Information based on query as of Thursday, May 9, 2024.
Permit Information
Permit NumberESC18-00171
StatusFinaled
Name CLAYTON BROOKS
Site Address 150 E SHERMAN ST
Project NameJones Residence
Customer Number 
ePlanReviewNo
Description
Per Attached ESC Conditions
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Site Final10/25/201910/29/201910/29/2019PPASS
DetailsMichael Zawacki
I removed DI bags at bottom of street.
General Inspection10/25/201910/25/201910/25/2019 CANC
DetailsAndy J. Long
rescheduled
General Inspection10/10/201910/10/201910/11/2019 CANC
DetailsAndy J. Long
General Inspection9/25/20199/25/20199/25/2019 CANC
DetailsAndy J. Long
General Inspection9/10/20199/10/20199/10/2019 PASS
DetailsMichael Zawacki
No issues after rain event.
General Inspection8/26/20198/26/20198/26/2019 PASS
DetailsMichael Zawacki
Revegetation in progress, currently prtty sparse.
General Inspection8/9/20198/9/20198/9/2019 PASS
DetailsMichael Zawacki
Regrowth in progress.
General Inspection7/25/20197/25/20197/25/2019 PASS
DetailsAndy J. Long
No changes, slope is vegetation. Storm drain still have sediment protection that needs to be removed.
General Inspection7/10/20197/10/20197/10/2019 PASS
DetailsMichael Zawacki
Revegetation in process, no issues with hillside.
Inlet protection still installed at intersection of sherman & Mockbee.
General Inspection6/25/20196/25/20196/25/2019 CANC
DetailsAndy J. Long
General Inspection6/10/20196/10/20196/10/2019PPASS
DetailsAndy J. Long
Site is revegetating. Roof top gutters installed, landscaping in progress. Slope has been hydroseeded and has supplemental irrigation.

Ok to remove silt fence. Also need to remove temporary sediment bags at bottom of Sherman @ Mockbee
General Inspection5/30/20195/30/20195/30/2019 PASS
DetailsMichael Zawacki
Some mixed growth on hillside. No major rilling or erosion issues. Silt fence installed still, some areas of sediment build up.
General Inspection5/14/20195/14/20195/16/2019 PASS
DetailsAndy J. Long
BMPS still istalled. HOme is now occupied but only temporarily stabilized with hydromulch. No corrections at this time, but all temporary BMPs will need to be removed before site final.
General Inspection4/29/20194/29/20194/30/2019 PASS
DetailsMichael Zawacki
Driveway paved and lot hydroseeded. Neighborhood storm systems need to be cleaned before permit closed.
General Inspection4/8/20194/12/20194/11/2019PPASS
DetailsMichael Zawacki
Working on getting everyrthing finished. Mini excavator on site, still need landscaping.
General Inspection4/2/20194/5/20194/8/2019PDONE
DetailsAndy J. Long
follow up inspection

Discussed corrections issued on previous inspection. Landscaping to occur this week. Will address erosion and outfall energy dissipation request. Change out DI bags.
General Inspection4/2/20194/2/20194/2/2019 FAIL
DetailsAndy J. Long
corrections needed:

