194/11/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in apartment units east of elevator lobby level 4 complete, apartment units east of elevator lobby on level 4 approved for cover. As stated before, need to have a jobsite set of approved drawings for proper documentation, if a current reviewed jobsite set of approved drawings is not provided then no inspection will be performed.

Kenny Caldwell is the contact for this inspection. He is requesting it for the 2nd Floor. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/9/20194/10/20194/10/2019PCANC
DetailsJim Page
Rescheduled for 11APR2019 per conversation with point of contact, this request is cancelled.

Kenny Caldwell is the contact for this inspection. He is requesting it for the 2nd Floor. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/4/20194/5/20194/5/2019APART
DetailsJim Page
Rough to cover inspection for level 4 east wing rooms complete, inspected areas approved for cover. Will notate city approved drawings when city approved job site drawing packet is provided instead of a single sheet blue print with 1 section.

Kenny Caldwell is the contact for this rough- in / Hydro. He is requesting a partial on the 4th Floor. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/3/20194/4/20194/4/2019ACANC
DetailsJim Page
Inspection request cancelled per conversarion with point of contact, baffles to prevent cold soldering on sidewalls protecting exterior projections.

Kenny Caldwell is the contact. He requests this to be a partial rough/hydro for the 4th floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro4/1/20194/2/20194/2/2019AFAIL
DetailsJim Page
Attic heads do not match what was submitted to the city. Cover is not approved for any area on level 3 until head spacing for attic heads is figured out and city approved drawings reflect what is installed.

Kenny Caldwell is the contact. This inspection is requested to be a partial rough-in/hydro for the 4th floor. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro3/25/20193/26/20193/26/2019APART
DetailsJim Page
Previously noted items in rooms on level 1, southeast wing have been corrected, southeast rooms approved for cover, total of 10.

This rough-in/hydro is for the 1st floor east side. The contact is Kenny Caldwell. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro3/22/20193/25/20193/25/2019PFAIL
DetailsJim Page
Prints show no more than 1 head off of 1 inch, dry sidewalls on level 1 have more than 1 head off of 1 inch, does not match city approved drawings. Add surge clips next to drops or provide longer rods to prevent surge.

Kenny Caldwell is the contact. He''d like this to be a partial rough-in/hydro for the 1st floor.
Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro3/8/20193/11/20193/11/2019PPART
DetailsJim Page
Hydrostatic test witnessed for levels 2 and 3 east of elevator loby, no pressure loss observed. Reamining piping to include standpipe on levels 2 and 3 to be tested at a later date.

This is for the 2nd;3rd Floors. Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro3/8/20193/11/20193/8/2019PCANC
DetailsJim Page
Kenny Caldwell is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro3/5/20193/8/20193/8/2019PPART
DetailsJim Page
Only level 3, east side of elevators inspected today, overhead fire sprinkler piping in area D and part of C, east side of elevators on level 3 approved for cover. Building temperature could not be maintained above 40 degrees at time of inspection, no hydrostatic test was performed.

Kenny Caldwell is the contact. This RTC/Hydro is for the 2nd ; 3rd floors. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in12/13/201812/17/201812/17/2018ADONE
DetailsJim Page
Request was for a conference, all combustible concealed spaces that do not meet the requirements in NFPA 13, 2016 edition, will require sprinkler coverage.

Jim Baker is requesting a consultation for sprinklers in the attic. He would appreciate your help. Thank you. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus