INSP-Final Inspection | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PASS |
Mark Scharfen
|
|
|
Corrections have been made. Eschuchons, heads fixed and signs placed. Passed
Todd Phone #: ###-####
|
INSP-Final Inspection | 5/8/2019 | 5/8/2019 | 5/8/2019 | A | FAIL |
Mark Stumbaugh
|
|
|
Escustechons missing or sprinklers low in rooms 109, 310, 120, 119, 110, 111. Tested interconnect with fire alarm panel-reports correctly. Forward flush is at 783 gallons.
Please call when in route Phone #: ###-#### >> Inspection requested via web by Kristin Dolan
|
INSP-Final Inspection | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | CANC |
Troy Cobbley
|
|
|
The project related fire alarm permit is still in Ready To Issue status. No inspection was performed. Will need to reschedule when ready. Please call ahead Phone #: ###-#### Inspection requested via web by Gary Gambino
|
INSP-Final Inspection | 4/24/2019 | 4/26/2019 | 4/26/2019 | A | FAIL |
Jim Page
|
|
|
Fire alarm system permit still in review, no device testing performed.
Todd Phone #: ###-####
|
INSP-Alarm Testing | 4/24/2019 | 4/26/2019 | 4/26/2019 | A | CANC |
Jim Page
|
|
|
Fire alarm devices under a seperate permit, this request is cancelled.
Todd Phone #: ###-####
|
INSP-Alarm Testing | 4/24/2019 | 4/25/2019 | 4/25/2019 | A | CANC |
Jim Page
|
|
|
Fire alarm devices under a seperate permit, this request is cancelled.
Todd Phone #: ###-####
|
INSP-Final Inspection | 4/24/2019 | 4/25/2019 | 4/25/2019 | A | PART |
Jim Page
|
|
|
Partial final inspection for overhead fire sprinklers complete, escutcheons are in place, no testing of fire alarm associated items due to fire alarm permit still in reviewed status.
Todd Phone #: ###-####
|
INSP-Final Inspection | 4/24/2019 | 4/24/2019 | 4/24/2019 | P | CANC |
Jim Page
|
|
|
Rescheduled for 25APR2019 per conversation with point of contact, this request is cancelled.
Todd Phone #: ###-####
|
INSP-Final Inspection | 4/9/2019 | 4/11/2019 | 4/11/2019 | P | PART |
Jim Page
|
|
|
Time requirements for dry system trip (3 systems total) test complete. Need as-builts submitted boefore final inspection.
Please call Todd Woods prior to arrival to coordinate inspection. Phone #: ###-#### Inspection requested via web by Kristin Dolan
|
INSP-Sprinkler Rough-in | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover. All rough in inspections for project complete.
Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/20/2019 | 2/21/2019 | 2/21/2019 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for reamining pipe in main entry hallway complete, approved for cover.
hallway // Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/14/2019 | 2/15/2019 | 2/15/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping above hardlids in corridor complete, corridors approved for cover.hallway // Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2019 | 1/31/2019 | 1/31/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for all overehad fire sprinkler piping witnessed, no pressure loss observed.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2019 | 1/30/2019 | 1/30/2019 | A | DONE |
Jim Page
|
|
|
24 hour air test on the 3 dry systems complete.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2019 | 1/29/2019 | 1/29/2019 | A | FAIL |
Jim Page
|
|
|
Hydrostatic test for wet system lost 4 psi during test, te-hydro is required.
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2019 | 1/29/2019 | 1/29/2019 | A | PART |
Jim Page
|
|
|
24 hour ait test started at 10AM with 40 psi on all three dry systems.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2019 | 1/28/2019 | 1/28/2019 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, inspection request will be rescheduled by contractor.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2019 | 1/28/2019 | 1/26/2019 | A | CANC |
Jim Page
|
|
|
Dry system air test Phone #: ###-#### >> Inspection requested via web by Shane Lesteberg Inspection cancelled from web by: Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2019 | 1/25/2019 | 1/25/2019 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for east side area B complete, area inspected approved for cover.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2019 | 1/25/2019 | 1/24/2019 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Shane Lesteberg Inspection cancelled from web by: Shane Lesteberg
|
INSP-Sprinkler Rough-in | 1/18/2019 | 1/22/2019 | 1/22/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for east side area B complete, area inspected approved for cover.
Cover inspection. Contact Nick Smith with time. Thanks! Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in | 1/2/2019 | 1/3/2019 | 1/3/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting for remaining section of area C complete, approved for cover.
Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 12/26/2018 | 12/27/2018 | 12/27/2018 | A | CANC |
Jim Page
|
|
|
Tenting has not been installed for area requested for cover, inspection cancelled per point of contact.
Todd Phone #: ###-####
|
INSP-Sprinkler Rough-in | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | PART |
Jim Page
|
|
|
Previously noted items for area C complete, area C on the fire sprinkler drawings approved for cover.
Site Contact - Nathan Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 12/6/2018 | 12/10/2018 | 12/10/2018 | A | FAIL |
Jim Page
|
|
|
Numerous heads throughout attic space are blocked, correct blockage issue. Numerous areas in attic space has no sprinkler protection. Sway bracing attached to truss webbing needs to be relocated to top cord, bottom cord or verticals. Need access to overbuilds to verify upright protection. Correct hangers on CPVC armovers that are over 6 inches.
CI sprinkler foreman - Nathan Gregory Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in | 11/26/2018 | 11/27/2018 | 11/27/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located in west wing complete (from fire doors west), area inspected approved for cover for both wet and dry system. Noted that hydrostatic tests can only be completed if the inside building temperature is maintained at 40 degrees or above with an un-interruptable heat source. If temperature cannot be maintained above 40 degress at all times then antifreeze will be required for hydros. If heat is shut off to building and the pipe is exposed to below 40 degrees after a hydro is completed then a new hydro will be required to verify intregrity of the system.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2018 | 11/19/2018 | 11/19/2018 | A | FAIL |
Jim Page
|
|
|
Sway bracing attachments need to be a minimum of a 4X, attachments for attic mains are attached to 2X4, not a 4X4 or larger. Fix blocked head as noted. Move hangers that are to close to the attic heads.
Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in/Hydro | 11/14/2018 | 11/15/2018 | 11/15/2018 | P | FAIL |
Jim Page
|
|
|
No stamped city approved drawings on site, need city approved drawings to be onsite at all times.
Contact Pablo at ###-#### Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|
INSP-Sprinkler Rough-in | 11/14/2018 | 11/15/2018 | 11/15/2018 | P | FAIL |
Jim Page
|
|
|
No stamped city approved drawings on site, need city approved drawings to be onsite at all times.
Contact Pablo at ###-#### Phone #: ###-#### Inspection requested via web by Shane Lesteberg
|