General Inspection | 8/4/2020 | 8/4/2020 | 8/6/2020 | | PASS |
Michael Zawacki
|
|
|
Crew working on stem walls for homes that will be part of retaining wall. Wahout being used, one driver had bad aim.
|
General Inspection | 7/20/2020 | 7/20/2020 | 7/20/2020 | | FAIL |
Michael Zawacki
|
|
|
3 foundations started on lower section, 3 piles of dumped washout. Unable to find permits for home, researching further.
|
General Inspection | 7/3/2020 | 7/3/2020 | 7/6/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/18/2020 | 6/18/2020 | 6/18/2020 | P | PASS |
Michael Zawacki
|
|
|
Water is flowing to onsite seepage beds. No erosion issues.
|
General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | PASS |
Michael Zawacki
|
|
|
No issues from rainfall. Looks like it stayed on tiers and seeped in. Road is clean. AME electric crew on site.
|
General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 5/21/2020 | 5/22/2020 | 5/26/2020 | P | PASS |
Michael Zawacki
|
|
|
No new activity. Stockpile is stable. No rilling to bottom of hill, silt fence still in place. Some vegetation growing on hillside
|
General Inspection | 5/19/2020 | 5/19/2020 | 5/19/2020 | | PASS |
Michael Zawacki
|
|
|
No new activity, no issues.
|
Conference | 5/1/2020 | 5/4/2020 | 5/6/2020 | P | DONE |
Andy J. Long
|
|
|
Request to finish grading on slope below lower road ASAP so it may be hydroseeded before end of May
RP to notify City of schedule
|
General Inspection | 5/1/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Andy J. Long
|
|
|
No BMP failures, significant erosion, or other problems occured after storm 4/30.
Need to finish revegetation ASAP before it gets too hot and dry. Follow up scheduled to discuss with RP
|
General Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Michael Zawacki
|
|
|
No workers on site. No esc issues, stockpile is still tackified. No issues on lower sections or hillside.
|
General Inspection | 4/9/2020 | 4/9/2020 | 4/10/2020 | | PASS |
Michael Zawacki
|
|
|
Upper ring road around stockpile paved. Curb, gutters, and inlets installed. New inlets have DI bags installed. No workers on site. No longer an entrance on Federal Way.
|
General Inspection | 3/25/2020 | 3/25/2020 | 3/25/2020 | | PASS |
Michael Zawacki
|
|
|
Some curbing and gutter installed. ooks likre they used washout, already tore it out with excavator., Crew on site with paving eqipment warming up, looks like they are waiting for delivery from hot plant.
|
General Inspection | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Michael Zawacki
|
|
|
Grader on site getting road bed to elevation to begin curbing. Paving is a while off, some foundations need to be completed before road can be put in due to grade. No esc issues at site. Stockpile is s till stable.
|
General Inspection | 3/6/2020 | 3/6/2020 | 3/6/2020 | | PASS |
Andy J. Long
|
|
|
WIP on grading and site infrastructure. No trackout, silt fence perimeter installed, and stockpile is tackified. No corrections at this time.
|
General Inspection | 2/20/2020 | 2/20/2020 | 2/20/2020 | P | PASS |
Michael Zawacki
|
|
|
Utility work at site. Site is clean and dry, berm has bee repaired. No issues.
|
General Inspection | 2/6/2020 | 2/6/2020 | 2/10/2020 | P | PART |
Michael Zawacki
|
|
|
Track utilities on site. Fence has held up good, no damaged areas. Site is tiered, no water can make it straight from top to bottom. One small rill forming by Amity entrance, looks like berm was breached. Talked to foreman on site said he will put in a new berm, area will be getting a wall. Entrance is a little short.
|
General Inspection | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | PART |
Andy J. Long
|
|
|
No trackout. No offsite discharges to MS4. Stockpile has been temporarily tackified. Post rainfall inspection conducted this morning by Granite.
Corrections needed: - need to repare areas of silt fence that are no longer trenched and conduct maintenance One section has let mud slip under. Clean up and reinstall requested - noted in site's self inspection as well. - up slope controls needed where water was able to run down slope - will discuss with RP for possible correction alternatives. Appears a diversion berm was graded on the lower terrace this morning.
Follow up pending
|
General Inspection | 1/27/2020 | 1/27/2020 | 1/27/2020 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/15/2020 | 1/15/2020 | 1/15/2020 | | PASS |
Michael Zawacki
|
|
|
snow covered
|
General Inspection | 12/31/2019 | 12/31/2019 | 12/31/2019 | | PASS |
Michael Zawacki
|
|
|
No workers on site. Giant stockpile has been tackified, steep hill along amity also tackified.
|
Conference | 12/13/2019 | 12/16/2019 | 12/17/2019 | P | DONE |
Andy J. Long
|
|
|
Notified RP of corrections needed: - construction entrance rock is round, not angular and more angular rock should be installed. - stockpile is still unstabilized, needs to be used, stabilized with temporary tackifier, or put down slope silt fence around it
|
General Inspection | 12/12/2019 | 12/12/2019 | 12/13/2019 | P | PART |
Andy J. Long
|
|
|
No trackout, no hillside erosion observed. Downslope silt fence is in good condition, east end of site slope has been tacified.
Corrections needed: - install angular rock construction entrance. Extend lenght. - provide temporary stabilization or sediment control perimeter around stockpile.
