General Inspection | 8/3/2020 | 8/3/2020 | 8/3/2020 | | PASS |
Michael Zawacki
|
|
|
No activity. Lot still has storage container and some materials.
|
General Inspection | 7/17/2020 | 7/17/2020 | 7/17/2020 | | PASS |
Michael Zawacki
|
|
|
No new activity, debris has been hauled away.
|
General Inspection | 7/2/2020 | 7/2/2020 | 7/2/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Michael Zawacki
|
|
|
No dirt flowing off site, some cones added to try to keep people off site.
|
General Inspection | 6/10/2020 | 6/10/2020 | 6/10/2020 | | FAIL |
Michael Zawacki
|
|
|
Requested corrections haven't been made. Wattle not fixed, still possible to drive onto lot.
|
General Inspection | 5/26/2020 | 5/26/2020 | 5/26/2020 | | PART |
Michael Zawacki
|
|
|
Wattle needs repair/ proper installation. People have drove onto lot, looks like they dumped landscape waste. Andy has already contacted RP about site.
|
General Inspection | 5/11/2020 | 5/11/2020 | 5/19/2020 | | PART |
Andy J. Long
|
|
|
No activity.
Correction request to Roth Homes to do maintenance on wattles that have been driven over. Recommend silt fence.
Notified Chris Roth and Brett Rankin with Roth
|
General Inspection | 4/24/2020 | 4/24/2020 | 4/30/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 4/9/2020 | 4/9/2020 | 4/9/2020 | | PASS |
Michael Zawacki
|
|
|
No new activity.
|
General Inspection | 3/25/2020 | 3/25/2020 | 3/25/2020 | | PASS |
Michael Zawacki
|
|
|
No activity, bmps still in place. Heard rumor house won't resume until other 2 have sold.
|
General Inspection | 3/5/2020 | 3/10/2020 | 3/17/2020 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 3/5/2020 | 3/5/2020 | 3/5/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 2/19/2020 | 2/19/2020 | 2/19/2020 | | CANC |
Andy J. Long
|
|
|
site is inactive
|
General Inspection | 2/4/2020 | 2/4/2020 | 2/6/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 1/20/2020 | 1/20/2020 | 1/21/2020 | | CANC |
Andy J. Long
|
|
|
site inactive
|
General Inspection | 1/3/2020 | 1/3/2020 | 1/3/2020 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/19/2019 | 12/19/2019 | 12/24/2019 | | PASS |
Andy J. Long
|
|
|
No activity. Site inactive for winter. Perimeter controls and stabilized access provided. No trackout or muddy runoff observed
|
General Inspection | 12/4/2019 | 12/4/2019 | 12/4/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity.
|
General Inspection | 11/19/2019 | 11/19/2019 | 11/19/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity.
|
General Inspection | 11/4/2019 | 11/4/2019 | 11/4/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity, pile not removed.
|
General Inspection | 10/18/2019 | 10/18/2019 | 10/18/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity. Cinder blocks placed on wattle to prevent people from driving over.
|
General Inspection | 10/3/2019 | 10/3/2019 | 10/3/2019 | | PASS |
Michael Zawacki
|
|
|
No new activity at site. Perimeter BMPs and stabalized entrance at site. Still has large pile of wood and concrete debris on site that needs to be removed.
|
General Inspection | 9/18/2019 | 9/18/2019 | 9/19/2019 | | PASS |
Michael Zawacki
|
|
|
Wattle installed along dirt perimeter. Cinder blocks in use to force people to gravel. Large debris pile still on site.
|
General Inspection | 9/3/2019 | 9/3/2019 | 9/3/2019 | | PART |
Michael Zawacki
|
|
|
No ESC issues at site. Rubbish pile still on site, no perimeter controls installed yet. Washout is on site.
|
Conference | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | DONE |
Andy J. Long
|
|
|
Met with RP to discuss upcoming schedule and corrections at site
- rubbish pile of vegetation and concrete chunks to be hauled away. - perimeter wattle to be installed has not yet been delivered, but has been re-ordered and installed this week. Access to the future driveway area should either have a construction rock entrance or barricade to prevent people turning around in the mud. - site will build new concrete washout for driveway work that will occur at 146 Skylark. - sweep loose dirt in gutter - install sediment protection on first receiving storm drain down hill
|
General Inspection | 8/13/2019 | 8/13/2019 | 8/13/2019 | | PASS |
Michael Zawacki
|
|
|
Backfill has been put back and/or removed, no more stockpile. No perimeter controls along road, sent message to RP to get some installed. No dirt in gutter or street at time of inspection.
|
General Inspection | 7/25/2019 | 7/25/2019 | 7/26/2019 | P | PASS |
Michael Zawacki
|
|
|
No new activity.
|
BMP Violation | 7/17/2019 | 7/18/2019 | 7/19/2019 | A | PASS |
Andy J. Long
|
|
|
Corrections made:
- Trash picked up, container empited - gutter swept, construction entrance installed. No trackout - stockpile now has staked in perimeter wattle installed around it.