- fix downed section of silt fence.
- address erosion occuring above the water storage vault
- install energy dissipation at the roof drain outlet next to driveway.
- plan for landscaping and stabilization.
- change out DI bags.
General Inspection3/18/20193/18/20193/18/2019 PASS
DetailsMichael Zawacki
Fill material has been brought in for driveway. Some topsoil put onto hill. Wattles needs repair, spoke with GC on site.
General Inspection3/1/20193/1/20193/1/2019 PASS
DetailsMichael Zawacki
Met on site with builder. No ESC issues. Some concern from home above starting wall repair and attempting to access through his lot.
General Inspection2/13/20192/13/20192/13/2019 PASS
DetailsMichael Zawacki
No new rilling, no runoff from site.
General Inspection1/28/20191/28/20191/28/2019 PASS
DetailsMichael Zawacki
Met with GC while on site. Rilling in rear has been fixed, wattles installed to break up slope. Lower silt fence is under load. Hillside still exposed, plan to hydroseed soon. Area around driveway entrance is going to be redone and cleaned.
General Inspection1/11/20191/11/20191/11/2019 PART
DetailsMichael Zawacki
Stucco washout on site and being used.
Section of silt fence at upper end removed for walking path onto job site, path has filled in section of rock channell and needs to be fixed.
Rill forming behind house and running downhill the length of property.
General Inspection12/24/201812/27/201812/27/2018APASS
DetailsMichael Zawacki
Silt fence still in place and working. Nothing leaving site.
General Inspection12/21/201812/24/201812/24/2018ACANC
DetailsAndy J. Long
General Inspection12/20/201812/20/201812/21/2018 CANC
DetailsAndy J. Long
rescheduled for 12/24
General Inspection12/5/201812/5/201812/12/2018 PASS
DetailsAndy J. Long
WIP on exterior finish. No trackout or muddy runoff observed. Silt fence perimeter is in good condition. No corrections at this time.

Note: need to install rip rap at end of blue drain pipe from lot.
General Inspection11/2/201811/2/201811/8/2018 PASS
DetailsAndy J. Long
Landscaping near completion, driveway and drainage pockets installed. No trackout or sediment runoff observed. No corrections requested.
General Inspection10/9/201810/9/201810/9/2018PPASS
DetailsMichael Zawacki
Silt fence perimeter intact. Flow is all concentrated in corner, no failures. Builder called Syman to check BMPs and install more to protect corner. Will monitor fence.
General Inspection10/2/201810/3/201810/4/2018APASS
DetailsAndy J. Long
Silt fence perimeter installed. Slopes are bare but tracked and compacted. No runoff down Sherman during rainfall. No corrections requested.
General Inspection8/23/20188/23/20188/23/2018PPASS
DetailsMichael Zawacki
Site is clean. Silt fence still along perimeter. Hillside around home is all exposed, no BMPs.
General Inspection6/26/20186/26/20186/26/2018PPEND
DetailsAndy J. Long
Sediment and sand accumulated by storm drain inlet at Sherman & Mockbee has been cleaned as requested.

WIP connecting utilities at site. Hillside has been graded fresh. After utility work site should have hillside erosion controls installed and check that runoff will not from site over this distrubed site.
General Inspection6/20/20186/20/20186/21/2018PPART
DetailsAndy J. Long
Silt fence perimeter working well to contain sediment. Vegetation on slope below excavation has been preserved. Permit sign posted.

Evidence of trackout and sediment runoff from access drive in combination with adjacent site.

Correction:
- sweep up accumulated sediment around inlet at bottom of hill. Coordinate with adjacent project RP.
- install runoff controls on driveway between home site and where joining other homes driveway.

Notified GC Noah
General Inspection6/6/20186/6/20186/6/2018PPASS
DetailsMichael Zawacki
WIP on forms for foundation. Site is contained.
Random Inspection5/31/20185/31/20185/31/2018PPASS
DetailsMichael Zawacki
Silt fence held all water and sediment. No issues on site. Foundation work in progress, washout on site.
General Inspection4/24/20185/4/20185/4/2018APASS
DetailsAndy J. Long
WIP on excavation for foundation and bulding pad. BMPs installed, permit sign posted at entrance. Vegetaation around disturbance has been preserved so far.
Site Preparation4/23/20184/24/20184/24/2018APASS
DetailsAndy J. Long
Noah Phone #: ###-####

Permit sign posted. Rock construction entrance installed with lining. Silt fence sediment controls installed correctly around perimeter. GC to have wattles installed along contour after grading is completed. Efforts will be taken to preserve sagebrush within clearing limits. Storm drain sediment protection installed at Sherman and Mockbee, requested that this be maintained regularly and removed at end of project.

Concrete washout pan to be used for foundation work.

Approved for construction.