Permit Information
Permit NumberESC18-00264
StatusFinaled
Name MARTY PIERONI
Site Address 182 E SHERMAN ST
Project NameFullmer residence
Customer Number 
ePlanReviewNo
Description
Grading for single family home, good for GRD and BLD permit if same Responsible Person. Rock construction entrance is required; fiber rolls should be installed along counters at toe of slope. Protect down hill stormwater features from sediment. Preserve vegetation around home footprint. Site preparation inspection is REQUIRED.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection10/4/201910/4/201910/4/2019 CANC
DetailsMichael Zawacki
DOC - Permit Finaled10/4/201910/4/201910/4/2019PPASS
DetailsMichael Zawacki
Owner is also building home above. Will continue to monitor and have repaired if needed. Site is stable.
General Inspection9/19/20199/19/20199/19/2019 CANC
DetailsAndy J. Long
General Inspection9/4/20199/4/20199/4/2019 CANC
DetailsAndy J. Long
General Inspection8/20/20198/20/20198/20/2019 PASS
DetailsAndy J. Long
Landscaped and revegetated. DI bags are still installed at Shernan & Mockbee.
General Inspection8/5/20198/5/20198/5/2019 PASS
DetailsMichael Zawacki
Regrowing, will final permit when I see how lot handles water.
General Inspection7/19/20197/19/20197/19/2019 PASS
DetailsMichael Zawacki
Revegetation in progress.
General Inspection7/4/20197/4/20197/5/2019 CANC
DetailsAndy J. Long
General Inspection6/19/20196/19/20196/20/2019 CANC
DetailsAndy J. Long
General Inspection6/4/20196/4/20196/4/2019 PASS
DetailsAndy J. Long
Home completed. Revegetation. Need to remove sediment controls from storm drain at Sherman and Mockbee. Adajacent house still not stabilized.
General Inspection5/20/20195/20/20195/23/2019 PASS
DetailsAndy J. Long
General Inspection5/3/20195/3/20195/3/2019 PASS
DetailsMichael Zawacki
Growing, will monitor.
General Inspection4/18/20194/18/20194/19/2019 PASS
DetailsMichael Zawacki
Site in good shape. Will continue to monitor growth. Will need to look at site drainage to make sure no erosion or sediment will cause issues. Permit will remain open unti home next door also stabalized so drainage can be evaluated and work with both contractors as needed.
General Inspection4/3/20194/3/20194/3/2019 PASS
DetailsAndy J. Long
Landscaped. Open to check that slopes are stabile and will complete vegetation. May require removal of one of the DI bags installed on Sherman @ Mockbee
General Inspection3/19/20193/19/20193/19/2019 PASS
DetailsMichael Zawacki
No ESC issues. Will monitor for stability and any runoff issues.
General Inspection3/4/20193/4/20193/4/2019 PART
DetailsMichael Zawacki
No runoff from site.
Hot tub pad was built on hill with bridge to roof deck. Will need to forward to other inspectors to make sure work is approved.
General Inspection2/13/20192/13/20192/13/2019 PASS
DetailsMichael Zawacki
Site is mostly stabalized, no runoff.
General Inspection1/28/20191/28/20191/28/2019 PASS
DetailsMichael Zawacki
All exposed areas have been sodded or hydroseeded. Driveway drain exposed after crossing share drive. Will monitor until completely stabalized.
General Inspection12/25/201812/25/201812/26/2018 PASS
DetailsMichael Zawacki
Hillside vegetation and landscaping installed. No current runoff issues. Will continur to monitor.
General Inspection12/7/201812/7/201812/12/2018 PASS
DetailsAndy J. Long
WIP on interior. Driveway is paved. Bond issued for landscaping and drainage.
General Inspection10/9/201810/9/201810/9/2018PFAIL
DetailsMichael Zawacki
Rilling occurring on hillside above driveway and a channel has formed along driveway. Wattle along bottom of drive is slowing and diverting water, damaged in places. flow is being concentrated and diverted into rock channel, water coming up onto road through parking area and carrying dirt to storm drain at sherman and mockbee.
General Inspection10/2/201810/3/201810/4/2018APASS
DetailsAndy J. Long
No sediment runoff down Sherman observed during rainfall inspection. Some of driveway is now paved and landscaping. No corrections at this time.
BMP Violation9/27/20189/27/20189/27/2018PPEND
DetailsAndy J. Long
GC Jeff called to state that his counterpart will enroll in RP class and become certified and designated RP for their projects on Sherman and Highland View.
BMP Violation9/26/20189/26/20189/26/2018PFAIL
DetailsAndy J. Long
Invalid RP listed for project. Request to homeowner GC to get certified.
General Inspection8/23/20188/23/20188/23/2018PPASS
DetailsMichael Zawacki
Hillside is exposed,some wattle along bottom. Little bit of dirt coming off driveway. Site is clean
Conference7/11/20187/11/20187/11/2018ADONE
DetailsAndy J. Long
Reviewed hillside erosion control installation of straw wattles with homeowner and builder Jeff. Wattles must be trenched and staked every 4-5 feet and installed along slope contours.