Approved.
|
BMP Violation | 7/8/2019 | 7/11/2019 | 7/12/2019 | A | PART |
Andy J. Long
|
|
|
Some trash picked up. No new construction activity. No trackout. Dry conditions.
Wattle around stockpile needs to be trenched and staked as requested. Follow up scheduled Monday AM
|
Complaint Inspection | 7/8/2019 | 7/8/2019 | 7/8/2019 | P | FAIL |
Andy J. Long
|
|
|
Corrections needed:
Uncontained trash and improperly installed wattle observed. No trackout or discharges
- Properly install perimeter sediment control wattle arouund the stockpile - Collect all loose trash, place in container, and order trash pick up. - Remove bags of quickqrete and garbage from the dried washout pit
Walked site with Roth Home's Cleve. Verbal correction request. follow up scheduled for Thursday 7/11
|
General Inspection | 6/26/2019 | 6/26/2019 | 6/26/2019 | | PASS |
Michael Zawacki
|
|
|
Foundation poured, washout used. Wattle is surrounding backfill. Rock entrance installed and trash box on site.
|
General Inspection | 6/7/2019 | 6/7/2019 | 6/10/2019 | | PART |
Michael Zawacki
|
|
|
Crew on site bending rebar and setting forms for foundation. Lined washout on site. Large pile of backfill, close to road, needs some perimeter protection. Sent message and pictur to Cleve with Roth Homes.
|
General Inspection | 5/22/2019 | 5/22/2019 | 5/22/2019 | | PASS |
Michael Zawacki
|
|
|
Washout has been cleaned and new lined washout is installed. No new activity, waiting for dry weather to install forms and pour.
|
BMP Violation | 5/7/2019 | 5/7/2019 | 5/7/2019 | P | FAIL |
Michael Zawacki
|
|
|
Washout never cleaned. Parcel hold and reinspection fee issued for 124 Skylark, lot from where the washout came.
|
General Inspection | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | FAIL |
Michael Zawacki
|
|
|
Concrete truck and pump truck washed out onto lot when they were supposed to haul off. Talked to foreman on site and has excavator scheduled to come clean it up.
|
General Inspection | 2/8/2019 | 2/8/2019 | 2/8/2019 | P | PART |
Michael Zawacki
|
|
|
Requested washout hasn't been built. All other request completed, no current activity. No trackout.
|
BMP Violation | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | FAIL |
Andy J. Long
|
|
|
Corrections completed: - road has been swept - additional rock installed on entrance - dumped washout cleaned up
Corrections remaining:
- stake in perimeter wattles - build new leak-proof washout - pay re-inspection fee
|
BMP Violation | 1/24/2019 | 1/24/2019 | 1/24/2019 | P | FAIL |
Andy J. Long
|
|
|
Significant violation:
- concrete washout dumped at entrance of site. Evidence of slurry flow down hill towards gutter
Routine violation: - trackout from unmaintained construction entrance
Corrections requested to Kevin w/ Roth Homes - clean up dumped concerete to prevent further dumping - provide new lined and leakproof washout container or pit. - sweep up trackout - provide new rock and maintain and widen construciton entrance.
Compliance Date: Monday 1/28 2 PM
Re-inspeciton fee issued to permit. Must be paid and ESC inspeciton requested prior to compliance or parcel hold and addition investigation fees will be assessed to site.
|
General Inspection | 1/7/2019 | 1/7/2019 | 1/7/2019 | P | PASS |
Michael Zawacki
|
|
|
Concrete retaining walls completed. Old foundation footprint has been filled and leveled. SOme backfill stored on site. Rock entrance installed.
|
General Inspection | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | CANC |
Andy J. Long
|
|
|
|
General Inspection | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Andy J. Long
|
|
|
No muddy runoff. No trackout, workers staying off the mud. Perimter wattles installed. Some more wattles to be installed once more thawing has occurred.
|
General Inspection | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | PEND |
Andy J. Long
|
|
|
corrections in progress:
- permit sign posted - inlet bag installed on first receiving storm drain as requested. - construction entrance installed (needs more length) - perimeter wattles installed.
Corrections pending: - lined concrete washout or container onsite with sign - add additional wattle interval at low end of site
|
General Inspection | 11/8/2018 | 11/8/2018 | 11/8/2018 | P | FAIL |
Andy J. Long
|
|
|
Multiple violations.
- no required site preparation inspection - no permit sign posted. - no concrete washout pit or container onsite - no construction entrance
Corrections: - post ESC permit sign - review ESC site plan and install BMPs listed, in particular concrete washout, trash container, and perimter wattles on the down hill side of parcel.
Make corrections and schedule a site preparation inspection for next week.
|
General Inspection | 10/16/2018 | 10/16/2018 | 10/16/2018 | P | FAIL |
Michael Zawacki
|
|
|
Footprint from home was used as an unlined washout.
|
General Inspection | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PART |
Michael Zawacki
|
|
|
Demo complete, work began without site inspection. No controls along street to prevent runoff, lot height is above curb and street.
|