Follow up scheduled.
|
General Inspection | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | PART |
Michael Zawacki
|
|
|
Giant pile of backfill hasn't been moved. Area has been graded, graders on site. Future roads are lower than surrounding areas, acting as berm. No tracking at site.
|
General Inspection | 11/25/2019 | 11/25/2019 | 11/25/2019 | P | DONE |
Michael Zawacki
|
|
|
No winterizing has begun, none of the suggested improvements done. Pipe creww on site still have 1000' feet. They hope to be done before thanksgiving.
|
Conference | 11/13/2019 | 11/14/2019 | 11/18/2019 | P | DONE |
Andy J. Long
|
|
|
Site walk through to plan for winterization and site stabilization.
Corrections needed: - new rock construction entrances for winter access - site will use some of the stockpile on site, reduce its height and have it sprayed with tacifier & mulch. May need additional perimeter sediment control around the pile. - need to apply hydroseed/mulch mix to the finished slope on the east side of site as well as the rest of the slope areas within site (not all of it is tracked yet) - Will put road mix down on roads and utilize the sites terraces to retain water on site. May open up access to the site's large seepage swale. - install berms at top of any slopes to prevent runoff from going over disturbed slopes.
Follow up at site at end of week as work progresses.
|
General Inspection | 11/7/2019 | 11/7/2019 | 11/7/2019 | P | FAIL |
Michael Zawacki
|
|
|
Mountain of backfill has been idle for greater than two weeks with no temporary stabalization. No slope interupting BMPs on site. Only installed BMP is silt fence along lower perimeter. No workers at site, sewer line material staged at site.
|
Complaint Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | PASS |
Andy J. Long
|
|
|
dust complaint
No dust at time of inspection. Spoke with onsite crew manager Alfredo about keeping dust down. Water truck is coming to site so work can continue on the lower swale adjacent to homes below. No major activity, finishing up sewer work,
No trackout or discharges.Silt fence BMP installed at bottom of site. Graded slope has been tracked:
Corrections: - stockpile has been on site for over a month, much of it is inactive and past stabillization deadline. - need to have graded areas hydroseeded before end of November
|
General Inspection | 10/11/2019 | 10/11/2019 | 10/14/2019 | | PASS |
Andy J. Long
|
|
|
No trackout. Cut slopes at grade have been tracked. No wind blown dust observed, site inactive at time of inspection.
Reminder of stockpile stabilization and/or removal
|
General Inspection | 9/26/2019 | 9/26/2019 | 9/27/2019 | P | PASS |
Michael Zawacki
|
|
|
Dozer and front end loader operating on site. Area has been sprayed with water and is pretty saturated, water truck was not on site at time of inspection. No dust in area being scraped, some from front end loader after it dumped onto stockpile. Wind is blowing onto Amity. No trackout from site.
|
Complaint Inspection | 9/13/2019 | 9/13/2019 | 9/16/2019 | P | PASS |
Michael Zawacki
|
|
|
Talked to RP about dust. Water truck back to operating on site. No dust at time of inspection. Neighbor said lots was blown in from weekend winds.
|
General Inspection | 9/9/2019 | 9/9/2019 | 9/9/2019 | P | PASS |
Michael Zawacki
|
|
|
Post rainfall inspection. No activity on site. Site is terraced, all water flowed to bottom. Seepage bed is open, looks like all water was obsorbed.
|
General Inspection | 9/3/2019 | 9/3/2019 | 9/3/2019 | | PASS |
Michael Zawacki
|
|
|
WIP on lower area, looks like excavation for seepage bed, lots of drain rock on site and being delivered. Rock entrances installed, haul roads have been watered. Non active areas of site are crusted, no blowing dust.
|
Site Preparation | 8/16/2019 | 8/19/2019 | 8/20/2019 | A | PASS |
Andy J. Long
|
|
|
Corrections completed as requested:
- stabilized construction entrance. - full time water truck working site. - sweeping rocks out of bike lane after each truck exit to Federal Way. - SWPPP info posted, Boise ESC permit is posted - Re-inspection fee paid, site preparation inspection complete.
Will need to watch the drainage areas on the east-northeast perimeter for addition downslope perimeter sediment control. Also need to check that runoff from Amity Road will not flow over the newly disturbed slope.
Correction request: - install sediment protection on storm drain on Federal Way, just west of the construction entrance.
|
BMP Violation | 8/12/2019 | 8/13/2019 | 8/15/2019 | P | FAIL |
Andy J. Long
|
|
|
Dust issues have been addressed, full time water truck on site, construction entrance installed. Some minor trackout observed. City of Boise ESC permit not yet posted.
Notified RP that they need to call in for Re-inspection and pay fee.
|
Complaint Inspection | 8/12/2019 | 8/12/2019 | 8/12/2019 | P | FAIL |
Andy J. Long
|
|
|
dust complaints received
- rough grading/grubbing in progress, no dust truck on site at time of inspection. Foreman states dust truck is on a circulating route and was previously at site. Dust plumes are leaving site and the light wind conditions blowing it into the neighborhood below. - no permit sign, no construction entrance, no site preparation inspection requested.
Project manager Jerry notified to halt work until dust control onsite, which he did.
Corrections: - have full time dust control water truck during initial grading/grubbing and dust generating activities. - Install construction entrance, construction entrance and schedule site preparation inspection with ESC division.
|