WIP on framing and also landscaping. Landscaping and irrigation lines are being worked on. Once irrigation is in (before end of July), slopes will be hydroseeded with a fescue grass and trees. After irrigation is in and before seeding, perimeter wattles and slope interupting wattles must be installed.

No trackout, discharges, or ESC violations occuring. Permit sign posted. Just need to continue to focus on stabilizing hillsides.
BMP Violation6/25/20186/26/20186/26/2018APEND
DetailsAndy J. Long
No new hillside erosion controls installed. Landscaping in progress. Will follow up with BMP site map to review with RP.

Trackout has been cleaned up, no discharges.
BMP Violation6/21/20186/22/20186/25/2018PCANC
DetailsAndy J. Long
General Inspection6/20/20186/20/20186/21/2018PFAIL
DetailsAndy J. Long
Permit sign posted, some wattles installed around site. GC-RP Jeff on site.

Minimal stabilzation and erosion controls (slope interupting wattles, perimter wattles) on slopes below home and around unfinished driveway. Road has had sediment runoff and sandy trackout.

Correction:
- sweep up trackout at entrance, coordinate with adjacent site to clean up accumulated sediment around storm drain at bottom of hill
- review ESC plan and install wattles and other controls.
- use rock check dams instead of wattle check dams to slow runoff from driveway and trap sediment

Jeff agreed that slopes need more control and that next week landscaping and BMP installation will occur. Will review ESC site plan on site wth Jeff on Friday and check for clean up.

General Inspection6/6/20186/6/20186/6/2018PPASS
DetailsMichael Zawacki
Builder cleaned all runoff from driveway and road. Site is repaired, channels have been fixed that were running along driveway. Foundation work in progress, washout is within foundation footprint.
Random Inspection5/31/20185/31/20185/31/2018PPEND
DetailsMichael Zawacki
Owner on site. There was a washout from driveway down road. Was being cleaned while on site. Owner will update BMPs and get everything clean before end of day.
General Inspection5/2/20185/2/20185/2/2018PPASS
DetailsMichael Zawacki
Retaining wall in place, driveway and landscaping started. Concern of runoff if we have large rain event, soil is sandy and very loose. Trench along perimeter should intercept any runoff, driveway may act as channel.
General Inspection3/29/20184/10/20184/10/2018PPASS
DetailsAndy J. Long
WIP on hillside erosion controls. Check dams installed along unfinished driveway. DI bags down hill removed to capture all runoff from site in Sherman Hollow stormwater system.
Tracking Control3/27/20183/28/20183/29/2018APASS
DetailsAndy J. Long
Trackout cleaned up. Permit sign posted. Crews onsite.

Reviewed next step of hillside erosion installment and placement of check dams on the driveway to slow velocity of runoff.

Approved for now

Site Preparation2/28/20182/28/20182/28/2018PPASS
DetailsMichael Zawacki
Call to meet there // Jeff Phone #: ###-####
Working on wattle installation, will put in construction entrance when grading begins. Plans on keeping most excavated material for landscape use.